Green Tribunal orders an interim stay on Mantri’s Bellandur project

Following the NGT stay on the multicrore project coming up on Bellandur lakebed, the High Court has decided to adjourn the case to July 18, 2014.

The National Green Tribunal (NGT) has ordered an interim stay on the mega-project coming up on the land between Bellandur and Agara lakes, in Bengaluru. This was in response to a petition filed by The Forward Foundation, Bangalore, Praja RAAG, Bangalore and Bangalore Environment Trust.

The stay order issued on April 16, 2014, states that “the Tribunal is satisfied that there is a substantial question connected to and concerned with environment which has got to be enquired into.”

It observes that “the construction activities are carried on in an extent of 13,50,455 m2 in an area of 80 acres in between two lakes and if permitted, the rapid encroachment being made would cause, no doubt, damage to the water course situated in between the two lakes impeding flow of rain water into Bellandur lake, the largest freshwater body in Bangalore and hence, an immediate intervention by the Tribunal by granting an order of stay of the construction activities becomes necessary.” The Tribunal has stayed further construction activities by the Mantri Techzone Private Limited and Core Mind Software and services Pvt Limited, until further orders.

The petition had questioned the project on the grounds of environmental impact by the project.

HC decides to observe NGT proceedings

In a hearing that took place on April 25, 2014, the counsel for one of the respondents brought to the notice of the High Court that a stay has been ordered by the National Green Tribunal. However, the petitioner in Bellandur-Agara mega project, Namma Bengaluru Foundation, clarified the High Court that the petitioners for National Green Tribunal were different from the petitioners in the High Court.

Following this, the High Court decided to wait and watch the NGT proceedings. As the next Tribunal hearing has been scheduled on July 15th, 2014, the HC bench decided to list the case on July 18, 2014.

Related Articles

Citizens protest against multicrore project coming up in Bellandur
Bellandur wetland multicrore project: KIADB orders suspension of work

Comments:

  1. NITIN SESHADRI says:

    The shocking aspect here is that one of the project proponents appears to be recklessly proceeding with work inspite of the NGT weighing in. I hear that one of the petitioners in the NGT matter was forced to file a police complaint before the ACP Madivala against one of the project promoters. Shameful behaviour !

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Blocked Kovalam-Nemmeli wetland channels risk disaster for South Chennai; Conservationists urge action  

Barriers built for the Mamallan Reservoir block Buckingham Canal water flow, vital to keep the wetland alive, avoid floods and sustain fishing families.

In Chengalpattu district, the main water channels of the Kovalam-Nemmeli coastal wetland, which drains a catchment of more than 270 square kilometres, have currently been blocked. Barriers that obstruct water flow have been built across Chennai's Buckingham Canal at three places: Thiruvidanthai-Vadanemmeli, near the Nemmeli-Thiruporur bridge, and Saluvankuppam. Earlier, we explored how the Mamallan Reservoir causes serious damage to the wetland’s ecology and how fishing livelihoods are affected. Field investigations by the Wetland Conservation Network have recorded the blockages preventing tidal exchange in the Buckingham Canal.           According to officials, these barriers were put up to enable construction of the Mamallan…

Similar Story

Explained: How Mumbai is losing its tree cover to infrastructure projects

Mumbai's landscape is changing with big infra projects. Experts suggest better use of government plots and improved street design to retain green cover.

Long before Mumbai’s relentless summer even began this year, the city was already simmering. In March, Mumbai was hit by a severe heatwave, with the temperature reaching a five-year high of 40° Celsius. As rapid urbanisation and a flurry of infrastructure projects replace dense tree cover with steel and mortar, heatwaves seem to have gone from being rare occurrences to an annual threat.   The Mumbai Metro Rail Corporation Limited (MMRCL) cut a whopping 3,093 trees in Aarey Colony to make way for Mumbai’s Aqua Line ( Metro 3). For environmentalist Stalin Dayanand, this is not just a temporary problem.…