For residents of Gunjur, Panathur and surrounding neighbourhoods in east Bengaluru, the promise of better road connectivity has remained elusive for nearly two decades. The proposed 150-foot-wide Comprehensive Development Plan (CDP) Road, intended to connect Gunjur to the Outer Ring Road (ORR) via New Horizon College, was included in Bengaluru’s Revised Master Plan (RMP) 2015, approved in 2007. Yet, in 2026, a crucial stretch of the road, situated directly inside the Panathur Tree Park, is still incomplete.
While the CDP road was proposed in 2007, a crucial 400-500 metre stretch of the road has already been used to develop the Panathur Tree Park by the Forest Department as part of the Centre’s Nagar Van Yojana 2020. Today, the Greater Bengaluru Authority (GBA), responsible for executing the CDP road projects, has identified 5.4 acres in Belthangady, Dakshina Kannada as compensatory land for the Forest Department.
However, this tussle with the Forest Department is only one of the decades-long obstacles that have stalled the road project. Previously, land had to be acquired from a Karnataka Power Transmission Corporation Limited (KPTCL) substation, 20 private properties, and two temples. Today, the road is presented with a new problem of a railway overbridge whose detailed project report has yet to be formulated.
The Gunjur CDP road is one of the 85% of CDP roads that continue to remain on paper even after two decades of its proposition — revealing a larger problem of interdepartmental coordination and a lack of implementation of proposed policies in urban Bengaluru.
The impossible choice between ecology and mobility
GBA’s prolonged delay in implementing the CDP road has resulted in confusion for the public and interdepartmental conflict with the Forest Department.
The story of this delay begins in 2015 when the erstwhile BBMP (Now GBA) began the land acquisition process for the CDP road and subsequently approached the Forest Department seeking land. The Forest Department claimed that the stretch of land required for the Gunjur CDP road was designated as forest land in 1987 and had undergone decades of afforestation before they were even approached.
They also secured CSR funding to develop the Panathur Tree Park, whose first Phase is now open to the public. Concerned over destroying parts of the forest and the Tree Park for the CDP road, the Forest Department suggested alternatives including an elevated corridor or an underpass, to preserve the forest’s continuity.
These options would be economically unfeasible, and hence discussions with the GBA pivoted to dividing the tree park and providing compensatory land to the Forest Department. The current proposal would take a strip of forest land approximately 25 metres wide and 400–500 metres long, dividing the larger green space into two sections.
Authorities have said that the tree park will continue on either side of the road. Proposals involving alternative sites for compensation, including Mandur and Anekal, were rejected before 5.4 acres of land in Belthangady, Dakshina Kannada, was finally agreed upon.

Effect on the tree park
However, this system of compensation raises new questions about the suitability of the alternative land, along with the relevant approvals from authorities in Dakshina Kannada, which have not been clearly documented and made public. Moreover, the government hasn’t made public the number of trees that have to be felled for the CDP road within Panathur Tree Park. Nor is there any information on the disturbance this may cause to the two-decade long ecosystem that has naturally developed in the area.
This reeks of poor coordination between government departments. It is unclear how a road proposed in 2007 was allowed to cut through a tree park developed years later, forcing the GBA and the Forest Department to confront their competing objectives after the fact.
As a result, residents of the Panathur-Gunjur area now face an impossible choice between two public needs, mobility and ecological protection, both of which should have been planned together much earlier.
The new obstacle of the railway overbridge
Even if the forest-related issues are resolved, another major obstacle remains which is the Bellandur Railway Overbridge (ROB) that cuts across the Gunjur CDP Road.
Karnataka Rail Infrastructure Development Enterprises (K-RIDE) has been carrying out its Doubling Project between Baiyappanahalli and Hosur that is predicted to significantly improve rail capacity. Part of this project included a new station at Bellandur road and expansion of 5 railway tracks. The railway tracks have to now be integrated with existing road networks and proposed road projects. One of the railway bridges from this project cuts across the proposed Gunjur CDP road.
For the past three years, railway authorities have gone back and forth on whether to build a Railway Overbridge (ROB) or a Railway Underbridge (RUB), both of which require specific planning and coordination from the GBA. Moreover, the GBA delayed sharing road plan details with K-RIDE, essential to get Southern Railway approval before construction could begin.
Ambiguity regarding project report
According to a 2025 Lokayukta complaint filed by the author, although an ROB was finalised for the Gunjur CDP road railway crossing, the GBA failed to award the Detailed Project Report (DPR) tenders it floated in both 2024 and 2025.
Authorities must also check whether the bridge can accommodate a 5-track railway expansion, especially evaluating space for bridge pillars and acquisition of private land.
While the author had inquired why the plan for the ROB cannot simultaneously be developed with the CDP road, the GBA authorities simply shrugged and said that it would be a waste of time if the forest clearances do not come through. There is a chain of dependencies where one department is made to wait for another, and a clear lack of a central coordination mechanism that can solve what seems to be a simple problem of communication.
Read more: Bengaluru’s Peripheral Ring Road: Traffic relief or ecological disaster?
The road that only exists on paper
The Gunjur–Panathur CDP road is intended to improve connectivity between the neighbourhoods and the Outer Ring Road (ORR). This expectation, however, has not materialised in reality.
The surrounding area has not waited for the road. High-rise apartments, technology parks, schools and colleges have expanded, increasing the number of people dependent on a limited network of roads. The proposed CDP road has been used to demonstrate future connectivity when seeking planning permissions for developments. It has also featured in builders’ marketing material.

Residents feel bottlenecked by the delay in constructing the CDP road, and with the growing number of development projects. This area is already subject to long traffic jams, poorly connected roads and commutes that can stretch to 60–90 minutes for a distance of just five kilometres. School buses get stuck in traffic, and people who bought homes closer to their workplaces to save time find themselves struggling with the infrastructure they expected would improve.
With the delay, the road may not be able to solve all of the residents’ commute issues, considering the rapid development in the area. Panathur-Gunjur area is also witnessing groundwater depletion and soon, residents predict, that many of the high-rises will have to depend on water tankers for their water supply. The increase in water tanker movement along this route can contribute to traffic congestion in the area.
This entire delay by the GBA reflects a lack of prior planning, inter-departmental coordination and phase-wise implementation plan for all of Bengaluru’s development projects.
A plan to implement all RMP projects in Bengaluru
The delay in the construction of the Gunjur CDP road highlights the need for a framework to ensure timely, coordinated implementation of infrastructure projects proposed in Bengaluru’s Revised Master Plan (RMP). The following legal and administrative measures could help prevent similar delays:
- Demand implementation schedules: Section 12 of the Karnataka Town and Country Planning (KTCP) Act addresses the stages of Master Plan implementation. Authorities should clarify timelines for major infrastructure projects.
- Initiate land acquisition early: Section 69 provides for land acquisition for public purposes. Early identification of land requirements could prevent disputes from delaying projects years later.
- Use Transferable Development Rights (TDR): Section 14A provides for development rights in specified circumstances involving land surrendered for infrastructure, potentially reducing acquisition disputes.
- Challenge administrative delays: Article 14 and judicial review may provide grounds to challenge arbitrary inaction and seek reasoned decisions or time-bound processes.
- Use the RTI Act: Residents can seek DPRs, land surveys, acquisition records, departmental correspondence, meeting minutes and explanations for delays.
- Scrutinise development approvals: Section 14 concerns conformity with the Master Plan and applicable regulations. Approvals that disregard relevant infrastructure constraints may warrant legal scrutiny.
- Review alternative-alignment decisions: Decisions overlooking feasible alternatives without adequate justification may be challenged through judicial review, depending on the circumstances.
- Initiate forest and environmental clearances early: Early coordination can identify constraints and alternatives before they become project bottlenecks.
What residents recommend
A dedicated policy should convert every major infrastructure project in an approved Master Plan into an Implementation Project with:
- A unique project ID, nodal department and designated Project Nodal Officer.
- A defined scope, DPR timeline and technical feasibility assessment.
- A land acquisition plan, statutory-clearance matrix and funding plan.
- Clear interdepartmental responsibilities and an implementation schedule.
- Measurable milestones, completion dates and periodic senior-level monitoring.
- Public disclosure of project status and progress.
For a growing city like Bengaluru, robust implementation mechanisms and accountability are essential. The Gunjur CDP road should serve as a case study for the absurd lack of coordination that has led to confusion and chaos in east Bengaluru.