Drain work submerges quality of life

If a development project on a single road could completely destroy quality of life for residents, it must be this one: BBMP's project at JP Nagar's Puttenahalli Main Road.

The problems of JP Nagar do not end with the underpass mess on the 24th Main, 15th Cross, in fact the residents are facing inconvenience even because of another major construction in that area. This time it is the construction of the drain line that is the cause of concern for the residents.

Compound wall Passway, JP Nagar, Bengalooru

Compound walls broken down and used as pass ways (Pic: Supriya Khandekar)

"There is a fight for getting daily necessities, reaching the grocery shop or the bus stand is a big task. The vegetable vendors also do not come regularly," says Sujatha M, who also lives on one side of the dug up road. She is a housewife and a mother of two kids, she also explained that the dust and noise add to the problem caused due to the digging. Along with her all the residents living in the area remain clueless about the completion dates for the project as there is no board mentioning such details.

The Puttenahalli main road (which leads to the Puttenahalli lake) has been dug up. The whole road is seeing the construction of an underground drain that connects to the Puttenahalli lake. The drain line there is under construction from the past few months.

People living on the either side of the main road find it difficult to reach the other side. In fact walking on the main road itself is next to impossible. Vehicles cannot come that way, if anyone wants to be on the main road then walking is the only way. While even walking is not that easy. One has to use the broken compound walls of the houses on the either side of the road as a passage to reach the desired location.

Construction reached on either side of the houses, JP Nagar, Bangalore

Construction has reached the houses on the either side of the road (Pic: Supriya Khandekar)

The dug up road that has left only mud, water, huge construction material, trucks and cranes all over the place. The digging has reached the houses on the either side of the road and most people have vacated the place. Others however are using these vacant houses by making ways from their compounds and even breaking down the compound walls.

While one side of the road has been temporarily cemented it does not look strong to bear the monsoon. Even on these places the rain water has entered the nearby houses. Along with that the same road has one private clinic still running and the patients have to sit just next to the dust and mud of the construction work.

Even patients on the other side of the road cannot reach the clinic. The whole area flooded because of the rains the earlier night. Some people expressed similar concern about not able to reach the nearest doctor. There are two play schools as well where kids cannot reach.

Clinic near construction, JP Nagar, Bengaluru

S Suresh, in his early forties, stays on the side which is now temporarily cemented. He said, "It took four months for this side to get a temporary road but that side seems to be taking longer due to the rains. There is no other way to walk on this road but to break the compound walls. Even doing that does not work if the place is flooded."

The people who are working on the project are also equally affected by this. Nagarjuna who works on the site said that it is sad to look at people who cannot move around, while he adds that because of monsoon the work will take longer to finish.

Dug up road for drain line, JP Nagar, Bengalooru

Dug up road for drain line (Pic: Supriya Khandekar)

"We stop working in the evening and after a heavy shower we cannot start till late the next day as the whole place is flooded," he explains. Nagarjuna has come from Andhra Pradesh and stays in a temporary blue plastic sheet tent on the site itself. His wife also works on the same site and his two daughters play around.

The BBMP engineer-in-chief AK Gopalaswamy was not available for comment after repeated attempts.

Addendum
On 24 July, Chikkarayappa, Chief Engineer (SWD), BBMP said that the construction will be complete by September this year.

Comments:

  1. Deepa Mohan says:

    Well-written article, Supriya! good description of the immense hardships citizens have to face.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Chennai Councillor Talk: Rathika aims to resolve long-standing patta issues in Ward 174

Flooding and sewage overflow are major problems in Chennai's Ward 174. Here is how Councillor Rathika is addressing them.

Like many first-time councillors in Chennai, Ward 174 Councillor M Rathika entered grassroots politics because of the reservation for women in urban local body elections. Ward 174 was one of the wards reserved for women (general) in the 2022 local body polls. Coming from a family with a political background, she had been working on the ground with her brother for years. When the elections were announced, she was given a seat to contest and won by around 5,000 votes. Ward 174 Name of Councillor: M Rathika Party: DMK Age: 44 Educational Qualification: Undergraduate Contact: 9445467174 / 9566165526 Ward 174…

Similar Story

City Buzz: Pollution chokes Delhi, north | Report lauds free bus rides for women

Other news: Successful reduction in road crash fatalities in Punjab, flood mitigation in Chennai and alarming annual rise in cybercrimes.

Delhi air 'severe plus'; North India reels under air pollution Delhi's air quality has been going from bad to worse since Diwali, and the air quality index plummeted to hit 'severe plus' category, at 457 on the evening of November 17th. At 8 am on Monday, November 18th, data from the Central Pollution Control Board pointed to a daily average AQI of 484. After days of hovering at severe levels (AQI of 400-450) it crossed the threshold, prompting the Commission for Air Quality Management to invoke implementation of Stage 4 of the Graded Response Action Plan, or GRAP, across the National…