The heated protests of July appeared to come to nought at the High Court on November 30th, when the latter ruled to allow BBMP proceed with widening at the cost of old growth trees.

In the Sankey road widening case, the High Court ruled in favour of BBMP on Wednesday, November 30th. BBMP’s contention that it had the authority to cut off scores of old growth trees on Sankey Road was upheld.

The petitioners – five individuals and residents’ association

Malleswaram Swabhimana Initiative – had argued that BDA had not indicated widening of the road in its draft Revised Master Plan 2015 (RMP) and hence public had no chance to object to the widening. BDA’s lawyers however argued that widening of the road to 30 metres was indicated in the 1984 and 1995 master plans and that public could have objected to the widening at the time. BBMP draws it road widening projects from BDA’s master plan.

[Edit]
Residents writing on a white board during a silent protest in the evening of July 1st, after 17 trees were cut down. File pic: Yogaraj Mudalgi.

"More than 200 trees maybe cut along the entire stretch for this. We did argue about the environmental cost of the project, but court did not consider it," says Meenakshi Bharath, one of the petitioners. Meenakshi is a well known civic activist in Malleswaram and also ran for city council from there in 2010 on the Lok Satta party ticket.

Matters came to a head in July this year when BBMP cut 17 trees in the Malleshwaram area of Sankey Road, irking citizens, and setting of a wave of protests. Police manually ejected protesters amidst heated arguments. Some citizens were arrested, including a retired BBMP official who joined cause. Several college students were detained.

The dispute then moved to the High Court after the latter issued a stay with two trees standing.

At the court, the point of contention was whether the RMP had to be a complete document in itself with all details, or whether it could be seen as a continuation of the previous CDPs (and hence would not need to mention all details). The judgement was based on this technicality;
it said that RMP could be seen as a continuation of the earlier CDPs.

Currently BBMP plans to widen the road to 27 m.

For the time being, the ruling will be seen within government as victory for pressing on with its roadwidening projects, trees or no trees. The court ordered that widening of the entire road from Yeshwantpur to Cauvery junction should be completed within a year.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

How Project Mumbai helped divert 70 tonnes of plastic from landfills

Volunteers of Project Mumbai promote sustainable waste management practices, inclusivity and mental health initiatives.

Mumbai is a city of contrasts — while it thrives as India’s financial capital, it also struggles with environmental challenges and urban governance issues. A growing section of its population is also grappling with mental health issues caused by urban stress. The beginning of Project Mumbai Project Mumbai was started in 2018, as a citizen-driven, not-for-profit initiative dedicated to making Mumbai a better place to live, work, and play. With a firm belief in collective responsibility, we operate on a unique Public-Private-People model, ensuring that citizens, corporations, and local authorities work together to create meaningful change. What started as a…

Similar Story

City Buzz: Tree felling in Kancha Gachibowli halted | Smart Cities Mission incomplete…and more

Other news: E-bikes in Mumbai, artificial rain in Delhi to combat air pollution, and poor water management aggravates GBS infections in Pune.

Supreme Court halts tree felling in Hyderabad's Kancha Gachibowli The Supreme Court has intervened to halt the felling of trees in Kancha Gachibowli, Hyderabad, following widespread protests. The court issued an interim stay on deforestation activities across 400 acres of land near the University of Hyderabad campus, citing ecological concerns and the presence of scheduled animal species. The Telangana High Court had earlier paused development plans for the land, which is earmarked for IT infrastructure by the Telangana Industrial Infrastructure Corporation (TGIIC). Students, environmental activists, and conservationists have opposed the government's plans, arguing that the land is ecologically sensitive and…