KIADB starts land acquisition for Metro Phase – II

Metro Phase II work in Bangalore takes off, with KIADB starting the land acquisition process. Actual work is supposed to start by January 2014.

Metro Phase II work takes off, with KIADB starting the land acquisition process. File pic.

Karnataka Industrial Areas Development Board  (KIADB) conducted the first hearing for the owners of properties to be acquired for alignment of Metro Phase II on 4 September, 2013. The properties notified were for Ragigudda and Silk Board stations, on RV Road- Bommasandra line.

Metro is all geared up to start the Phase-II work by January 2014. To achieve this target, the process of identification of properties was already initiated by KIADB officers deputed to the Metro, in the last few weeks.

In the first hearing, only the properties required for building Ragigudda and Silk Board stations received notification. KIADB  issued notifications to 55 properties out of which 10 properties had been awarded by BBMP to poor people, way back in 1980’s.

Property owners resign to their fate

Only 20 owners of properties in question were present at the hearing held at the KIADB office, in Nrupathunga Road. Most of them were concerned over losing their property partially. Most of them were wondering what will they do with the partial land. They wanted BMRCL to take entire land and or compensate them with good amount.

Mangala M (identity changed on request), one of the owners of properties awarded to poor by the BBMP, works as a labourer at a private office. She said: “Money has no value to us, if we are not able to acquire land in same area or anywhere else in Bangalore. The property prices are all time high. Where shall we go? We request the Metro to give us some land somewhere nearby to re-settle.”

“On a blank white sheet of paper, objections have been recorded in an indecipherable handwriting.KIADB land acquisition officers  took our signature on it,” says Anand M, Mangala’s husband, who works as a labourer in a private company.

When Anand questioned this, the KIADB officer told him it was exactly the same that he objected.  He  says, “I did not sign it,. So I was asked to bring an objection letter.”

Majority of people who attended the hearing were looking for good compensation, as everyone seemed to accept that the project was final and they could not afford to fight it.

Special Land Acquisition officer, Ravi Tirlapu, told Citizen Matters: “No serious objections have been raised by the people. Many of them have sentimental attachments to the property. A good compensation will be given to the people depending on the market value.”

‘Land bill might not be BMRCL-friendly’

Neither the BMRCL nor the KIADB are open about the compensation amount. However they assure that a fair market value will be taken into consideration. Public Relation Officer, Chavan said, “The prevailing market value will be considered at the time of determination of compensation based on the fair market value.”

Residents are looking for the Land Acquisition BILL 2012 to get implemented, in the hope that it might provide some respite to them, as it has been termed as citizen-centric.

Tirlapu says, “If the bill gets passed as an act, it will be difficult to comply as it is citizen-oriented. It will be additional burden on the government and shall not be friendly.”

What next?

Process for the land acquisition will follow the terms of KIADB Act-1966 and General Land Acquisition Act-1894. Compensation amount will be decided by the Krishnappa Committee. Krishnappa is a former revenue secretary who is an advisor to BMRCL.

All the objections will be taken to BMRCL who will in return file their reasons behind the said acquisition. If the KIADB officer finds it necessary, the properties will be acquired.  

“99% such objections do not lead to any changes. People are aware of it. It is not an easy task to change the alignment once decided, as it will again be required to go to HPC of the Central government. A compensation very close to market value will be awarded,” said Tirlapu.

The land acquisition to be started in April 2013 wasn’t allowed by the Election Commission because of the Code of Conduct. The realignment controversy too contributed to the delay in execution of Phase II.

Related Articles

Metro Phase-II victims, intimidated by surveyors, write to BMRCL
BBMP plans to merge Silk Board elevated road with Metro line
Why Narayana Hrudayalaya wants Metro, while Jayadeva Institute doesn’t

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

How OMR residents strive for better last-mile connectivity and improved public transport

Residents of Chennai’s OMR push for bus and metro links; FOMRRA’s survey highlights poor last-mile connectivity and urges MTC to expand services.

As commercial development along Old Mahabalipuram Road (OMR) has surged, reliable public transport has become essential. Yet, daily commuters, labourers, office workers, college and school students, and Resident Welfare Association (RWA) staff continue to grapple with limited access to Metropolitan Transport Corporation (MTC) buses. For many, reaching bus stops on the main road is a daunting task, especially since interior localities remain underserved and private operators like share autos rarely venture into these areas. The absence of adequate bus stops and the restricted MTC service forces residents into long, difficult journeys. The worst-affected by this lack of last-mile connectivity are…

Similar Story

Civil society groups push for cleaner, safer and accessible transport in TN cities

The Tamil Nadu Urban Mobility Charter 2031 urges more buses, EV adoption, and safer streets to make cities equitable and people-first.

A collective of active citizens, non-governmental organisations, sustainable transport experts, and other stakeholders has called for strengthening the public transport network in Tamil Nadu's cities, making it accessible to all and creating low-emission zones across urban centres. The Sustainable Mobility Network (SMN), a coalition of over 30 civil society organisations across India, has released the 'Tamil Nadu Urban Mobility Charter 2031', a comprehensive roadmap urging political parties and governments to put sustainable mobility at the heart of the state’s development agenda. The Charter was shaped through a multi-stakeholder roundtable convened by ITDP India, Citizen consumer and civic Action Group (CAG),…