KIADB starts land acquisition for Metro Phase – II

Metro Phase II work in Bangalore takes off, with KIADB starting the land acquisition process. Actual work is supposed to start by January 2014.

Metro Phase II work takes off, with KIADB starting the land acquisition process. File pic.

Karnataka Industrial Areas Development Board  (KIADB) conducted the first hearing for the owners of properties to be acquired for alignment of Metro Phase II on 4 September, 2013. The properties notified were for Ragigudda and Silk Board stations, on RV Road- Bommasandra line.

Metro is all geared up to start the Phase-II work by January 2014. To achieve this target, the process of identification of properties was already initiated by KIADB officers deputed to the Metro, in the last few weeks.

In the first hearing, only the properties required for building Ragigudda and Silk Board stations received notification. KIADB  issued notifications to 55 properties out of which 10 properties had been awarded by BBMP to poor people, way back in 1980’s.

Property owners resign to their fate

Only 20 owners of properties in question were present at the hearing held at the KIADB office, in Nrupathunga Road. Most of them were concerned over losing their property partially. Most of them were wondering what will they do with the partial land. They wanted BMRCL to take entire land and or compensate them with good amount.

Mangala M (identity changed on request), one of the owners of properties awarded to poor by the BBMP, works as a labourer at a private office. She said: “Money has no value to us, if we are not able to acquire land in same area or anywhere else in Bangalore. The property prices are all time high. Where shall we go? We request the Metro to give us some land somewhere nearby to re-settle.”

“On a blank white sheet of paper, objections have been recorded in an indecipherable handwriting.KIADB land acquisition officers  took our signature on it,” says Anand M, Mangala’s husband, who works as a labourer in a private company.

When Anand questioned this, the KIADB officer told him it was exactly the same that he objected.  He  says, “I did not sign it,. So I was asked to bring an objection letter.”

Majority of people who attended the hearing were looking for good compensation, as everyone seemed to accept that the project was final and they could not afford to fight it.

Special Land Acquisition officer, Ravi Tirlapu, told Citizen Matters: “No serious objections have been raised by the people. Many of them have sentimental attachments to the property. A good compensation will be given to the people depending on the market value.”

‘Land bill might not be BMRCL-friendly’

Neither the BMRCL nor the KIADB are open about the compensation amount. However they assure that a fair market value will be taken into consideration. Public Relation Officer, Chavan said, “The prevailing market value will be considered at the time of determination of compensation based on the fair market value.”

Residents are looking for the Land Acquisition BILL 2012 to get implemented, in the hope that it might provide some respite to them, as it has been termed as citizen-centric.

Tirlapu says, “If the bill gets passed as an act, it will be difficult to comply as it is citizen-oriented. It will be additional burden on the government and shall not be friendly.”

What next?

Process for the land acquisition will follow the terms of KIADB Act-1966 and General Land Acquisition Act-1894. Compensation amount will be decided by the Krishnappa Committee. Krishnappa is a former revenue secretary who is an advisor to BMRCL.

All the objections will be taken to BMRCL who will in return file their reasons behind the said acquisition. If the KIADB officer finds it necessary, the properties will be acquired.  

“99% such objections do not lead to any changes. People are aware of it. It is not an easy task to change the alignment once decided, as it will again be required to go to HPC of the Central government. A compensation very close to market value will be awarded,” said Tirlapu.

The land acquisition to be started in April 2013 wasn’t allowed by the Election Commission because of the Code of Conduct. The realignment controversy too contributed to the delay in execution of Phase II.

Related Articles

Metro Phase-II victims, intimidated by surveyors, write to BMRCL
BBMP plans to merge Silk Board elevated road with Metro line
Why Narayana Hrudayalaya wants Metro, while Jayadeva Institute doesn’t

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Bengaluru’s Road Circulation Plans: Have your say to fix the city’s mobility problems

The GBA and BDA have invited feedback for proposed road plans by Dec 11th. Know more about the proposals and why citizen inputs matter.

The Greater Bengaluru Authority (GBA) and the Bengaluru Development Authority (BDA) have released proposed Road Circulation Plans, inviting public suggestions and objections till December 11th, before the final approval. This is a necessary step to address the city’s mobility issues. But before framing the suggestions and objections, citizens need to understand what is meant by a circulation plan and how and why it is prepared. This is critical for Bengaluru, as endless urban expansion without an updated master plan has strained the city’s mobility and transportation systems.  Bengaluru residents can send their feedback to the Office of the Chief Town Planner,…

Similar Story

Out of reach: Chennai’s informal settlements lack safe and accessible bus shelters

MTC is expanding its fleet but an analysis found that 41% of Chennai slum settlements lack nearby bus shelters. Here’s what needs to change.

The Metropolitan Transport Corporation (MTC) serves as the backbone of Chennai's urban mobility, carrying millions of residents every day and accounting for over 70% of the city's public transport share. As the transport utility expands its fleet with new buses and renovates shelters across Greater Chennai Corporation (GCC) limits, evaluating the accessibility of this mode of public transit becomes important, especially around access points near the city’s informal settlements.  To what extent does the MTC bus shelter network provide accessible and adequate service to slum settlements? And, where should improvements be prioritised? That forms the basis of this study, which…