Citizens victory: High Court stays Agara-Sirsi flyover

High Court orders the State and the BDA to relook at the project. It also ensures that the citizens say will be considered.

The High Court on July 25, 2012, disposed off the PIL by ordering a final stay on the Sirsi-Agara flyover construction work till the time the CM appointed committee submits their report. Chief Justice Vikramajit Sen and Justice Aravind Kumar ordered the stay.

Flyover work – water tank junction. Pic: Anisha Nair

The BDA counsel submitted that the Chief Minister has already formed a committee to study this project and take into account the citizens’ grievances. According to HC order, the Government will also have to issue an advertisement in papers inviting the public, to attend the hearing and voice their opinion. Petitioners’ representative will also be called to present their case before the committee.

The committee’s first meeting is to be held on August 13th, 2012. They will be submitting their findings on September 15th, 2012 and the High Court will take a final decision on the work on October 5th, 2012.

The HC also asked the petitioners to withdraw the contempt case filed against BDA and its erstwhile commissioner in the interests of amicable discussions.

The residents who filed the case are happy with the ruling. Muralidhar Rao, RWA member, Koramangala, says, “We do not know who is in the committee, but they will surely have to hear us out this time.”

Rajeev Chandrashekar, Rajyasabha MP and Koramangala resident, says “This is a big victory for citizens participation in the decision making process and must serve as a precedent for all future projects being taken up in the city. It is important that Government must choose on its own to involve and engage residents before taking up any project..” The MP’s Namma Bengaluru Foundation funded the PIL against the project.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Fishers of Thiruvanmaiyur Kuppam: Aborigines of the coast, not ‘Beach Grabbers’

Fishers of Thiruvanmaiyur Kuppam challenge claims of encroachment, defending their long-standing rights amid coastal development.

The dispute between the fishermen and the more affluent, non-fishing residents of Thiruvanmaiyur and Besant Nagar has simmered for years, highlighting tensions over land use, development, and livelihoods. Acting upon the complaint from the residents (non-fishers) in the locality, the GCC demolished the temporary constructions made by the fishers of Thiruvanmaiyur Kuppam in June this year. Being less than 40 metres from the coastline, they were termed encroachments. A mainstream news outlet even referred to fishers' construction as ‘beach robbery,’ emphasising concerns that the illegal construction of houses and pathways could lead to the loss of turtle nesting sites and…

Similar Story

Bellandur Lake rejuvenation: An urgent call for action

Citizens have strongly disapproved the slow progress on Bellandur Lake's rejuvenation project. Immediate intervention is needed to avoid failure.

Bellandur Lake, Bengaluru’s largest water body, has been at the heart of an ambitious rejuvenation project since 2020. However, persistent delays, severe funding shortages, and inadequate planning have left citizens increasingly frustrated. Time is slipping away, and without immediate government intervention, this critical environmental project risks failing. A recent meeting with government bodies shed light on the project’s stagnation and the urgent steps required to salvage it. Progress so far Desilting Work: Of the estimated 32.33 lakh cubic meters of silt, 22.69 lakh cubic meters (70%) have been removed, leaving 30% unfinished Early monsoons and slushy conditions have delayed progress…