World’s first Indo-Saracenic building, right here in Chennai, set to regain old glory

Constructed by Nawab Muhammad Ali Wallajah in 1768, Humayun Mahal is said to be the first construction in the Indo-Saracenic style of architecture. After years of neglect, this block of the Chepauk Palace is all set to be restored. Here's more about the ongoing work.

It has suffered decades of neglect: languishing in dilapidated condition for years and later ravaged by fire. But, Humayun Mahal in Chepauk, the world’s first-ever building constructed in the Indo-Saracenic style of architecture, is now slated for a new lease of life. 

The long, creaking sound of walls being drilled into echo across the construction site on a mid-October Friday morning. Scraping the plastering off a wall in the interior of the building, B Raju, a 49-year-old worker wipes the sweat off his face. “We are following the same traditional methods followed to construct the building over 240 years ago,” said B Raju, who has earlier worked in restoring heritage buildings in Karaikudi and Thanjavur. 

Various groups are at work at the site of the mammoth restoration project: a few skilled workers mix limestone and sand, another group breaks eggs meticulously and separates the whites from the yolk and a smaller group of five workers powder whitestone, which gives out crystal sugar-like particles. 


Constructed by the eighth Nawab of the Carnatic, Muhammad Ali Wallajah in 1768, Humayun Mahal and Kalas Mahal form the Chepauk Palace. Chepauk Palace was the official residence of the Nawabs till 1855.

Going back to tradition

The choice of raw materials is intriguing. It is not the usual cement, sand and bricks that you would see in any other construction site. “These raw materials used traditionally vouched for the building’s strength for centuries. We are using the same materials, after thorough research and multiple trial and errors, to regain the glory of Humayun Mahal,” said Joint Chief Engineer of PWD, K P Sathyamurthy.

He also shares several other interesting facts about the restoration: 

  • Madras Terrace roofing (with wood, Madras achikal brick and lime plaster) was used for the first time in the construction of Humayun Mahal. The same roofing, which can be seen on many buildings in the United Kingdom, is being used in renovation now.  Even today, the brick is known as Madras brick everywhere.
  • Mughal plastering technology is being used for the interiors to bring out the serene white shade. Lime, sand, whitestone, egg whites and curd are among the various raw materials used for the procedure.
  • Once the plastering is done, it has to be scraped with a piece of granite stone for at least three days.

This is how the Madras achikal brick looks!

Challenges

There are four key aspects  of the restoration procedure that call for focus: the source of raw materials, skilled labour, timing and application.

Raw material Source
Sand Cauvery River 
Whitestone Rajapalayam and Rajasthan
Limestone Virudhu Nagar 
Curd        Chengalpet and Tiruttani
Granite stone                Hilly regions of Rajapalyam
Square tiles Tirunelveli

“Procuring raw materials of the highest quality is important. There is a specific time when the mixture is to be applied and a procedure to be followed for that. Only skilled labour would adhere to those norms,” explained the senior PWD official. 

However, manpower is a huge challenge. “I earn peanuts as a construction worker. But I did not quit since it is my passion to work on old buildings. Not everyone will think this way,” said Raju. A lot of workers have migrated to countries such as Dubai and Saudi Arabia for better opportunities. 

Once renovated, Humayun Mahal, just like any other heritage building in Chennai, will house a number of government departments. Not just history buffs, but even lay citizens of Chennai are looking forward to visiting the renovated structure. Every corner of the building holds slices of the past and each brick has a tale to narrate.

Meanwhile, here are some shots of the ongoing renovation work:

Comments:

  1. b dhanasekaran says:

    in egmore court complex govt constructed new building at a cos of 16 crores housing about 12 court and several offices and also renovated the old court building at a cost of five crores housing for three court. new building was constructed and opened even after about one year of opening the new court the heritage building work is not over. on enquiry it was informed only plumbing works are pending for want of funds. nobody knows when it will be over but now the five crore spent building is lying without proper maintenance. who will take responsibility for the unnecessary delay.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Bengaluru Buzz: Rain breaks 150-day hot spell | Addressing water woes… and more

Other news of the week: Drive to increase lifespan of trees, Koramangala Valley waterway to be completed by Aug 15th and LED project revived.

Showers break 150-day hot spell Sources from the India Meteorological Department (IMD) had said that dry weather may prevail in the city till May 5th, but light showers on May 2nd brought relief. It had been a zero rainfall month in April, a first since 1983 - and one of the longest dry spells of nearly 150 days since November 2023. The rains also brought in the usual issues of water logging, power outages and traffic bottlenecks. May Day was the hottest of the month so far in 40 years, touching 38.1 degrees Celsius. Kempegowda International Airport showed the highest…

Similar Story

Mumbai Buzz: Two die in a manhole accident | Metro 3 trials begin and more…

Other news in Mumbai: Two children suffocate to death in abandoned car; Bombay HC rap for demolishing galas; Leopard captured at Vasai.

Two die, third critical after falling into manhole Mumbai continues to see tragic accidents related to manual scavenging and deadly manholes. Two people died and a third is critical after falling into a 30-foot-deep manhole in Malad. The manhole was connected to a drain pipe on the site of a private under-construction building at Pimpripada in Malad east. Raju, who was a worker at the site, fell in and after that two nearby residents, Aqib and Javed jumped to save him. When none of them came out, the locals called the fire brigade to rescue them. According to the preliminary…