Namma Metro: The race is on to get Whitefield line operational by March

Metro will operate feeder services between Baiyappanahalli and KR Puram till Whitefield line is fully operational, for commuter convenience.

“I have been selling coconuts here for 30 years and one thing that I can assure you is that this line to Whitefield will be of great help to commuters,” says Arif, a coconut seller outside KR Puram metro station. “Everyday I see people running to catch buses and waiting hours at the bus stop. With the metro coming, traffic too should reduce.”

The much awaited KR Puram-Whitefield Metro line, likely to become operational in March, is expected to bring relief to thousands of daily commuters, most of whom are tech professionals working in and near Whitefield.

Metro ridership is expected to increase

Phase I of the Baiyappanahalli-Whitefield corridor (Purple line expansion) includes the 13-kilometre section from KR Puram to Whitefield. Anjum Parwez, director of BMRCL, said that once in service, the Metro trains on this 12-station route will cover the distance in 23 to 24 minutes.

Metro construction workers at a site in the Whitefield line.
Metro construction workers doing their job without any safety equipments. Pic: Kanishka Khandelwal

The stretch will also have a walkway access directly linked to the Information Technology Park Limited (ITPL) campus from the Pattandur Agrahara Metro Station.


Read more: Living with the metro construction: Safety, pollution and accessibility concerns 


Two six-coach trains are now being tested for safety and other parameters by BMRC. The inspection work includes checking of tracks, station safety, signaling, and electrical installations.

The completed Baiyappanahalli-Whitefield stretch will include stops at Whitefield, Channasandra, Kadugodi, Pattandur Agrahara, Sadaramangala, Nallurhalli, Kundalahalli, Sitharama Palya, Hoodi Junction, Garudacharpalya, Saraswati Nagar, and KR Puram. 

Until the entire stretch is open, the BMRCL will operate bi-directional feeder services between Baiyappanahalli and KR Puram, which is expected to be a major convenience to commuters.

Once the Whitefield line becomes completely operational, the metro ridership is expected to increase by 3.5 lakhs as it seamlessly connects Whitefield, a major IT corridor and residential hub, with the city’s central business district and other areas. 

Pollution and pedestrian safety concerns

However, due to the ongoing legal disputes between environmental and local authorities over the relocation of some 60 trees close to Benniganahalli Lake, this extension experienced numerous delays. And not all agree that it will ease traffic with more people using the metro. “I take this KR Puram bridge almost every other day as my school is  nearby and all I see is excessive dust and traffic,” says Kimakshi Khanna, a student. “None of us can stand here without masks as it becomes difficult to even breathe at times.’’

A commuter waiting for the bus at a metro construction site.
Commuters waiting for buses at the construction site without any safety measures in place. Pic: Kanishka Khandelwal

With the launch of metro services just two months away, I decided to visit this stretch and see the situation on the ground for myself. I took a metro from Jayanagar to the current last stop nearest to Whitefield i.e Baiyappanahalli, which also houses the metro depot. From Baiyappanahalli station I could see very little construction going on. I sought the help of a metro official and learnt that construction is happening mainly near KR Puram and not anywhere near Baiyappanahalli. 

I took an auto to the KR Puram metro station, which is located in the middle of a highway and near a flyover. I did not see any division between the roads and the construction site. The construction of what looked like a flyover was going on as well. I could not observe any kind of safety precautions being taken by workers or for the crowds of pedestrians along the road.

The metal and other construction material were haphazardly lying on the road. People find it difficult to cross the roads because of heavy traffic and dust coming from the construction site. The construction site is uncovered and generates huge amounts of dust, which has covered buildings nearby, giving them a brownish hue.

I did not observe any police personnel present around.


Read more: Namma Metro is not designed for inclusivity 


There are no offices or shops near the metro site. There is one foot over bridge for crossing. Most people use it to reach the metro station since crossing the road at ground level is difficult and dangerous with this being one of the busiest roads in the city. There is a bus stop by the side of the construction.

People have to wait for the bus in the construction areas. I tried talking to some of the workers about the construction but they were hesitant as there was no supervisor present.

Cars pass by a metro construction site.
No proper footpath/ division between the construction site and the road. Pic: Kanishka Khandelwal

One interesting thing is that construction work is happening all through the day and night. At night, the shift changes and another set of workers arrive to take over from the day shift. However, all the noisy machine work is done during the day so as not to disturb the neighbourhood at night.

Namma Metro in 2023

As per its current schedule, BMRCL is likely to operationalise close to 40 kilometres of lines under Phase II in the current year. The most important one being the linking of two major IT corridors–Whitefield and Electronics City—after years of delay.

The former is an extension from Baiyappanahalli while the latter will be the new Yellow Line from R.V. Road to Bommasandra (19 kilometres), with a metro-cum-road flyover between Ragigudda and Silk Board. 

The other lines expected to be completed are Kengeri to Challaghatta of the Purple Line on Mysuru Road and Hesaraghatta Cross to Madavara on the Green Line on Tumakuru Road. 

Also read:

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai infrastructure report card: How have big ticket projects fared in last five years?

As elections approach, political parties try to gain mileage from recent infrastructure projects. But are Mumbaikars convinced?

Several infrastructure projects have been launched or inaugurated in Mumbai over the last five years, in the backdrop of huge political upheavals in Maharashtra with unexpected alliances, fractured coalitions, and the overthrow of the Maha Vikas Aghadi (MVA) by the Eknath Shinde-led Mahayuti. Celebrated as an engineering feat, the Mumbai Coastal Road, named Dharmveer Swarajya Rakshak Chhatrapati Sambhaji Maharaj Coastal Road, was inaugurated by chief minister Eknath Shinde with deputy chief ministers Devendra Fadnavis and Ajit Pawar on 11th March. This is amongst the major infrastructure projects that have been completed in the past five years and being counted as one…

Similar Story

Homeless in Chennai: Families that lack shelter need urgent support

Many homeless families in Chennai are in urgent need of support as they brave extreme weather conditions and safety issues.

Chennai has approximately 8,331 homeless individuals concentrated in hotspot areas and along major roads across 15 zones. Notably, 69% of this population consists of families who have lived on the streets for generations. Despite this high number, a recent study by the Information and Research Centre for the Deprived Urban Communities (IRCDUC) reveals that the city doesn't have a single shelter for families. In January 2023, Citizen Matters visited five GCC homeless shelters in Chennai to identify operational gaps. These shelters cater to boys, girls, the elderly, and individuals with mental illnesses. Yet, the funding for their operation and maintenance…