The report shows Mumbai's challenges with solid waste management, sewerage and how it failed the Swachh Bharat Mission of 'Garbage Free Cities'.

After a steady reduction from 2017 to 2020, the city witnessed an increase in waste collection from 5500 Metric Tonnes per day (MTD) in 2020-21 to 6300 MTD in 2021-22, says a report released by Praja Foundation. The highest contributor is wet (food) waste which comprises 73% of the total garbage collected at the landfills.

The report on the status of civic issues in Mumbai, highlighted challenges in solid waste management, sewerage and water bodies. Moreover, due to the deteriorating sanitisation facilities, the Brihanmumbai Municipal Corporation (BMC) failed the Swachh Bharat Mission (SBM) 5-Star Rating of ‘Garbage Free Cities’ in 2022, says the report.

The waste generated in the city had reduced from 7,350 MTD 2017-18 to 5500 MTD in 2020-21. The 15 per cent increase in the past year could be related to resuming of post-pandemic activities.

“The National Institute of Urban Affairs (NIUA) recommends the Integrated Solid Waste Management (ISWM) system to reduce waste generation, process waste at source and reduce waste sent to landfill. The ESR 2021-22 states, Deonar dumping ground receives approximately 12% (700 MTD) and Kanjurmarg landfill receives 88% (5,500 MTD) of waste on a daily basis since Kanjurmarg has a waste-to-energy plant,” said, Milind Mhaske, CEO, Praja Foundation.

Cost benefits of decentralisation of waste

According to the report, the BMC can save Rs.1,485 crore with a decentralised waste management. The operation and maintenance of landfills, the fuel prices for transport of the waste are the major areas where the BMC can save money using a decentralised system.

The cost to collect and transport One MTD of waste to the landfill from all 24 wards is Rs. 3,840/day. Hence, to transport 6,300 MTD of waste, it costs BMC Rs. 2.42 crores/day and annually, this cost is as high as Rs. 883 crores. While for the landfill, the cost of operations and maintenance Rs. 3,000/- for one metric tonne per day, thus for 5,500 MTD of waste annually it costs Rs. 602 crores.

“To reduce these costs, BMC should adopt decentralised SWM, which has been done successfully in Councillor Ward No. 203 in F/S ward through the Swachh Mumbai Prabodhan Abhiyan (SMPA) model. This scheme involves community-based organisations that collect waste from slum households and process within the ward,” added Mhaske.

Members of Praja Foundation at the release of their report
Praja Foundation members discussing Mumbai’s civic issues at the release of the annual report. Pic: Sherine Raj

Bulk waste generators to treat waste at source

The Solid Waste Management Rules, 2016, states that the BMC must achieve waste management at the source, and should reduce its dependence on dumping grounds. The civic body made it mandatory for bulk waste generators like housing societies and commercial establishments with more than 20,000 sqm area, or generating 100kg waste daily, to treat waste at source. However, the NGO pointed out that currently only 50% of societies are processing the waste in their premises.

“There is a significant gap in waste management practices, the BMC should come up with an effective plan to improve waste processing and management in these societies, as 50% (1,401) of the 2,825 BWG societies in Mumbai are not processing their wet waste at source,” said Rini Cherian, programme coordinator, Praja Foundation.


Read more : Plastic pollution from landfills poses severe risk in Mumbai


Rise in citizens’ complaints

Over the past decade, citizens’ complaints related to Solid Waste Management have increased by 124% (from 5,519 in 2013 to 12,351 in 2022). The highest number of 4,356 complaints in 2022 were related to garbage not lifted and the removal of debris. These complaints have been constant in the past 10 years, stated the NGO.

While Air Pollution complaints increased by 237% (from 65 complaints in 2013 to 219 complaints in 2022) and drainage increased by 35% (12,708 in 2013 to 17,121 in 2022) in the same period. However, the average time taken to resolve these complaints was as high as 31 days in 2022.

“Mumbai faces major climate change issues such as air pollution, heat waves, and contaminated water bodies due to inefficient sanitation and waste management processes. In 2022, the BMC’s Mumbai Climate Action Plan (MCAP) included targeted interventions to improve the efficiency of solid waste management, sewerage treatment, and measures to ensure good air quality, which is a positive step,” said Nitai Mehta, Founder and Managing Trustee, Praja Foundation.

Mithi River pollution

Mithi River is heavily polluted with fecal coliform (17000MPN/100ml), much higher than the prescribed norm by the CPCB limit of less than 2500 MPN/100ml.

Moreover, the average maximum Biochemical Oxygen Demand (BOD) recorded in all major beach outlets was 22 mg/it. in 2021, much higher than the prescribed norm by the CPCB of <3 mg/lt.

“The focus should also be given to restoring Mumbai’s rivers and beaches and ensuring effective measures to curb water pollution. The effective implementation of MCAP and robust monitoring can help tackle climate change in Mumbai, ensuring a better future for generations to come,” concluded Mishra.

Also read :

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Broken roads, uncleared garbage: In Pune’s Ramtekdi, businesses await basic civic services 

Businesses in the industrial hub pay lakhs in taxes, yet they lack civic infrastructure, despite multiple complaints to the Pune Corporation.

Businesses in Ramtekdi Industrial Estate are expected to manufacture, employ and attract customers, but the basic infrastructure around them tells another story.  The industrial estate in Hadapsar is home to small and medium manufacturing units, including businesses supplying Indian companies and exporting overseas. For our unit on Lane 1, getting to work means navigating a road broken into deep craters that fill with stagnant water during the monsoon season. Trucks carrying goods, workers on two-wheelers and visitors to the factory, all have to negotiate the same stretch. The state of the approach has become a problem for the business itself.…

Similar Story

Fix building violations, traffic and waste issues: BECC Citizens’ Manifesto

As Bengaluru anticipates its first GBA election, Bengaluru East City Corporation’s residents raise concerns over civic and infrastructure issues.

Bengaluru has been without elected corporators for over six years. While the Greater Bengaluru Authority (GBA) replaced the Bruhat Bengaluru Mahanagara Palike (BBMP) formally last year on September 2nd, elections to the new GBA have been stalled. Citing logistical challenges from the ongoing Special Intensive Revision (SIR), authorities received a Supreme Court extension to hold elections by December 31st. The restructured GBA, expanding from 198 wards to five corporations across 369 wards, faces continuing gaps in solving various ward-level issues — such as solid waste management and traffic problems, poor execution of civic works and funding issues. People believe the…