Chennai Buzz: Corporation fines contractors | Shelters homes face fund shortage..and more!

Chennai Corporation has fined contractors for flood mitigation work delay. The shelter homes in the city face a fund crunch. Catch this and more news!

Chennai Metro Phase 2 progress and accessibility promise

The elevated metro line between Porur and Poonamalle as part of Phase 2 will have a total of 453 pillars. Of this, 111 pillars have already been erected as part of the progress on this line. The total cost of the elevated line is estimated to be Rs 1147 crore. The line is set to be open and operational from June 2023.

This line will extend from Lighthouse to Poonamallee and is part of Corridor 3. The total length of all lines in Phase 2 is 118.9 km. The review is on for the project work in Phase 2.

Meanwhile Chennai Metro Rail Limited (CMRL) has also issued an assurance that all metro stations and rails will be made accessible and inclusive for persons with disabilities within six weeks. The promise came on the heels of a petition filed in the Madras High Court on the accessibility of the metro. 

Source: The Times of India | The New Indian Express


Read more: All that’s wrong with stormwater drains in Chennai and how to fix them


Corporation fines contractors for delay

Three contractors have been imposed fines by the Greater Chennai Corporation (GCC) for the delay in carrying out flood mitigation works in the city. The contractors were working along the stretches of Ambedkar College Road, Vembuli Amman Salai and Rangiah Road. They have been penalised Rs 75000, with the quantum set to increase in case of further delays. 

ramp laid over road cut
Stormwater drain under construction. Pic: Senthil Kumar

The flood mitigation works involve fixing issues with stormwater drains, improving the network and desilting and maintenance of the drains. Various multilateral agencies are involved in providing funding for the augmentation of the city’s stormwater drain network. In addition to this, desilting of canals, flood mitigation in subways and augmentation of electrical motors to pump flood water will also be carried out before the onset of the northeast monsoon. 

Source: The Hindu

Chennai corporation shelters face fund shortage

Shelter homes owned by the Greater Chennai Corporation are facing difficulties in operations due to a shortage of funds. NGOs that run the shelters have raised the issue of non-disbursal of funds. The funds have not been distributed for the past six months. This has forced NGOs to resort to donations to keep the shelters functioning. 

Central government funding for the shelters running under the National Urban Livelihood Mission (NULM) has not been paid. Each shelter is owed around Rs 10 lakhs since late last year. The NGOs are spending out of pocket on staff salaries and meeting the needs of the residents. Contracts of 35 NGOs running shelters have not been renewed to date despite the usual renewals taking place in January each year. The civic body is looking to mobilise funds for shelters from different schemes in the absence of funding under NULM.

Source: The New Indian Express


Read more: In search of a shelter for a mentally ill person on the streets of Chennai


Four more Sewage Treatment Plants (STPs) in the city

Chennai is set to get four sewage treatment plants (STPs) in the coming months along waterways in the city. One of the plants at Chetpet has been inaugurated while three more are set to come up along Adyar and Cooum rivers. A tertiary treatment plant is also being built at Langs Garden Road. All plants are nearing completion and will be operational shortly. 

Two of the STPs will be built at a cost of Rs 4.31 crore near the Adyar in Kotturpuram. They will have a capacity of treating six lakh litres of sewage per day. This will be ready by July. Another STP near the Mambalam canal with the capacity to treat 40 lakh litres of sewage will be inaugurated by September. 

Source: The Hindu

[Compiled by Aruna Natarajan]

Also read:

Comments:

  1. Rajan says:

    If you could only write up about the encroachment done by the govt itself on the Poonamalle High road right next to TNPCB office just half a kilometre from DG Vaishnava college by the TNHB itself it will be helpful. They are building huge multistory buildings beginning at the exit of Koyambedu flyover till TNPCB office right on the cooum river flood plains. Only last year all the illegal encroachments were removed so that flood waters can easily flow on the cooum but the govt itself has become the encroacher now. Not only this they have unnecessarily built a storm water drain haphazardly, construction is going on for more than a year and they don’t know how to finish it. Please write about this.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

City Buzz: Precautions against HMPV | Bengaluru bus fare hike irks commuters…and more

Other news: Rise in demand for office space, Regional Meteorological Centre to expand network and housing sales go up.

Precautions against HMPV across Indian cities In Gandhinagar, Ahmedabad and Rajkot civil hospitals, isolation wards have been created as precautionary measures against the Human Metapneumovirus (HMPV). Just a day earlier, the State government revealed that a two-month-old boy had been admitted with the infection. In Mumbai too, a six-month-old was admitted to a hospital after testing positive for the virus. A respiratory virus infection was reported in Bengaluru too. Sources said that HMPV affects the upper and lower respiratory tracts and is a risk to all vulnerable groups, including young children, the elderly and those with weak immune systems.  …

Similar Story

City Buzz: Metro boom in Chennai, Kochi | Chaos on New Year’s Day…and more

Other news: HYDRAA clarifies on demolitions, improvement in Delhi's education standards and BBMP starts pothole filling drive.

Ridership shoots up in Chennai, Kochi Metros Chennai Metro Rail's patronage increased by 1.41 crore in 2024, with 10.52 crore using it, compared to 9.11 crore in the previous year. The ridership is nearly one-third of the total 35.53 crore passengers using Chennai Metro Rail Limited (CMRL) services for more than nine years since June 29, 2015. While the ridership for CMRL to break even was 4.33 lakh per day in its initial three years since June 29, 2015, the Chennai Metro catered to only 2.8 crore till December 31, 2018. Meanwhile, the Kochi Metro set a new monthly ridership…