Green Tribunal orders an interim stay on Mantri’s Bellandur project

Following the NGT stay on the multicrore project coming up on Bellandur lakebed, the High Court has decided to adjourn the case to July 18, 2014.

The National Green Tribunal (NGT) has ordered an interim stay on the mega-project coming up on the land between Bellandur and Agara lakes, in Bengaluru. This was in response to a petition filed by The Forward Foundation, Bangalore, Praja RAAG, Bangalore and Bangalore Environment Trust.

The stay order issued on April 16, 2014, states that “the Tribunal is satisfied that there is a substantial question connected to and concerned with environment which has got to be enquired into.”

It observes that “the construction activities are carried on in an extent of 13,50,455 m2 in an area of 80 acres in between two lakes and if permitted, the rapid encroachment being made would cause, no doubt, damage to the water course situated in between the two lakes impeding flow of rain water into Bellandur lake, the largest freshwater body in Bangalore and hence, an immediate intervention by the Tribunal by granting an order of stay of the construction activities becomes necessary.” The Tribunal has stayed further construction activities by the Mantri Techzone Private Limited and Core Mind Software and services Pvt Limited, until further orders.

The petition had questioned the project on the grounds of environmental impact by the project.

HC decides to observe NGT proceedings

In a hearing that took place on April 25, 2014, the counsel for one of the respondents brought to the notice of the High Court that a stay has been ordered by the National Green Tribunal. However, the petitioner in Bellandur-Agara mega project, Namma Bengaluru Foundation, clarified the High Court that the petitioners for National Green Tribunal were different from the petitioners in the High Court.

Following this, the High Court decided to wait and watch the NGT proceedings. As the next Tribunal hearing has been scheduled on July 15th, 2014, the HC bench decided to list the case on July 18, 2014.

Related Articles

Citizens protest against multicrore project coming up in Bellandur
Bellandur wetland multicrore project: KIADB orders suspension of work

Comments:

  1. NITIN SESHADRI says:

    The shocking aspect here is that one of the project proponents appears to be recklessly proceeding with work inspite of the NGT weighing in. I hear that one of the petitioners in the NGT matter was forced to file a police complaint before the ACP Madivala against one of the project promoters. Shameful behaviour !

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

BDA’s tree plantation drive faces accountability issues, not accounting errors

This record-breaking drive in Bengaluru has cleared out shrub ecosystems rich in biodiversity to plant saplings that may never thrive.

Fifteen lakh trees. A place in the Guinness Book of Records. The Bengaluru Development Authority (BDA) has been on overdrive, promoting its new project to plant 15 lakh trees in spaces created in its new layouts. 240 acres have been earmarked across BDA’s faraway layouts. The saplings are to be planted across lake and nala buffer zones, parks and public spaces in new neighbourhoods like Nadaprabhu Kempegowda Layout, Banashankari 6th Stage, and Dr Shivarama Karanth Layout, according to the BDA Chairman N A Haris. While such massive tree plantation exercises are by themselves questionable, there is also the question of a…

Similar Story

Where are the flamingos? How Metro construction is devastating Chennai’s Pallikaranai Marsh   

In a report, environmentalists warn marsh blockages increase flood risk for South Chennai and call for urgent measures to avert ecological damage.

On a regular day in May, the calls of migratory waders and other shorebirds foraging in sprawling mudflats fill the air in the southern reaches of Chennai. May is the dry season for the Pallikaranai Marsh, when water levels naturally recede, exposing the critical feeding and breeding grounds that attract hundreds of bird species to this globally recognised urban wetland. But this year is different. The mudflats are gone. In their place is a stagnant expanse of water. This unusual water level during the dry season is not due to early rains. Indiscriminate construction within the marsh is blocking the…