Green Tribunal orders an interim stay on Mantri’s Bellandur project

Following the NGT stay on the multicrore project coming up on Bellandur lakebed, the High Court has decided to adjourn the case to July 18, 2014.

The National Green Tribunal (NGT) has ordered an interim stay on the mega-project coming up on the land between Bellandur and Agara lakes, in Bengaluru. This was in response to a petition filed by The Forward Foundation, Bangalore, Praja RAAG, Bangalore and Bangalore Environment Trust.

The stay order issued on April 16, 2014, states that “the Tribunal is satisfied that there is a substantial question connected to and concerned with environment which has got to be enquired into.”

It observes that “the construction activities are carried on in an extent of 13,50,455 m2 in an area of 80 acres in between two lakes and if permitted, the rapid encroachment being made would cause, no doubt, damage to the water course situated in between the two lakes impeding flow of rain water into Bellandur lake, the largest freshwater body in Bangalore and hence, an immediate intervention by the Tribunal by granting an order of stay of the construction activities becomes necessary.” The Tribunal has stayed further construction activities by the Mantri Techzone Private Limited and Core Mind Software and services Pvt Limited, until further orders.

The petition had questioned the project on the grounds of environmental impact by the project.

HC decides to observe NGT proceedings

In a hearing that took place on April 25, 2014, the counsel for one of the respondents brought to the notice of the High Court that a stay has been ordered by the National Green Tribunal. However, the petitioner in Bellandur-Agara mega project, Namma Bengaluru Foundation, clarified the High Court that the petitioners for National Green Tribunal were different from the petitioners in the High Court.

Following this, the High Court decided to wait and watch the NGT proceedings. As the next Tribunal hearing has been scheduled on July 15th, 2014, the HC bench decided to list the case on July 18, 2014.

Related Articles

Citizens protest against multicrore project coming up in Bellandur
Bellandur wetland multicrore project: KIADB orders suspension of work

Comments:

  1. NITIN SESHADRI says:

    The shocking aspect here is that one of the project proponents appears to be recklessly proceeding with work inspite of the NGT weighing in. I hear that one of the petitioners in the NGT matter was forced to file a police complaint before the ACP Madivala against one of the project promoters. Shameful behaviour !

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Status check: Key concerns remain as Chennai moves ahead with WTE plans

Greater Chennai Corporation's tender for the Waste-To-Energy plant is at the final stage; Here is what we know about the bidders

17,422 metric tonnes per day — that's the staggering amount of trash the Greater Chennai Corporation (GCC) will generate in 30 years. Currently, Chennai produces 6,143 metric tonnes of waste daily, which adds to the growing piles in Kodungaiyur and Perungudi dump yards. Like many other major cities, GCC is struggling to find a sustainable solution for waste management and has proposed a Waste-To-Energy (WTE) plant. However, the experiences of cities like Delhi are testimony to the significant environmental and health impacts of WTE plants. A recent The New York Times investigative report on the Delhi WTE reveals: "The government…

Similar Story

Flooded lands, disappearing birds: Pallikaranai wetland tour highlights impact of shrinking lakes

A vital wetland, Pallikaranai has shrunk drastically due to urbanisation, threatening biodiversity and vulnerable communities in Chennai.

Many of us who have lived in Chennai for years have probably crossed Pallikaranai Marshland at least once. Yet, we often overlook that we are passing through an area that was once ecologically rich and a haven for diverse species. But the marshland, one of the few coastal aquatic habitats in India to qualify as a wetland, is now just a shadow of its former self. Unchecked encroachments and rampant urbanisation have drastically reduced the catchment area of Pallikaranai Marsh. With the Northeast monsoon bringing rains to Chennai, residents are increasingly concerned about flooding. Experts point out that rejuvenating the…