Peripheral Ring Road: Out of 4500 Cr, is 3850 Cr for grabbing land?

While the actual amount required to construct the Peripheral Ring Road is around 650 crores, the Bangalore Development Authority is planning a mega project of 4500 crores, where land and money get wasted.

When the alignment of around 50+ kms of the proposed road is more or less the same as NICE road, BDA has to construct only 60+ kms, not 110 kms as projected. Pic: wikimedia commons

Why should the Peripheral Ring Road cost 4300 crores, and why should Japanese agency Japan International Cooperation Agency (JICA) be funding it? The toal length of the project is about 110 km, of which 50+ is unnecessary, because the western half of the road is more or less identical to the NICE Road which has already been built. So what we really need is road construction for 60+ km, and at about 9-10 crores a km, it should cost no more than 650 crores.

Where is the rest of the money going? The answer is ‘land acquisition.’ Tons of people own the land on which the road is proposed to be built, and the government is currently in the process of trying to notify and buy up the land needed for the road corridor. Three-fourth of the money is for this activity.

However, is land acquisition necessary? Most of the Ahmedabad Ring Road was built without land acquisition, and at less than 1/4 of the cost per km that Bangalore Development Authority is projecting for PRR. Moreover, that project not only built the road, but improved a lot of the infrastructure in the vicinity of the road. If all that can be done for so much less money in one state, why not in Karnataka?

Moreover, the way Gujarat did the project is the legally right way too, conforming to the Town Planning Act (it’s called ‘land reconstitution’). Our government is so used to the land-as-political capital exercise that even after taking  missions to Gujarat by several top officials of BDA, we continue with the same old junk – dispossessing farmers at low prices, gifting that land to speculators, making money in denotification scams, and building a road without any regard for what’s around it. 

And why does JICA want to finance this racket?

Reconstitution works like this. Let’s say you are doing a project. It could be anything – making a new road like the PRR, or widening an existing one, or even much bigger things like making a whole new layout in a newly urbanising area. In each of these cases, there are some private property owners whose lands are in the spaces where we want to put up roads, pipes, pumping stations, transformers, etc. 

The usual practice of the socialist state was to simply identify the properties falling on these ‘needed’ places, and simply buy them out using the compulsory acquisition process. This is unfair – because one set of people lose property, but others behind and around them get all the gains. It is costly – the state has to come up with the money to buy out all these properties. It is also slow – many home owners go to court, others get their properties denotified, which forces plans to change, etc. 

Reconstitution recognises that for any project there is a much wider ‘zone of benefit.’ So, if we make a 75 m PRR, on either side of that road for about half a kilometer, property values will jump. All those nearby properties are getting the benefit of new infra, without contributing one paise to the project. 

Therefore, what good town planners do is that they treat the entire zone of benefit as the target area. In this area, they compute the total amount of land needed for ALL the new infra (roads, side roads, drains, and much more), and work out the percentage of the total area taken up by the new infra. This usually comes to about 11%. Then they add another 2% for their efforts, totalling 13% of so. And within the zone of benefit, ALL PROPERTY OWNERS LOSE 13% OF THEIR PROPERTY, and the rest of the land is reconstituted among the owners, so that each gets his balance 87% or so.

This is extremely doable in unbuilt areas, and even works well. All properties end up getting connected to new infra, and the plots are all made rectangular in shape. The entire area gets improved as a result. Until such improvement is made, the town planning authorities keep the permitted FSI very low, which gives owners an incentive to participate in the scheme to raise their building rights. Even in semi-constructed areas, the schemes can work, with some diligence and modifications.

If the PRR were built like this, it would cost 650 crores, and those who already have the lands in those areas – including small farmers – would benefit. No money would be needed for acquisition, but only for road building itself (about 1/4 of the cost, max, even with all the side infra). BDA could end up with 2% of the land free to itself, to develop afterward for large developments. 

But the way it is going about it now, everyone who owns land already is either dispossessed or favoured out through denotification, these lands are transferred from poor farmers to rich speculative buyers, and no part of the area other than the thin slice of road gets developed. Naturally, people object, go to court, etc. which is why even 10 years after it was mooted there is no sign of the project actually taking shape.

The Town and Country Planning Act requires that any developed area should be formed through a town planning scheme. In 55+ years of its existence, the Karnataka planners have not executed even one such scheme. BDA’s master plan is very much like the splash of colours that your children can create on a canvas by simply throwing paint around. But behind that madness is a very cunning and disgraceful scheme – nothing more than a land grab that uses the law as an instrument of crime. And JICA is the moneylender that stands ready to grease this pole.

Comments:

  1. Babu Rao says:

    It is important to review all the NOTIFICATIONS done by a panel. There are few which are done with no plan to really implement any scheme. We as middle class citizens as a group purchased sites about 17 years back and nearly 8 years have passed since a notification was passed on our lands. It is on Bannerghatta road at about 2 kM from Meenakshi mall. Our plight is neither we can move in constructing houses or hope for alternative. This was done at a time when NICE road was likely to be constructed and to oppose that politically this notification was made.
    It is tiime review is made of all notifications and aligned to the new master plan so that everyone gets to know clearly what the government intends to do for the next 10 years if not more

  2. vasudevan d says:

    Vasudevan.D
    Ref; Rs 4500 cr. road project… It is loot of public money. for a 60 km of new road it will not cost more than 120 to 150 crores as per the National High way authorities of India. In fact it was just 1.5 crore when the Golden triangle project was started by former PM A.B Vajapeyee. So where the remaining crores are going .. into the pockets of middlemen and politicians pockets. Moreover, the government or private parties should NOT acquire or purchase lands from farmers instead the required land should be taken on lease and annual lease should be given to individual owners by the project authorites. This would bring down the project cost very considerably and curb corruption, loot of public money and raising land cost. In a quarter of the project cost the project could be completed besides overcoming delays due to legal tangles. The farmer/land owner will be happy to received the best possible return for his land and also hold on his pride of having his forefather’s land or his own hard earned investment in his life time. The need of the hour is to stop land procurement for projects. In particular about his Road project we should find ways to stop it even approaching a court to know why so much need to be invested . In fact with such huge amount the state can have a 100 km railway network which would help the poor and the rich for hundreds of years Why the govt is not thinking to help the common man ?. Vasudevan

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Anger behind the wheel: How to rein in the growing menace of road rage

Traffic congestion coupled with anxiety, peer pressure and a lack of self-awareness has led to an increased number of road rage incidents.

Priyanshu Jain, an MBA student at Mudra Institute of Communications (MICA) in Ahmedabad, tragically lost his life in a road rage incident on November 11th. The 23-year-old was stabbed by Virendrasinh Padheriya, a head constable in the city, following an altercation. Padheriya, who has a criminal past, was later apprehended from Punjab. Priyanshu's family and friends are devastated by his death, and both his hometown of Meerut and citizens in Ahmedabad are demanding justice. A series of protests have been organised, including a silent march, a candlelight vigil, and a peaceful hunger strike. Pranav Jain, his cousin, describes Priyanshu as…

Similar Story

How a student app to connect with share autos can help commuters in Chennai

A team from St. Joseph's Institute of Technology and IIT Madras makes commuting easy for Chennai residents through their innovative app.

Crowded buses, with passengers jostling for space, are common on Chennai's roads. The city has many public transport users, including college students and people commuting daily for work. Share autos play a crucial role in providing last-mile connectivity, helping passengers travel from bus stops and MRTS stations to their final destinations. These share autos fill the gap by making multiple stops between bus stations, schools, colleges, and other key locations. However, the share auto system has its shortcomings, the most notable being that it is unreliable. Share auto drivers often decide daily whether to stop at a specific location. If…