Month end, what’s the status of Kadirenahalli underpass?

An update on the JNNURM underpass project at Kadirenalli road junction, Outer Ring Road. BBMP chief had said it would be ready by end of the month.

According to BBMP’s second quarter status report for JNNURM projects, 2009-10, the sanctioned cost was Rs 24.86 crores, with BBMP putting up 50% of the funds. The tender was awarded in March 2008, with the project scheduled to complete in January 2009 as per the Detailed Project Report. In the same report, BBMP gives reason for delay as:  "Sital conditions (faced hard rock which has to be blasted), traffic diversion are the reasons for delay. And another major problem is land acquisition."

The Deccan Herald reported on September 13th about the Kadirenahalli underpass getting ready to be opened. It said the BBMP Commissioner H Siddaiah inspected the underpass and BBMP has decided to open the facility by end of the month, atleast one way. The report adds, ‘The route from Uttarahalli main road towards Padmanabhanagar and Jayanagar will be opened for vehicular movement’.

$(document).ready(function(){ $(‘.carousel .carousel-inner .item’).first().attr(‘class’, ‘active item’);});  

In July, Bangalore Mirror reported engineers of the contractor Madhava HighTech Infrastructure were using    untreated water for curing the concrete pillars.

S Srinivasan, a resident of Uttarahalli, has sent in some pictures. The state of the underpass construction, as on September 20th can be seen. He says, ‘It is my view that it is a long long way off for this junction to be operational.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Watch: What MP P C Mohan told Bellandur residents during his campaign

On April 21st, residents discussed infrastructure projects, mobility and traffic congestion with the BJP MP candidate from Bangalore Central.

With a long career of 25 years in politics, P C Mohan, the incumbent BJP MP from Bangalore Central constituency, is contesting in the 2024 Lok Sabha elections for the fourth time. At an interaction with residents from Bellandur on Sunday, April 21st, the MP candidate answered questions on infrastructure projects for the locality, solutions for traffic management and decongestion of roads, lack of civic planning in Mahadevapura, among other issues. Here are some excerpts from the interaction: Metro is a long-term project that could take 6 years. From a policy perspective, what can we do to use existing modes…

Similar Story

Lok Sabha Elections 2024: What Mumbai civic groups want their MPs to address

As Mumbai readies for polls, civic groups share their demands from elected representatives - infrastructure, environment and public transport.

Even as summer heat sets new records in Mumbai, the city is gearing for elections on May 20 amidst chaotic political developments. As leaders jump the political parties, citizens are focussing on the official manifestos released by major political parties. An election manifesto is a statement put out by a political party or a candidate defining their goals. It reflects the social issues that they promise to tackle should they be elected. As such this document becomes a compass for voters who can decide in which direction they would like to see the country go.ย  Urban civic groups, having the…