What Bengaluru’s flight users got in 5 years, rail users await for 10 years

While SMVB has finally become operational with 29 trains originating and terminating here, passengers still face several difficulties.

In 2022, the South Western Railways (SWR) announced that the agency would undertake a complete revamp of the two main coaching terminals (the beginning and final points for trains), Krantiveera Sangoli Rayanna (KSR) and Yeshwantpur railway station, as well as the Cantonment Railway station, a major boarding point for several trains.

The stations would be modelled after the Sir M. Vishveshwaraya Terminal (SMVB) inaugurated in June 2022. The announcements repeatedly emphasise that these railway stations are going to be transformed into airport-like terminals.

Delayed promises

But airports take time and if SMVB is anything to go by, three airport-like railway stations could take several years. Where railways are concerned, delayed promises are not new.

SWR began planning the SMVB station as the third coaching terminal for Bengaluru in 2012, to reduce the burden on KSR and Yeshwantpur railway stations. It took three years for the project to be greenlit and was supposed to be completed by 2019.

The railways missed the deadline and indeed had to redesign aspects of the station due to technical flaws. The terminal was finally completed in 2021 and then lay unopened for over a year, apparently so that it could be inaugurated by Prime Minister Narendra Modi. Times of India has a detailed report on the timeline of the station. Such delays also cost the railways and consequently the public financially.

Meanwhile, the other three railway stations have also seen more delays in revamping than any actual revamping itself. Rail activists and travellers have been asking for improvements in KSR for years. The station does not have enough elevators to access foot over bridges to reach different platforms with heavy luggage, lacks adequate seating, emergency medical facilities, and ATMs. Clean toilets are a distant hope and recently the passenger subway was filled with sewage.

In 2018, SWR handed over the station’s running to Indian Railway Stations Development Corporation (IRSDC), a joint venture of the Rail Land Development Authority and Indian Railway Construction Limited, both run by the government.


Read more: An urban rail network: Light at the end for Bengaluru’s harried commuters!


In 2021, IRDSC was abruptly shut down and KSR was handed over to the General Manager of the Bengaluru zone, SWR. During its three year tenure, IRSDC achieved little but reportedly planned several projects and was waiting for permissions from the railways. Nearly two years on, it is not clear if any of these planned projects have materialised under the SWR.

KSR’s congestion problems were to be solved by Yeshwantpur, Cantonment, and SMVB, but the delays in developing the latter stations have further hit the main city station. In 2019, SWR promised that most trains would originate or terminate in these three stations by 2022 to reduce the burden on KSR.

The railways department announced that SMVB would be ready by 2020, while Yeshwantpur would be converted into a “mega terminal” by 2022 at the cost of 120 crore and Cantonment would have four additional platforms within the same timeline, along with a suburban railway terminal for which 37.4 crores was already sanctioned.

Inside Cantonment railway station
Plans to revamp KSR, Yeshwantpur and Cantonment railway station have been delayed several times. Pic: Pranchiyettan via Wikimedia Commons

Instead, SMVB was undergoing design changes while no new developments happened at Cantonment. Yeshwantpur was given a mini makeover at the cost of 12 crores in 2021. This included additional AC rooms, an amphitheatre, wide access roads and parking facilities, landscaping, and inexplicably a large metal sculptural element at the entrance. What the SWR did not add was additional platforms or resolve signalling issues, so that more trains could be shifted from KSR as per their promise.


Read more: A guide to traveling with pets on Indian Railways


While SMVB has finally become operational with 29 trains originating and terminating here, passengers face several difficulties accessing this station. None of the other railway stations have even really taken off yet.

The airport’s quick deliverables on projects

In contrast, the Kempegowda International Airport (KIA), which appears to serve as the aspiration for the railways, has made fairly steady progress on their project. As air traffic and passenger footfall increased, Bengaluru International Airport Limited (BIAL) began making plans for a second terminal at the airport.

The initial plans were created in 2015, architects hired in 2018, construction began in 2019 and Phase 1 was unveiled in 2022. BIAL claims that the airport will begin operations in 2023, though it is not clear when Phase 2 of the new terminal will be ready.

We must hope that the railways aspire not just for the airport’s look but also timeframe to complete these projects. Because where the airport currently sees around 16 million passengers annually and the new terminal can cater to 25 million more passengers, KSR city station in its current state caters to over 90 million people and Yeshwantpur to over 35 million people.

Railways information

  • Visit this website if you want to reach out regarding queries on railways or email Shyam Singh , Div. Rly Manager at drm@sbc.railnet.gov.in, or call A.N. Krishna Reddy, Public Relations Officer, on 080-22874670.

Also read:

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

,

Maharashtra cities need a mobility fix: Building roads not a solution

Mumbai and other urban centres in Maharashtra have seen a surge in vehicle ownership, while public transport needs have not been met.

Maharashtra, one of India’s most urbanised States, faces a transportation crisis that has snowballed into a public health, environmental, and economic challenge. With over half its population residing in urban areas, Maharashtra is home to 28 municipal corporations — the highest in the country. Cities like Mumbai and Pune are struggling with the relentless surge in vehicle ownership, which has led to traffic congestion, alarming pollution levels, and a steep rise in road crashes.  Despite these pressing concerns, many cities have pursued an approach focused on expanding road infrastructure, relying on flyovers and highways to absorb traffic overflow. However, experts…

Similar Story

Walkability and affordable transit ignored as elections focus on big projects in Mumbai

Political parties are harping on big-ticket projects, while hardly anyone is focusing on the city's lifelines — BEST and railways.

As the Maharashtra state elections get underway, the daily struggles of Mumbai's citizens, especially their commuting woes, seem to be overlooked in the electoral discourse. Political parties are focusing on massive infrastructure projects, sidelining the city's lifelines like the Railways and the Brihanmumbai Electric Supply and Transport (BEST) Undertaking in favour of the Metro Rail. Despite being partially operational, the Metro has yet to make a significant impact. Surveys reveal that 52% of Mumbaikars walk to work, yet on many roads, pedestrian infrastructure remains neglected, encroached upon, and unusable. While traffic congestion has made commuting a nightmare, trains are perennially…