Work on Meistripalya Kere starts, to finish by early 2014

After years of litigation and delay, BDA is starting the re-development of Meistripalya Lake in the heart of Koramangala.

Several years of efforts by Koramangala citizens bore fruit on Friday, 12-July-2013 when a Bhoomi Puja was held to mark the start of re-development work on Meistripalya Lake in Koramangala.

Bhoomi puja for Meistripalya Lake re-development, by BTM Layout MLA Ramalinga Reddy, Koramangala corporator Kokila Radhakrishna and other officials. Pic: Srinivas

The work, estimated to cost Rs 175 lakhs, is based on a  Detailed Project Report (DPR), developed by the BDA and Lake Development Authority using inputs furnished by Koramangala citizens. Over the years, a number of elected representatives and officials have played a major role in bringing the project to fruition.

The 11 acre Mestripalya lake bed was embroiled in litigation between the BDA and a litigant who claimed ownership rights over it. In the early 80s the government had acquired vast tracts of land in Koramangala, including the Meistripalya Kere, that happened to be a public tank.  The lake itself was not ‘acquired’, in that sense, but the original owner claimed that the land was his, and went to court to reclaim it.

It was a group of active citizens of Koramangala who took the initiative to move the Supreme Court in the matter — it was a great victory for the citizens of Koramangala when the Supreme Court ruled in 2010 that the BDA would be the owner of the land and the land be protected as an open space and developed as a lake. The Laxman Rau Committee report of 1986 had already declared that the breached tank bed should be developed as a Forest area.

Meistripalya topology map

Meistripalya mentioned in the Survey of India topology map, 1970-71

After the legal victory, the role of the citizens did not end. A group of Koramangala residents got together a group of technical experts to make a detailed plan on how to rejuvenate the lake. The technical group included Dr. Harini Nagendra,  Urban Ecologist, Dr. S Subramanya, Entomologist & Ornithologist, Rohit Marol,  Landscape Architect, Ramesh Sivaram, Environmental Engineer, Manvel Alur, Environmental Specialist, Manjunath, Socio Economic Analyst, and Muralidhar Rao, Coordinator. They worked closely with the Lake Development Authority and BDA which brought out the final DPR.

Though the DPR was ready a year and a half ago, the execution could not proceed till now, as the land survey had to be first completed by the revenue department  

Rajeev Chandrashekar, MP was instrumental in opening the doors of the bureaucracy in BDA and enabling a strong citizen participation in the technical, environmental and sociological aspects of the Mestrikere restoration project. Former BDA and BBMP commissioner, H Siddhiah also played a major role in easing the roadblocks to the project at different points of time.

With all the plans in place now, the lake should have sufficient water for 365 days in the year. Plans are also in place to build a waste water treatment plant to treat the sewage, build a tree arboreum and encourage a sunbird corner.

The Bhoomi Puja function was inaugurated by Ramalinga Reddy, Minister for Transportation, Government of Karnataka in the presence of Kokila Radhakrishna, Corporator, Ward 151, Nayak, BDA Engineer from BDA, and other officials from the BBMP, BWSSB and BDA.

Talking to the residents, Ramalinga Reddy promised that the development work would be completed in a timely manner. Nayak mentioned that they plan to complete work in 9 months.

Residents hope to see the work moving ahead in the next few months with BWSSB’s task being moving sewage lines, BDA’s responsibility for civil works and BBMP taking care of drains and water channels.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Garudachar palya: The “hot spot” in Whitefield’s IT Hub

Examining the heat island effect in densely built-up Garudachar Palya ward in Whitefield’s IT Hub, which also has limited tree cover.

Garudachar Palya is part of Mahadevapura constituency, with an area of 6.5 sq km, which includes four revenue villages — Garudachar Palya, Hoodi, Seegehalli, and Nallurahalli. These villages have stayed mostly the same, while the city has expanded around them with more organised development from the BDA. This mismatch has led to issues like narrow village lanes becoming crowded with traffic, as they’re now used as shortcuts to bypass main roads. Looking at population growth, between 2011 and 2024, the ward has seen an estimated increase of 62.24%. This rapid growth adds to the existing strain on infrastructure. Ward no…

Similar Story

Saving Dwarka Forest: Citizens approach apex court to protect forest land near Delhi airport

Delhi’s Dwarka Forest has seen brazen destruction thanks to a railway redevelopment project. A recent SC stay order has raised hopes.

According to a recent World Bank report, India presently accounts for a meagre 1.8% of the global forest cover. Even more concerning is the fact that an enormous ‘46,759 acres of forest-land have been sanctioned for mining’ across the country, over the course of the last five years, by the Ministry of Environment, Forest and Climate Change (MoEFCC) itself. According to many ace climate scientists and researchers, our planet has already hit “the tipping point”. In this backdrop, the people’s struggle to save Dwarka Forest, one of the last remaining natural forest lands in a choking capital city, is a…