Union govt is boosting suburban rail in Bengaluru, State needs to step up

Once the State and Railways get on the same page on suburban rail, it will be a matter of a few months to see real progress. How much time before this happens?

Suburban Rail as a mass urban transport has a big role to play in controlling Bengaluru’s traffic. This project has been crawling for more than a decade. The proposals for this came well before 2010. During last few years, due to pressure from different corners and follow ups, the project has been taken up seriously by both GOK and Ministry of Railways on cost sharing basis.

Unfortunately Government of Karnataka (GoK) is very slow in taking this forward. The priorities of Railways are for intercity trains and goods train movement. So the government needs to go a step further to work with Railways.

Many feasibility reports have been submitted by Railway Infrastructure Technical & Economic Services (RITES) to Government of Karnataka and Railways on suburban railways. Currently suburban rail in Bengaluru has been provided on the existing rail infrastructure with MEMU and DEMU rakes, and carries more than 2 lakh commuters.

In the last two years, Railways has given importance to augmenting rail infrastructure in Bengaluru in terms of coaching terminals, doubling and quadrupling, electrification and automatic signaling system. These should lead finally to running of EMU coaches as full-fledged suburban trains. Potential of suburban trains is more than 25 lakh commuters per day at minimal cost. Benefits of suburban rail will start flowing when the capacity is expanded.

Initially the Railway Ministry was reluctant to run suburban rail in Bengaluru, but was forced to take it up after push from citizens and elected representatives. In the recent Union Budget, funds allocation for Bengaluru has substantially increased, and is close to Rs 400 crore. Following projects with detailed funds provided for execution :

Project Money allocated
Doubling of Yeshwanthpur – Channasandra Rs 42 crore allocated ( Project cost 150 crore )
Doubling Baiyyappanahalli —Hosur Rs 82 crore allocated (Project cost Rs 340 crore)
Doubling Yelahanka – Penukonda Rs 100 crore  
Quadrupling Cantonment — Whitefield Rs 50 crore allocated (Project cost Rs 480 crore)
3rd Coaching Terminal at Baiyappanahalli Rs 20 crore (Project cost Rs 116 crore)
Bengaluru Suburban Rail Rs 10 crore
Electrification of Bengaluru – Omalur via Hosur (196 rkms) Rs 70 crore
Electrification of Chikkabanavara – Hubli ( 456 rkms) Rs 162 crore

More work needs to be done

Other major works which need attention are, 1) Automatic Signaling system  2) Level-crossing eliminations  3) Newly identified halt stations 4) Doubling and electrification of Devanahalli Railway line.

The State and Ministry of Railways have been unable to solve the differences on SPV formation, thus contributing to more delays. Once the State and Railways get on the same page on suburban rail, it will be a matter of a few months to see real progress. The commissioning of SPV will be a major step towards suburban rail. Good news is that railway works related to capacity and technology upgradation have begun in right direction, with substantial fund allocation.

Integration with other modes of public transport is the key in this game changer for city traffic. Government of Karnataka needs to give seriousness in integrating multi-modal transport system and there should not be any excuses on account of  interdepartmental coordination, funds and design aspects.

Once the already sanctioned projects are completed, the capacity of suburban rail will substantially increase and will help Railways to run more suburban services. This will enable more than 8 lakh commuters to use suburban rail services. Elevated rail corridor may take a few more years to realize under Special Purpose Vehicle (SPV). Railways and Government of Karnataka should take up small investment projects to enhance the capacity and provide good suburban rail services without burdening the finances of Railways and the State.

New halt stations like Hoodi and Krishnadevaraya under Member of Parliament Local Area Development (MPLAD) funds have given a new model to the funding pattern of rail infrastructure. Every MP of Rajya Sabha and Lok Sabha representing Bengaluru Metropolitan Region should take up developing new halt stations under MPLAD funds, which can help suburban rail see real progress.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

झोपडपट्टी पुनर्वसन प्राधिकरण कायद्याच्या चौकटी बाहेर : जय भीम नगरच्या रहिवाश्यांनी कुठे जायचं?

या मालिकेच्या पहिल्या  भागात, आपण बघितले  कि कशी जय भीम नगरच्या रहिवाश्यांची घरं पाडली गेली आणि त्या ठिकाणी असलेल्या हिरानंदानी गार्डन्सच्या कायदेशीरदृष्ट्या संशयास्पद इतिहासाचा आढावा घेतला. ५ ऑक्टोबर रोजी, मुंबई उच्च न्यायालयाच्या शिफारशीनुसार पवई पोलिसांनी बीएमसीच्या एस वॉर्डमधील अधिकाऱ्यांवर, हिरानंदानी ग्रुप (HGP Community Pvt Ltd) आणि चार सहकाऱ्यांवर जय भीम नगरमध्ये अनधिकृत पाडकाम केल्याबद्दल एफआयआर नोंदवला. आरोपींवर गुन्हेगारी कट, सार्वजनिक सेवकाने इजा करण्याच्या उद्देशाने चुकीचा दस्तऐवज तयार करणे आणि खोटी माहिती पुरवणे यांसारख्या आरोपांचा समावेश आहे. पाडकामापूर्वी जय भीम नगरमध्ये राहणाऱ्या ६०० -६५० कुटुंबांपैकी सुमारे १००-१५० कुटुंबे अजूनही तिथे राहत आहेत. मागील काही महिन्यांत तीव्र पावसाचा सामना करत राहिलेल्या या…

Similar Story

Bengaluru’s misplaced priorities: Tunnel road, sky-deck and expressways

A petition to the state to avoid costly projects such as the Tunnel Road and sky deck, as many basic needs of the city remain unmet.

The Karnataka Cabinet has cleared two big-ticket projects: Tunnel Road and Sky-Deck. The BBMP’s DPR for the Bengaluru Tunnel Road is for a six-lane, 18-kilometre underground tunnel that will connect Hebbal in the north to the Central Silk Board junction in the south. The project is estimated to cost around Rs 16,500 crore. The proposed 250-metre-high sky deck, supposed to become the tallest tower in South Asia, is estimated to cost Rs 500 crore. The tunnel roads may be extended, there may be other expressways, flyovers, double-decker roads, etc., in the pipeline. All these projects taken together are expected to…