Union govt is boosting suburban rail in Bengaluru, State needs to step up

Once the State and Railways get on the same page on suburban rail, it will be a matter of a few months to see real progress. How much time before this happens?

Suburban Rail as a mass urban transport has a big role to play in controlling Bengaluru’s traffic. This project has been crawling for more than a decade. The proposals for this came well before 2010. During last few years, due to pressure from different corners and follow ups, the project has been taken up seriously by both GOK and Ministry of Railways on cost sharing basis.

Unfortunately Government of Karnataka (GoK) is very slow in taking this forward. The priorities of Railways are for intercity trains and goods train movement. So the government needs to go a step further to work with Railways.

Many feasibility reports have been submitted by Railway Infrastructure Technical & Economic Services (RITES) to Government of Karnataka and Railways on suburban railways. Currently suburban rail in Bengaluru has been provided on the existing rail infrastructure with MEMU and DEMU rakes, and carries more than 2 lakh commuters.

In the last two years, Railways has given importance to augmenting rail infrastructure in Bengaluru in terms of coaching terminals, doubling and quadrupling, electrification and automatic signaling system. These should lead finally to running of EMU coaches as full-fledged suburban trains. Potential of suburban trains is more than 25 lakh commuters per day at minimal cost. Benefits of suburban rail will start flowing when the capacity is expanded.

Initially the Railway Ministry was reluctant to run suburban rail in Bengaluru, but was forced to take it up after push from citizens and elected representatives. In the recent Union Budget, funds allocation for Bengaluru has substantially increased, and is close to Rs 400 crore. Following projects with detailed funds provided for execution :

Project Money allocated
Doubling of Yeshwanthpur – Channasandra Rs 42 crore allocated ( Project cost 150 crore )
Doubling Baiyyappanahalli —Hosur Rs 82 crore allocated (Project cost Rs 340 crore)
Doubling Yelahanka – Penukonda Rs 100 crore  
Quadrupling Cantonment — Whitefield Rs 50 crore allocated (Project cost Rs 480 crore)
3rd Coaching Terminal at Baiyappanahalli Rs 20 crore (Project cost Rs 116 crore)
Bengaluru Suburban Rail Rs 10 crore
Electrification of Bengaluru – Omalur via Hosur (196 rkms) Rs 70 crore
Electrification of Chikkabanavara – Hubli ( 456 rkms) Rs 162 crore

More work needs to be done

Other major works which need attention are, 1) Automatic Signaling system  2) Level-crossing eliminations  3) Newly identified halt stations 4) Doubling and electrification of Devanahalli Railway line.

The State and Ministry of Railways have been unable to solve the differences on SPV formation, thus contributing to more delays. Once the State and Railways get on the same page on suburban rail, it will be a matter of a few months to see real progress. The commissioning of SPV will be a major step towards suburban rail. Good news is that railway works related to capacity and technology upgradation have begun in right direction, with substantial fund allocation.

Integration with other modes of public transport is the key in this game changer for city traffic. Government of Karnataka needs to give seriousness in integrating multi-modal transport system and there should not be any excuses on account of  interdepartmental coordination, funds and design aspects.

Once the already sanctioned projects are completed, the capacity of suburban rail will substantially increase and will help Railways to run more suburban services. This will enable more than 8 lakh commuters to use suburban rail services. Elevated rail corridor may take a few more years to realize under Special Purpose Vehicle (SPV). Railways and Government of Karnataka should take up small investment projects to enhance the capacity and provide good suburban rail services without burdening the finances of Railways and the State.

New halt stations like Hoodi and Krishnadevaraya under Member of Parliament Local Area Development (MPLAD) funds have given a new model to the funding pattern of rail infrastructure. Every MP of Rajya Sabha and Lok Sabha representing Bengaluru Metropolitan Region should take up developing new halt stations under MPLAD funds, which can help suburban rail see real progress.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

The fight over Jai Bhim Nagar: Whose land is it, anyway?

Settlers in Jai Bhim Nagar in Powai’s Hiranandani Gardens were forcefully evicted in June. And it’s a contentious move in more ways than one.

A tarp-covered shed on a busy sidewalk in Powai lights up every evening with the cacophony of children. The ‘sabki library’ is a makeshift after-school space for the children of Jai Bhim Nagar living on the sidewalk, where they show up diligently to study with volunteers from nearby IIT Bombay.  The library was set up there over three months ago, soon after the Jai Bhim Nagar settlement was demolished, and its residents forcibly evicted. While many residents from the 600-odd homes have shifted elsewhere since then, about 150-200 families still live on the streets surrounding the demolished slum. “We have…

Similar Story

Mumbai infrastructure report card: How have big ticket projects fared in last five years?

As elections approach, political parties try to gain mileage from recent infrastructure projects. But are Mumbaikars convinced?

Several infrastructure projects have been launched or inaugurated in Mumbai over the last five years, in the backdrop of huge political upheavals in Maharashtra with unexpected alliances, fractured coalitions, and the overthrow of the Maha Vikas Aghadi (MVA) by the Eknath Shinde-led Mahayuti. Celebrated as an engineering feat, the Mumbai Coastal Road, named Dharmveer Swarajya Rakshak Chhatrapati Sambhaji Maharaj Coastal Road, was inaugurated by chief minister Eknath Shinde with deputy chief ministers Devendra Fadnavis and Ajit Pawar on 11th March. This is amongst the major infrastructure projects that have been completed in the past five years and being counted as one…