Explainer: How Bengalureans can generate rooftop solar power in their homes

The author's home rooftop solar system was set up on February 4th afternoon, and since then has produced 355 units of electricity as of February 28th.

Global warming due to increasing carbon footprint is a major challenge to environmental sustainability. The use of fossil fuels, such as coal, for power production is among the major causes of carbon dioxide emissions. Currently, Karnataka generates 61.5% of its power requirement through thermal stations that use coal as fuel.

Though we have one of the world’s third largest solar power plants, the Pavagada Solar Park Palavalli in Tumkur district, only 0.11 % of the state’s power requirement is met through solar energy. There is, however, huge potential to generate power through large rooftop surface areas with sunshine, which is as yet untapped.

It is advisable, therefore, that homes move to an ‘on-grid solar rooftop system’. The easiest way is for homes to meet their own power needs and export the excess units to BESCOM. My home system of 2.9 KW with Tata Solar ‘Mono Perc Half cut 144 cells DCR’ panels and Growatt string inverter were commissioned and synchronised on February 4th afternoon, and since then has produced 355 units of electricity as of February 28th.

India as a responsible nation has pledged that by 2030, 40 % of its power requirement will be through renewable energy sources such as solar energy, wind energy etc. Moving to solar energy is a great opportunity for a tropical country like ours to generate low-cost power and also save the environment.

The feasibility of moving to solar energy

The one-time investment after subsidy (Rs 44,500) could be about Rs 1.8 to 1.9 lakh for a 3 kW (all-inclusive, current technology-Mono Perc DCR module) system that could generate nominally about 430 units per month. So, apart from the contribution to reducing carbon footprint, the financial returns are around 20%, per annum, through savings of the current bill.

There are, therefore, compelling reasons for every house and apartment to move to solar energy.

How to install a home solar system

Junction box for rooftop solar power.
Junction box for rooftop solar power. Pic: Kochu Sankar G

The first step is to decide on the capacity needed. For this, the following are key considerations:

  • BESCOM-approved load: You are allowed to install it on the grid system only up to your approved load capacity.
  • Monthly consumption: Decide this based on the maximum, and an average number of units per month, and plan for future needs (say additional gadgets, EV etc.).
  • Shadow-free rooftop space available: You will need roughly 100 Sq ft area / KW.

BESCOM/MNRE Empanelled Solar vendors do provide free consultations, but it is always better to cross-check once with other experts.

Power generation graphic.
Dashboard for Solar power generation. Pic: Kochu Sankar G

Read more: You too can build a sustainable home, just do as this former submariner did


Next step: Apply for the Soura Gruha Yojane (SGY) scheme on the National Portal

Residents can directly register on the National portal using the BESCOM consumer number and registered mobile number, and file an application in simple steps instantly, and upload the latest BESCOM bill.

Once that application is submitted, intimation goes to the BESCOM Divisional office to conduct the feasibility and give approval. Your BESCOM Assistant Engineer /Junior Engineer will visit your premises to inspect and upload his report within one week. If not done automatically, you may contact your local BESCOM Assistant Executive Engineer and get it expedited. Once you find it uploaded, the installation can be done.

In the portal, you may also find a list of 35 empanelled vendors, you may choose three to four of them from your neighbourhood and take quotes, negotiate with the most reliable brands with a proper price and finalise.

Once the order is placed, the vendor will work with you to take forward the rest of the processes, such as getting and uploading the inspection report, commissioning/net meter synchronisation etc.

I was interacting with BESCOM officials directly and did not have to pay any bribes at all. Our divisions AEE, AE and JE have been very upfront and enthusiastic about the project and professionally supported us. Do not get carried away by the demands of some middlemen and agents.

6 steps to follow to apply for subsidy under the Soura Gruha Yojane (SGY) scheme.
Steps to apply for subsidy under the Soura Gruha Yojane (SGY) scheme. Pic courtesy: MNRE portal

Read more: How Century Saras put sunshine to best use


Tips:

  • The vendor needs to be with you till the time the defect-free subsidy claim is made by you, and then acknowledged and accepted by the Ministry of New & Renewable Energy(MNRE).
  • The MNRE system is transparent and the portal gives you regular updates.
  • The current program as of now is open for applications till March 31 2030.
  • There are also thousands of residents who applied in 2020-21 on the BESCOM portal under the earlier scheme, which was dormant for two years, and now they can also avail of the benefits as the implementation of that scheme is also happening now, through 3 BESCOM empanelled vendors.

Also read:

Comments:

  1. SIVARAMAN HARIHARAN says:

    Appears BESCOM is slow & appears to be discouraging SOLAR ROOF TOP. They need to first practice , before they preach for others. I am trying for 2nd SOLAR SYSTEM since Nov 16th 2022, no proper response from them till date.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Opinion: Why climate action must recognise and include India’s informal workers

As COP29 discusses ways to mitigate the climate crisis, India must address the adversities faced by informal workers and chalk out plans.

The ongoing COP29 conference in Baku, is a pivotal moment in climate action, focusing on global cooperation to limit warming to 1.5°C. Key priorities include mobilising financial resources for developing countries to submit ambitious climate plans (NDCs) by 2025 and continuing support through the Fund for Loss and Damage (FRLD) established at COP28. COP29 also aims to strengthen adaptation efforts by setting finance-backed targets for the Global Goal on Adaptation.  While COP29 primarily focuses on international climate initiatives, India must address pressing domestic issues. One key group often overlooked is informal workers in Indian cities. Over 80% of India’s urban…

Similar Story

Status check: Key concerns remain as Chennai moves ahead with WTE plans

Greater Chennai Corporation's tender for the Waste-To-Energy plant is at the final stage; Here is what we know about the bidders

17,422 metric tonnes per day — that's the staggering amount of trash the Greater Chennai Corporation (GCC) will generate in 30 years. Currently, Chennai produces 6,143 metric tonnes of waste daily, which adds to the growing piles in Kodungaiyur and Perungudi dump yards. Like many other major cities, GCC is struggling to find a sustainable solution for waste management and has proposed a Waste-To-Energy (WTE) plant. However, the experiences of cities like Delhi are testimony to the significant environmental and health impacts of WTE plants. A recent The New York Times investigative report on the Delhi WTE reveals: "The government…