What it takes to get a skywalk in Bengaluru

Citizens' efforts in the last few years got BBMP to take pedestrian safety seriously and build skywalks. Here’s the story of one skywalk on ORR.

Last month, in December 2021, a new skywalk came up on Outer Ring Road, near New Horizon College, Kadubeesanahalli, built by Embassy Tech Park. Coming as it did, after a long period of no new skywalks being opened, it threw the spotlight on the importance of skywalks.

In the recent past, BBMP has built a number of skywalks across the city under the PPP (Public-Private Partnership) model, which affected the final decisions on their locations and designs. However the overhead pedestrian crossings on Outer Ring Road have become a reality, largely due to citizen activism.  The Sanjay Giri skywalk, between Akme Harmony Apartment and Cloudnine Hospital in Bellandur, is a well-known success story. The skywalk finally came up in 2019, due to the relentless efforts of citizen group Bellandur Jothege.


Read more: Elected reps promise solutions for Bellandur pedestrians


How the Sanjay Giri skywalk came to be

It all started in 2017, when local citizens got involved, to ensure pedestrians could cross the road safely. Crossing the road is a challenge common across the long stretch of Outer Ring Road – especially from Bellandur to Mahadevapura. In November 2017, Sanjay Giri, a 19-year old security guard of Akme Harmony Apartment died after a car hit him while he was crossing the Outer Ring Road. 

Residents of apartments in the neighbourhood decided to take action. In August 2017, they got together to organise a poster campaign. When the poster campaign didn’t get the attention it needed, they called for a protest and human chain which finally got the attention of officials. Kishori Mudaliar and other active citizens in the neighbourhood formed Bellandur Jothege to push for pedestrian-focused solutions.

Kishori says, “We invited resident welfare associations in Bellandur, collected signatures, and Mukund Kumar (a resident of the neighbourhood) met PC Mohan (MP), who we invited. That’s when MLA Arvind Limbavali (also) attended.”

The protest, demanding a skywalk, organised by Bellandur Jothege
The protest, demanding a skywalk, organised by Bellandur Jothege. File pic

Citizen pressure and MLA’s push got BBMP to approve the skywalk plan. The skywalk was formally inaugurated in 2019, and was named after the young security guard who had lost his life.

Infrastructure construction takes years

With citizen demand increasing over the years, many skywalks had been approved on ORR. But many reasons like requirements of NOC from BMRCL, lack of responses to tenders, election code of conduct, or even unavailability of MLA for bhoomi pooja have delayed such projects. 

It took two years for the Sanjay Giri skywalk to come up. Naresh Sadavisan, a former Bellandur resident, puts this down to the BBMP not prioritizing pedestrians. “Heavy vehicles and four wheelers are privileged over pedestrians. And this is just not restricted to skywalks, this is part of a larger thought process of planning, consequently, pedestrians have little place to walk across.” Bellandur Jothege even came up with the idea of Bellandur Walks. Naresh says, “Between the Sarjapur junction and Kaikondrahalli, in pre-pandemic times, based on anecdotal evidence, it is reasonable to believe that out of the six lakh commuters, 30%  of the population live within a four kilometer radius. We wanted to conduct a four kilometer trial pilot walk but the city did not act on it.” 

Naresh points out another lacuna i.e. little coordination among civic bodies. “ORR is part of the Major Roads division while the inside is part of Ward roads, the two don’t talk to each other. Also BWSSB doesn’t align with BBMP’s plans. It was only after civic protests and unfortunate deaths that the BBMP and local MLAs agreed to a skywalk.”

Inauguration of skywalk in December 2021, on Outer Ring Road, near New Horizon College, Mahadevapura assembly constituency.
Inauguration of skywalk in December 2021, on Outer Ring Road, near New Horizon College, Kadubeesanahalli, Mahadevapura assembly constituency, built by Embassy Tech Park. Pic: MLA Arvind Limbavali/Twitter

Kishori says this experience helped her understand how the process worked. “The Sanjay Giri skywalk paved the way for six more skywalks in Bellandur/ORR, of which five have been completed while one is pending.” 

Kishori says that the impact Bellandur Jothege had in building skywalks are in terms of design intervention, a change in mindset, and bringing pedestrian safety in the civic agenda.


Read more: Why Bengaluru should invest in pedestrian infrastructure


According to some Bengalureans, skywalks don’t serve much use as pedestrians run across the road and don’t use skywalks. To this, Naresh says: “Pedestrians will use it if it is convenient. If it is properly maintained and all the facilities are available and if all three factors of locality, safety and purpose are served then they will use it. The difference is between poorly thought out skywalks versus well thought out skywalks. Maintenance of skywalks is very important but even for that there is hardly any budget.” R K Misra, co-founder of Yulu, also says skywalks must have facilities such as lifts and ramps so that they are easily accessible for pedestrians.

Pedestrian road crossing facilities can include Zebra crossings at junctions, High Raised Pedestrian Crossing (HRPC), Medians and Refuge Islands, Skywalks/foot overbridge and subways. The decision for the right type of crossing has to be based on road characteristics — road, footpath and median widths, traffic composition- traffic volume and type of vehicles and their speed, pedestrian traffic volume, land use pattern, and local resident surveys.

While plans like Comprehensive Mobility Plan for Bengaluru (CMP-2020) prepared by BMRCL and DULT proposed location for skywalks, the ground reality is rarely aligned to such plans.

The deciding factor for skywalks: Who pays?

In the last decade, BBMP has constructed over two dozen overhead walkways, most under the PPP model. 54 had been approved, as can be seen in this list.

BBMP expects skywalks to be built as a private-public project, where the advertiser pays for the infrastructure and makes up the investment through ad revenues. This often means the location of skywalks are often decided based on where investors can maximise their revenue, rather than pedestrian need.

Clement Jayakumar, a member of citizen group Doddanekundi Rising, says that the Bruhat Bengaluru Mahanagara Palike (BBMP) does not take pedestrian-friendly infrastructure as seriously as it ought to and therefore, citizens often help identify issues where there is maximum crossing of people and high traffic speed. “The interest is not there (to build) in the spot where we need the skywalk, the prioritization is not aligned with pedestrian infrastructure. This is because if it is not a commercially viable spot then advertising agencies are not interested in investing in it.”

Inauguration of skywalk at Innovative Multiplex, Outer Ring Road near Marathahalli, built in the Public and Private Partnerships (PPP) scheme.
Inauguration of skywalk at Innovative Multiplex, Outer Ring Road near Marathahalli, built in the Public and Private Partnership (PPP) Scheme. Pic:  MLA Arvind Limbavali/Twitter 

RK Misra, who has been actively engaged in urban issues and has advised governments, says, “Skywalks have only been successful when citizens have identified the locations where it should be built. Citizens take into consideration the actual needs of the area/locality. Usually, if skywalks are built out of commercial exploitation that it has not been of much use.” 

Clement says that the Private-Public Partnership (PPP) can be one option but not the only option. “If BBMP doesn’t get any tender bids within three months then they should convert it into self funding. If funding is an issue let them leave other BBMP work, like asphalting of roads, and focus on pedestrian infrastructure.”

Like in the case of the Sanjay Giri skywalk, most other skywalks on the stretch have been PPP projects or have had the cost borne by the business groups on the road like Outer Ring Road Companies Association (ORRCA) or the Embassy Tech Park.

What does the future hold for ORR’s skywalks?

Now with the Metro construction initiated on Outer Ring Road, the existing walkways are at risk. They are expected to be dismantled, and restructured to integrate with the Metro’s viaduct. When and how it happens, at what inconvenience to commuters and pedestrians on the road, remains to be seen.

[Corrigendum: Errors regarding the chronology of events organised by citizen groups have been corrected. An error regarding the funding source of Sanjay Giri skywalk has also been corrected.]

Also read:

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

झोपडपट्टी पुनर्वसन प्राधिकरण कायद्याच्या चौकटी बाहेर : जय भीम नगरच्या रहिवाश्यांनी कुठे जायचं?

या मालिकेच्या पहिल्या  भागात, आपण बघितले  कि कशी जय भीम नगरच्या रहिवाश्यांची घरं पाडली गेली आणि त्या ठिकाणी असलेल्या हिरानंदानी गार्डन्सच्या कायदेशीरदृष्ट्या संशयास्पद इतिहासाचा आढावा घेतला. ५ ऑक्टोबर रोजी, मुंबई उच्च न्यायालयाच्या शिफारशीनुसार पवई पोलिसांनी बीएमसीच्या एस वॉर्डमधील अधिकाऱ्यांवर, हिरानंदानी ग्रुप (HGP Community Pvt Ltd) आणि चार सहकाऱ्यांवर जय भीम नगरमध्ये अनधिकृत पाडकाम केल्याबद्दल एफआयआर नोंदवला. आरोपींवर गुन्हेगारी कट, सार्वजनिक सेवकाने इजा करण्याच्या उद्देशाने चुकीचा दस्तऐवज तयार करणे आणि खोटी माहिती पुरवणे यांसारख्या आरोपांचा समावेश आहे. पाडकामापूर्वी जय भीम नगरमध्ये राहणाऱ्या ६०० -६५० कुटुंबांपैकी सुमारे १००-१५० कुटुंबे अजूनही तिथे राहत आहेत. मागील काही महिन्यांत तीव्र पावसाचा सामना करत राहिलेल्या या…

Similar Story

Bengaluru’s misplaced priorities: Tunnel road, sky-deck and expressways

A petition to the state to avoid costly projects such as the Tunnel Road and sky deck, as many basic needs of the city remain unmet.

The Karnataka Cabinet has cleared two big-ticket projects: Tunnel Road and Sky-Deck. The BBMP’s DPR for the Bengaluru Tunnel Road is for a six-lane, 18-kilometre underground tunnel that will connect Hebbal in the north to the Central Silk Board junction in the south. The project is estimated to cost around Rs 16,500 crore. The proposed 250-metre-high sky deck, supposed to become the tallest tower in South Asia, is estimated to cost Rs 500 crore. The tunnel roads may be extended, there may be other expressways, flyovers, double-decker roads, etc., in the pipeline. All these projects taken together are expected to…