Why Cauvery Stage IV water has reached Bangalore, but not your home

How much of water from the Cauvery Stage IV, Phase II is reaching citizens? Which areas are getting it? If your area is supposed to be covered and you are still not getting water, here’s why.

Residents of Sobha Daffodil apartment in HSR Layout Extension have been waiting for water for the last 4-5 months. They had paid around Rs 10 lakh to the BWSSB for water from Cauvery Stage IV Phase II project; they got pipelines laid and meters fixed. But no water comes here yet.

Pic courtesy: BWSSB.org

“We paid a few crores some 3-4 years back too, for water. In the last few months, we went to the local BWSSB office some 10 times. Every time, we were told that water will come the next day or next week, but there has been no supply,” says a member of the apartment owner association here, on condition of anonymity.

Cauvery Stage IV project was supposed to have met the water needs of CMC areas in the city. About 500 MLD (Million Litres per Day) was supposed to come, but not even half of this is reaching the city now. BWSSB says that only 220 MLD is coming from the scheme. The project was commissioned on October 31st last year.

Stage IV water is supposed to be for the 7 CMCs and Kengeri TMC that merged with BBMP in 2007, not including the 110 villages.

Overall, there are some 43,600 new connections in the city that are getting Stage IV water.

Why the delay

There are two main reasons for the delay – one that many people are not taking new Cauvery connections yet, and two, that the Board has not completed pipe laying in all areas yet. Because of this, a large number of people who have already paid for the new connections, are still water-starved.

Stage IV water is supposed to be for the 7 CMCs and Kengeri TMC which were added to the city corporation limits in 2007. There were 110 villages also that were added to BBMP at the time; these villages are not supposed to get the new water.

BWSSB has nine divisions in Bangalore, of which north, north west and east divisions are getting the highest amounts of Stage IV water. Overall, there are some 43,600 new connections in the city that are getting Stage IV water. Some of the new water goes to old connections too, augmenting existing supply.

Here are areas that get Stage IV water now and the amounts they get, by division (according to Executive Engineers of the respective divisions):

North 40 MLD Parts of Yelahanka, to Jakkur and Thanisandra in Byatarayanapura constituency, and to four wards in Dasarahalli constituency (Shettihalli, Mallasandra, Bagalkunte and T Dasarahalli).
North west 60 MLD Dasarahalli constituency, Peenya, parts of Yelahanka, Rajagopala Nagara, part of Hegganahalli, Chokkasandra, HMT ward and T Dasarahalli.
West 8 MLD Rajarajeshwari Nagar, Kengeri, Ullal, Annapoornashari Nagar, Papreddy Palya, Mallathahalli, Kengunte, Jagajyothi Layout, Jnanbharathi Layout, Ideal Homes, BEML Layout 3rd 4th and 5th stages, Pattanagare, Channasandra etc.
South 10-15 MLD Kothnur Dinne which includes JP Nagar 6th, 7th and 8th phases, Vijaya Bank Layout and Bommanahalli.
South East 25 MLD Core areas like Indiranagar, Jeevan Bheema Nagar, Domlur, Ulsoor, Thippasandra, HAL, LIC Colony, Lakshmipura etc., which have already been getting water. Existing supply is only augmented with the new water.
Central   Does not get any water from Stage IV. But once OMBR reservoir gets stage 4 supply completely, its Stage III water will be diverted to central division. This will come to 20 MLD
North East 6 MLD This division also has core areas that already get water. New water augments supply in Bhoopasandra and Nagashettihalli areas.
South West   No water from Stage IV as these are core areas. Water will get diverted here only if there is excess after all CMC areas get water.
East 40 MLD Water goes to KR Puram constituency, Mahadevpura constituency and Sarvagna Nagar constituency

 

 

Map of stage 4 water coming into reservoirs (numbers in Red). The actual quantity to be supplied, is marked next to each reservoir, along with the phrase ‘To local command area’. Click on image to zoom.

“Public has to take connections first”

In CMCs, pipelines were laid in many areas in 2005 as part of GBWASP (Greater Bangalore Water and Sanitation Project). The lines were laid, but no supply was given at the time. When people in these areas take connections, water will be released to them through these pipelines. Since road alignments had changed much and muck had clogged the pipes, much time was spent in doing trial runs to de-clog pipes and to repair damaged ones.

BWSSB Chief Engineer T Venkatraju says that, now if everyone does not take connections, water cannot be supplied even to those who have taken them. This is because the ends of these pipelines are left open near individual houses, as there are no valves to stop the flow and water will spill out if connections are not taken to the houses. Of the 1.4 lakh households that were given GBWASP connections, only 40,000-50,000 had taken connections, as of January end.

 

On why this was done, Venkatraju says, “Many of these roads are only 3m wide, and hence valves could not be fixed along the roads, when the pipes were first laid. Roads are now getting flooded when water is released.” Valves will be fixed for individual houses only when they take a connection. So unless everyone takes a connection, water will spill out through the open-ended lines.

If every single house in an area does not take BWSSB connection, water cannot be supplied to anybody. Why? The ends of these pipelines have been left open near individual houses, and water will spill out if connections are not taken to the houses.

He says that this is the case in Devasandra, which is at the tail end of the water supply system in KR Puram constituency. “For water to reach there, the people along the way, such as in Ramamurthy Nagar, have to take connections. Some 30,000-40,000 house connections were given in KR Puram constituency under GBWASP. But only 1000-2000 have applied for new connections.”

Of the 1.4 lakh households that were covered under GBWASP, only 40,000-50,000 had taken connections, as of January end.

Venkatraju says that out of the one lakh houses in the constituency, only about 10,000 are getting water from Stage IV now. Similarly, he says that, in HSR Layout only 25% of people have applied for new connections.

Experts lament this strange logic. “Mind bogglingly stupid” is how city-based water expert S Vishwanath describes laying of open-ended lines in the GBWASP project. “Now at least, BWSSB should give free connections to everyone and start charging them for monthly water consumption, instead of waiting for public to take connections. This was done successfully in places like Vijayawada earlier,” he says.

“Mind bogglingly stupid” – S Vishwanath

Vishwanath also says that BWSSB should have used the loop system of pipes, instead of the current tree-and-branch system. In the loop system, the supply lines are set up in a closed system and there are no open ends. Water is equally distributed to every point; but in the tree system, “water pressure becomes very low as it comes to the last point,” he says.

N S Mukunda of Abhyudaya, a South Bangalore-based RWA federation, says that the case of open-ended pipes show BWSSB’s severe technical incompetence. “It is not difficult to plug the end of lines, or to put valves to regulate supply to groups of houses. The GBWASP project itself was a sham – public were asked to pay for connections even without BWSSB committing to give water.”

While Venkatraju says that the Board has more than enough water and is only waiting for public to take connections, Mukunda says that BWSSB is only giving excuses. He says that the basic necessities – enough water, reservoirs/tanks with good storage capacity, and proper distribution system – do not exist. “About 45% of the water goes in leaks,” he says. The data given by BWSSB shows that, currently about 50% of water is unaccounted for.

In the month of January, BWSSB has accounted for only 6.6 lakh connections while at least 16 lakh properties are estimated to be in BBMP limits. By conservative estimates, some 33,000 Million Litres come to the city every month from Cauvery, but in January, BWSSB has accounted for only about 16,785 Million Litres. The other half of the water was lost because of leakages and illegal connections.

A BWSSB engineer says, on condition of anonymity, that unaccounted water is higher than usual now, as more water is lost due to testing and trial runs for Cauvery Stage IV.

Why are residents not applying for Cauvery connections?

Venkatraju says that people in CMC areas are not taking connections as they have been getting water from BWSSB tankers already. BWSSB says they supply borewell water to households in CMC areas for Rs 50 per month.

BWSSB has been disconnecting GBWASP house pipelines of those who are not taking new connections. This has been going on for a while, but is not being done in a large scale as it is also a difficult job; the intention is to get people to apply soon. Once the line is disconnected, the house owner will have to get the connection laid again at his own cost, after taking road cutting permission from BBMP.

The deadline for public to take new connections was January 15th, which was then extended to February 15th, and now has been stretched to March 15th, as per news reports.

Areas like JP Nagar 8th phase had not been covered under GBWASP, and most are not applying for new lines to be laid. G Jagadish, President of Federation of JP Nagar 7th and 8th phases, says, “Most people in 8th phase have individual borewells; there are also community borewells. So, many of them don’t want to spend more on new connections. In the long run, everyone has to get connections as borewell water levels are depleting, and as there are restrictions on digging new borewells now.”

Some areas are not getting water also because BWSSB is yet to complete about 25% of its pipe laying works.

Jagadish says that main lines already exist here and that only individual connections have to be taken. People here are also dissuaded on seeing that those in 7th phase, who get Stage IV supply, get water only once a week, that too for 2-3 hours. “BWSSB officers told us that water is being rationed now as summer is coming,” says Jagadish.

Some areas are not getting water also because BWSSB is yet to complete about 25% of its pipe laying works. GBWASP lines have not been fully linked with the feeder lines coming from reservoirs. This is the case in Central Jail Reservoir, which is actually supposed to supply 43 MLD to areas nearby.

As lines are not laid, no water is being supplied from here now. “This area is already getting water from Cauvery Phase 1, hence priority is low here. It is also among the outer villages that form BBMP (beyond CMC), which are anyway not supposed to be covered in Stage IV,” says Narayan, Chief Engineer (Cauvery).

Comments:

  1. sas says:

    useful maps & info; thank you for digging it out. Ideally, BWSSSB (having also used the tax payers money) should have out it on their own website.

  2. Rantjil Boulder says:

    The pipes were not laid properly. In vignan Nagar area, most of the places there are leakage and lots of cauvery water gets wasted.

  3. Muralidhar Rao says:

    Amazing incompetence!

  4. S V Raghavan says:

    There is absolutely no truth in water distribution by BWSSB.
    Consider this: Bangalore & Surrounding areas have about 10 million people ( 6 mil official).
    If avearge person consumes 50 litres ( 3 buckets) per day we require 500 million ltrs per day.
    Actually BWSSB claims to supply 10 times that in four & now five stages of Cauvery not taking TG halli.
    BWSSB delivers on every alternate day for half an hour at very low pressure in Sultanpalya, R T nagar. My bill is minimum amount for last 5 yrs. We buy water at Rs 750 a 5000 ltr tanker at least twice a month.
    We are only two members and have to buy.
    Many letters to BWWSSB chairmen have fallen in deaf ears
    This is same in all areas except where politicians live & perhaps BWSSB quarters.
    So, where does the balance Cauvery water go ????
    Water Tanker Mafia rule all ares with BWSSB linesman on take.
    Do you see the bluff BWSSB gives???

    BBMP, BWSSB,BESCOM, BDA, PDS, etc, etc, work to serve only 25% of peoples needs & makes us starve & beg for all our basic needs , EVEN WHEN WE ARE READY TO PAY.

    This story is same in all civic bodies across India !!!!

    What a Shame Indian citizens have to struggle 65 yrs after
    independence.

  5. Navin Reddy says:

    BWSSB KR Puram staff just lie on every occasion. On top of this, when we go for a new connection, a plumber authorised by BWSSB asks for 5000 Rs, as well a new connection for Rs 25,000 bribe. For whom do they think they are working for, are they not human beings and not getting salaries, Govt Servants have got into the practice of bribery (forced “BEGGING”) from innocent & hapless people, what does the Chairman do, just sit in an AC cabin & enjoy all the collections from the respective zones! Cool job in government…..(:-(

  6. Vindia says:

    In Anarayanpura there was already pipes laid for CMC water supply. To supply Kaveri water, new pipelines were laid, monumental waste of resources.

    There are at least two different types of illegal connections. One is used by those who do not have other sources of water. Other is the illegal connection to use excess amount of water or to waste water.

  7. nandini says:

    I am not able to view those 110 villages which are not receiving water. Kindly, the concerned post the same and the second thing is how was this 110 villages divided offlate. Thanks

  8. Navya P K says:

    Hi nandini, please refer this document for the list of 110 villages: http://bwssb.org/pdf/List%20of%20110%20Villages.pdf

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Opinion: Why climate action must recognise and include India’s informal workers

As COP29 discusses ways to mitigate the climate crisis, India must address the adversities faced by informal workers and chalk out plans.

The ongoing COP29 conference in Baku, is a pivotal moment in climate action, focusing on global cooperation to limit warming to 1.5°C. Key priorities include mobilising financial resources for developing countries to submit ambitious climate plans (NDCs) by 2025 and continuing support through the Fund for Loss and Damage (FRLD) established at COP28. COP29 also aims to strengthen adaptation efforts by setting finance-backed targets for the Global Goal on Adaptation.  While COP29 primarily focuses on international climate initiatives, India must address pressing domestic issues. One key group often overlooked is informal workers in Indian cities. Over 80% of India’s urban…

Similar Story

Status check: Key concerns remain as Chennai moves ahead with WTE plans

Greater Chennai Corporation's tender for the Waste-To-Energy plant is at the final stage; Here is what we know about the bidders

17,422 metric tonnes per day — that's the staggering amount of trash the Greater Chennai Corporation (GCC) will generate in 30 years. Currently, Chennai produces 6,143 metric tonnes of waste daily, which adds to the growing piles in Kodungaiyur and Perungudi dump yards. Like many other major cities, GCC is struggling to find a sustainable solution for waste management and has proposed a Waste-To-Energy (WTE) plant. However, the experiences of cities like Delhi are testimony to the significant environmental and health impacts of WTE plants. A recent The New York Times investigative report on the Delhi WTE reveals: "The government…