BBMP’s rainwater harvesting works stillborn

The city council allocated crores of rupees last year for rainwater harvesting at parks, playgrounds and BBMP buildings. What happened?

The monsoon rains are delayed this year. But by sheer coincidence, BBMP’s rainwater harvesting plans of last year remain unimplemented, almost as if the monsoons were granting their own extension to BBMP, ominously. What’s worse, a Citizen Matters inquiry revealed that the city’s accounts department declined to release funds due to the engineers’ lack of interest.

Bengaluru faces a shortage of 410 MLD (megalitre water per day) of water. The average rainfall here is 923 mms within a geographical area of 800 sq kms.  It is in this context by seeing the potential of RWH, BBMP made implementation of rainwater harvesting compulsory in all its offices, parks and playgrounds and allocated Rs 20 crores in 2011-12 budget. It also proposed to reserve 10 per cent of ward grant allocation to RWH. In addition to that, to encourage citizens, a two percent rebate in property tax also proposed in all the houses, which are having RWH units. This 2011-12 decision now seems utopia.

A BBMP official explaining how the newly installed RWH unit works.

Last month, when Citizen Matters spoke to Krishnaswamy K S, Executive Engineer of the RWH project, ahead of the nearly approaching monsoon season, he said, “We have not done any kind of works associated with RWH so far. But we have some plans and have started doing some work.” 

There is more. The 20 crore rupees allocated in the previous budget for RWH has been withheld by the BBMP Account Section due to the lackadaisical approach from the incharge engineers. The officers in-charge for RWH were supposed to submit the proposal details prior to the release of the money.

“The in-charge officers were supposed to do the site verification, tender allocation, project layout and so many other works prior to the release of the money. Nothing has been done so far. So the money has not been released,” said N V Subbanna, Chief Accounting officer BBMP.

B S Prasad, Chief Engineer for RWH at BBMP, declined to comment on the delay.

In the meantime, a new financial year has begun and the budgetary allocation of the previous year appears to have been forgotten.  Most of the flats, parks, playgrounds, offices, buildings in the city are still devoid of a RWH system.

RWH unit at BBMP head office is the biggest one.

Ironically, one RWH unit was installed at BBMP head office and at IPP (Indian Population Programme) Malleswaram office this year. Surprisingly, this project was not part of the BBMP RWH initiative. Executive Engineer L Chandrasekhar says, “The total cost of the project was Rs 35 lakhs. We have done all the works with our department money only. It does not have any connection with the 20 crore allocated for RWH in the budget.”

As our officials take a long stretch to plan and blame each other for the delay in starting the work, even the delayed monsoon rains may come and go. The city’s water problem will only be more severe in the coming days.

Comments:

  1. Shashidhar K. G. says:

    BBMP projects (east) have implemented two recharge wells in Richards Park (ward60) in 2011.This was an initiative of RTRA with the support of the local MLA Hon Prasanna Kumar.

    Shashidhar /RTRA-Richards Town Residents Association

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Bengaluru’s Peripheral Ring Road: Traffic relief or ecological disaster?

Even as landowners contest unfair compensation, other issues persist: emissions, large-scale tree felling, and the project's alignment through lake ecosystems.

Two decades after the Peripheral Ring Road (PRR) was announced, the project is far from completion. For farmers, it has meant years of uncertainty and mounting financial losses, while residents remain unsure about the usefulness of the long-pending road development. In an earlier article, we explored how the PRR project could lead to forced migration and threaten the livelihoods of farmers. In Part 2 of the series, we did a deep dive into the manipulation of compensation options that landowners strictly oppose. However, farmers and environmentalists raise different concerns: even if the road is built, will it truly ease traffic…

Similar Story

From Kuruvimedu to Besant Avenue, how Chennai breathes unequally

Ahead of the art exhibition ‘Pugai Padam’, this photo essay captures the contrasting realities of air and the lived experiences of air pollution in Chennai.

The chimneys of the NTECL Vallur Thermal Power Station, billowing smoke, loom over Kuruvimedu in Ponneri, Thiruvallur near Chennai. Wedged between the plant and its sprawling 300-acre ash pond, the hamlet lies under a blanket of kari (coal) and sambal (ash), coating its narrow streets, colourful homes, and trees. Kuruvimedu is hard to find on Google maps, just as its namesake bird. The main road leading to this place is flanked by factories and industrial complexes, its surface riddled with potholes that make every journey dangerous for motorists.  Home to mangroves, networks of canals, and fields, Kuruvimedu once buzzed with…