BBMP’s rainwater harvesting works stillborn

The city council allocated crores of rupees last year for rainwater harvesting at parks, playgrounds and BBMP buildings. What happened?

The monsoon rains are delayed this year. But by sheer coincidence, BBMP’s rainwater harvesting plans of last year remain unimplemented, almost as if the monsoons were granting their own extension to BBMP, ominously. What’s worse, a Citizen Matters inquiry revealed that the city’s accounts department declined to release funds due to the engineers’ lack of interest.

Bengaluru faces a shortage of 410 MLD (megalitre water per day) of water. The average rainfall here is 923 mms within a geographical area of 800 sq kms.  It is in this context by seeing the potential of RWH, BBMP made implementation of rainwater harvesting compulsory in all its offices, parks and playgrounds and allocated Rs 20 crores in 2011-12 budget. It also proposed to reserve 10 per cent of ward grant allocation to RWH. In addition to that, to encourage citizens, a two percent rebate in property tax also proposed in all the houses, which are having RWH units. This 2011-12 decision now seems utopia.

A BBMP official explaining how the newly installed RWH unit works.

Last month, when Citizen Matters spoke to Krishnaswamy K S, Executive Engineer of the RWH project, ahead of the nearly approaching monsoon season, he said, “We have not done any kind of works associated with RWH so far. But we have some plans and have started doing some work.” 

There is more. The 20 crore rupees allocated in the previous budget for RWH has been withheld by the BBMP Account Section due to the lackadaisical approach from the incharge engineers. The officers in-charge for RWH were supposed to submit the proposal details prior to the release of the money.

“The in-charge officers were supposed to do the site verification, tender allocation, project layout and so many other works prior to the release of the money. Nothing has been done so far. So the money has not been released,” said N V Subbanna, Chief Accounting officer BBMP.

B S Prasad, Chief Engineer for RWH at BBMP, declined to comment on the delay.

In the meantime, a new financial year has begun and the budgetary allocation of the previous year appears to have been forgotten.  Most of the flats, parks, playgrounds, offices, buildings in the city are still devoid of a RWH system.

RWH unit at BBMP head office is the biggest one.

Ironically, one RWH unit was installed at BBMP head office and at IPP (Indian Population Programme) Malleswaram office this year. Surprisingly, this project was not part of the BBMP RWH initiative. Executive Engineer L Chandrasekhar says, “The total cost of the project was Rs 35 lakhs. We have done all the works with our department money only. It does not have any connection with the 20 crore allocated for RWH in the budget.”

As our officials take a long stretch to plan and blame each other for the delay in starting the work, even the delayed monsoon rains may come and go. The city’s water problem will only be more severe in the coming days.

Comments:

  1. Shashidhar K. G. says:

    BBMP projects (east) have implemented two recharge wells in Richards Park (ward60) in 2011.This was an initiative of RTRA with the support of the local MLA Hon Prasanna Kumar.

    Shashidhar /RTRA-Richards Town Residents Association

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

CIDCO’s new flamingo study raises questions on Navi Mumbai airport safety, wetland future

The Bombay Natural History Society had earlier pointed out that protecting wetlands and ensuring aviation safety should go hand in hand.

The City and Industrial Development Corporation of Maharashtra (CIDCO)'s decision to appoint Australian aviation consultancy Avisure to study bird movement around the Navi Mumbai International Airport has raised fresh questions about the future of Navi Mumbai's wetlands. The agency has cited the ongoing study as grounds to defer legal protection for DPS Flamingo Lake, arguing that no irreversible decision should be taken until the assessment of bird-related aviation risks is complete. But bird movement around the airport is not being studied for the first time. Findings of BNHS More than a decade ago, the Bombay Natural History Society (BNHS) was…

Similar Story

Save Mumbai Mangroves campaign: Who really benefits from the coastal road?

Mangroves are being cut in Mumbai even as the world observes Environment Day. Watch this video to understand citizens' concerns regarding the Coastal Road project.

"We are literally risking our lives with floods. We are a coastal city. To mess around with mangroves is digging your own grave," says Pooja Domadia of Save Mumbai Mangroves, a campaign born in the wake of the decision to construct the Versova-Bhayandar Coastal Road in Mumbai. This mega project is going to impact 45,000 mangroves. The cutting of the mangroves has already begun to make way for the 26.3 km Coastal Road. In March this year, the Supreme Court dismissed a petition challenging the Bombay High Court's go-ahead for the project. But concerned Mumbaikars are not giving up. Save…