BBMP’s deadline to fill potholes passes, quietly

Corporators and engineers say there are too many potholes, too little money and too little time. Did the Commissioner speak too soon?

On September 1st 2010, local daily newspapers reported that BBMP Commissioner H Siddaiah had issued a circular to zonal joint commissioners to fill all potholes in the city within a fortnight. Each ward was given Rs 1 lakh for this purpose.

potholes

On September 15th, the deadline came. And went. But potholes continue to remain.

In south Bangalore’s Kengeri (Ward 159), Corporator R Anjanappa (BJP) says they have completed work only to an extent. "Rs 1 lakh is too little money for us to fill all potholes…there are still many potholes to be filled", he says.

Suresh Devathraj, an engineer in the same ward, says they would try to finish filling potholes by next week.

Panning east, the situation is entirely different in Garudacharpalya (Ward 82) in Mahadevapura Assembly Constituency. "No work has been started here. The funds allotted by BBMP have been withdrawn and they are in the process of issuing tenders now for filling potholes, so there is no question of deadline of 15 days", claims corporator N Pillappa (Congress).

However, BBMP Mayor S K Nataraj denies withdrawing funds and says the ward Assistant Executive Engineers (AEE) are responsible to monitor complete the work.

The BBMP Commissioner may have given his directive to fill all potholes in the city in 15 days, but local engineers and corporators explain the practical problems they face while implementing the work, clearly indicating that a 15-day ultimatum may not necessarily work to make the city pothole-free.

K R Puram AEE, Narayan K says they are still in the process of "identifying" potholes. "We are currently working in Devasandra area and the funds allotted are far too small. We will try to finish the work in another ten days and request more funds later. We could not deliver on time due to rain which is worsening the roads further with more potholes", he says.

BBMP Joint Commissioner (Mahadevapura zone) Shivabasavaiah says filling of potholes is a continuous process. "There are a large number of potholes. Our engineers keep looking for them and filling them", he says, adding, "A drive like this will not fill all potholes. Tomorrow rains will come and more potholes will be created."

Comments:

  1. S Srinivasan says:

    The filling of potholes should have been done carefully and professionally. What we see is just dump some demolished structural remains, not tamped properly and Tar mix spread over. This cannot stand even one rain. When vehicles pass over this area, the potholes open up again. In addition to the unscientific speed breaker humps, we have this bonus depressions in the roads to slow down the traffic. This type of shoddy work left to the contractor without any inspection is a waste of public funds. What else we can expect from BBMP. CM does not have his house in all the roads .Afterall, the burden and sufferings are reserved for the general public.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Cycle city no more? Audit reveals only 11% of Pune’s roads pass the test

Pune is set to host the 2026 Grand Tour, but a Parisar audit reveals unsafe, narrow, and encroached cycle tracks across the city.

Children and adults pedalling to school, work and play — this was a common sight on Pune's streets not so long ago. Once known for its vibrant cycling culture, the city still has many groups and communities that promote non-motorised transport. However, with the rise of motorised vehicles, cycling has not only taken a back seat, but has also become unsafe and inconvenient due to poor infrastructure. This is despite Pune having dedicated cycle tracks and lanes. The decline in cycling infrastructure is reiterated by a recent audit, which found that only 11% of cycle tracks in Pune fell in…

Similar Story

Why accessibility remains elusive at Bengaluru’s bus stops and terminals

Our reality check of the city's major bus stops revealed that most do not adhere to MoRTH guidelines, excluding persons with disabilities.

Bengaluru is racing to bridge the gap between first-mile and last-mile connectivity in public transport, but for people with disabilities, the journey is riddled with obstacles. Inaccessible bus stops and terminals in the city keep them excluded. “I have been travelling on muscle memory alone. There are no supportive facilities or infrastructure in bus stops or terminals,” says Mohan Kumar, a visually-impaired person who has been commuting in Bengaluru buses since 2012.  The exclusion starts at the bus stop. “Even if buses are inclusive, it is nearly impossible to reach the bus stops in Bengaluru due to poor design and…