Kadubeesanahalli underpass flooding problem fixed: BDA

The underpass under construction at Kadubeesanahalli junction on the Outer Ring Road now has a proper drainage system to prevent flooding, says the BDA.

Earlier in May 2012, the Outer Ring Road between Marathahalli and Kadubeesanahalli gridlocked following a heavy downpour and the flooding of the underpass, one section (south going) of which was completed. The BDA Chief Engineer TN Chikkarayappa says, “We will collect fines from the contractors for all the violations once the work is completed.”

Work in progress at the Kadubeesanahalli underpass. Pic: Anisha Nair

The Rs 39.8 crores project contracted to Simplex Infrastructure Ltd., has been delayed. The deadline for completion of the underpass work was July this year. It has been extended to August now. The work will be completed by end of August and traffic will be allowed from the first week of September, says the BDA.

However, the process of restoring the service roads will take another two to three months. Chikkrayappa says, “These things depend on the company. We cannot give exact date on when the work will be completed.”

Though the BDA claims drainage work is completed and will prevent flooding, the next major downpour will be the real test.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Fishers of Thiruvanmiyur Kuppam: Aborigines of the coast, not ‘Beach Grabbers’

Fishers of Thiruvanmiyur Kuppam challenge claims of encroachment, defending their long-standing rights amid coastal development.

The dispute between the fishermen and the more affluent, non-fishing residents of Thiruvanmiyur and Besant Nagar has simmered for years, highlighting tensions over land use, development, and livelihoods. Acting upon the complaint from the residents (non-fishers) in the locality, the GCC demolished the temporary constructions made by the fishers of Thiruvanmiyur Kuppam in June this year. Being less than 40 metres from the coastline, they were termed encroachments. A mainstream news outlet even referred to fishers' construction as ‘beach robbery,’ emphasising concerns that the illegal construction of houses and pathways could lead to the loss of turtle nesting sites and…

Similar Story

Bellandur Lake rejuvenation: An urgent call for action

Citizens have strongly disapproved the slow progress on Bellandur Lake's rejuvenation project. Immediate intervention is needed to avoid failure.

Bellandur Lake, Bengaluru’s largest water body, has been at the heart of an ambitious rejuvenation project since 2020. However, persistent delays, severe funding shortages, and inadequate planning have left citizens increasingly frustrated. Time is slipping away, and without immediate government intervention, this critical environmental project risks failing. A recent meeting with government bodies shed light on the project’s stagnation and the urgent steps required to salvage it. Progress so far Desilting Work: Of the estimated 32.33 lakh cubic meters of silt, 22.69 lakh cubic meters (70%) have been removed, leaving 30% unfinished Early monsoons and slushy conditions have delayed progress…