Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

,

Maharashtra cities need a mobility fix: Building roads not a solution

Mumbai and other urban centres in Maharashtra have seen a surge in vehicle ownership, while public transport needs have not been met.

Maharashtra, one of India’s most urbanised States, faces a transportation crisis that has snowballed into a public health, environmental, and economic challenge. With over half its population residing in urban areas, Maharashtra is home to 28 municipal corporations — the highest in the country. Cities like Mumbai and Pune are struggling with the relentless surge in vehicle ownership, which has led to traffic congestion, alarming pollution levels, and a steep rise in road crashes.  Despite these pressing concerns, many cities have pursued an approach focused on expanding road infrastructure, relying on flyovers and highways to absorb traffic overflow. However, experts…

Similar Story

Walkability and affordable transit ignored as elections focus on big projects in Mumbai

Political parties are harping on big-ticket projects, while hardly anyone is focusing on the city's lifelines — BEST and railways.

As the Maharashtra state elections get underway, the daily struggles of Mumbai's citizens, especially their commuting woes, seem to be overlooked in the electoral discourse. Political parties are focusing on massive infrastructure projects, sidelining the city's lifelines like the Railways and the Brihanmumbai Electric Supply and Transport (BEST) Undertaking in favour of the Metro Rail. Despite being partially operational, the Metro has yet to make a significant impact. Surveys reveal that 52% of Mumbaikars walk to work, yet on many roads, pedestrian infrastructure remains neglected, encroached upon, and unusable. While traffic congestion has made commuting a nightmare, trains are perennially…