Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Road safety: Accidents continue, measures inadequate

The infuriating hit and run Porsche case in Pune, is still on people’s minds, and now another case of hit an run, this time in Mumbai’s Worli, hit headlines, raising serious questions about road safety. Mihir Shah, son of a Shiv Sena (Eknath Shinde) leader, is accused of hitting a couple on a scooter and dragging the wife on the bonnet of the car instead of stopping the car, resulting in her death. He has been arrested and sent to judicial custody. Victim’s husband, on a video, said that if the driver of the vehicle had stopped the car, his…

Similar Story

Train travails at Chennai Central signal dire need to solve overcrowding

Overcrowding in trains bound from Chennai to faraway places points to an urgent need for additional trains to ease the rush.

Last month, news reports emerged of ticketed passengers stranded at Chennai Central railway station. They carried bonafide tickets for seats on a train bound for Howrah, but discovered that unauthorised travellers had occupied their coaches; it is said that people began to board the train even as the railcars were entering the platform so that the sleeper coaches were full by the time they made a stop at the station. According to a report in The Hindu, ticketless passengers had not only overrun the reserved coaches but also blocked walkways with their luggage, making it impossible for those who had…