Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Riding the Chennai Metro is a breeze, but last-mile connectivity remains a worry

Chennai needs a unified transit system to ensure seamless travel for metro commuters on either side of the journey.

Stepping off the Thirumangalam metro at 6.45 pm, the train ride seemed effortless. It was cool, fast, and on time, taking just fifteen minutes from the office. Now comes the hard part. Standing at the station exit, finding a ride home is a struggle, as I switch between three apps to book an auto. The metro feeder bus only runs every 40 minutes and has just left. By the time I reach home, the "fast" metro trip has cost an extra half-hour and ₹120 in surge-priced rides, a last-mile problem the metro itself was built to solve. This is the…

Similar Story

A four-hour commute: The daily transport struggles of women from Chennai’s resettlement areas

Watch this video to understand how absence of last-mile connectivity and unreliable public transport in Chennai is failing those who need it the most.

Chennai has long had a tradition of public transport usage, with commuters having the choice of the suburban railway network, Metropolitan Transport Corporation (MTC) buses operating in the city and the Metro Rail for their daily transit. Despite the government introducing new services recently, especially electric buses, private vehicles numbers have soared and bus ridership has gone down considerably. Last mile connectivity issues, poor coverage in certain areas and the inability of the government to encourage residents to use public transport are major impediments. In fact, private vehicles make up 65 per cent of all motorised transport in the Chennai…