Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Pre-poll report card: Chennaiites call for better last-mile connectivity, walkable footpaths

Across suburban Chennai, fragmented public transport and poor last-mile connectivity force residents to rely on private vehicles

For the average Chennaiite, the daily commute has become an arduous task of navigating peak-hour congestion, poor footpaths and an unreliable public transport system. Ahead of the Assembly elections on April 23rd, the gap between official promises and the reality on the road continues to widen. Here is what the numbers say: Currently, the Metropolitan Transport Corporation (MTC) operates a fleet of 4,110 buses and launched 120 low-floor electric buses in 2025. However, experts say the city actually needs 7,000 buses for comfortable travel and better last-mile connectivity. Residents flag overcrowding and long wait times, which force many commuters, especially in…

Similar Story

Reshaping driving lessons: Road safety should be the ultimate priority

A Bengaluru driving school is rethinking how people learn to drive. Watch the video to find out how.

Nine two-wheeler riders die every hour in India. In 2024 alone, more than 4 lakh road accidents were reported. Nearly 1.7 lakh people lost their lives in these crashes. While Indian roads aren't the best, Dimpu Chindappa also attributes accidents to driver behaviour. Dimpu is an engineer who was building roads and now she own a driving school in Bengaluru, "Drivonaut". Drivonaut is a unique driving school which prioritises road safety and prepares drivers to prevent accidents. While most driving classes cut through the system to get their students the driving license, Drivonaut ensures that they are fully prepared for…