Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Draft GBA Parking Rules: Fixing the problem or making it worse?

In a panel on Bengaluru's parking rules, experts explain how the clauses prioritise revenue generation and supply over mobility. Watch the video here.

The Urban Development Department published the draft Greater Bengaluru Authority (Parking) Rules, 2026 on August 11 and opened it up to the public to give suggestions and file objections. This draft is the legal framework meant to strengthen Bengaluru's Parking Policy 2.0, introduced by the Directorate of Urban Land Transport in Feb 2021. When the parking policy was first brought in, the idea was to discourage the use personal vehicles and free up road space to ensure better mobility. However, the draft rules mostly focus on creating paid on-street parking zones, off-street parking on corporation land, leasing vacant private plots to run…

Similar Story

Mumbai’s suburban rail: Can the major infrastructure upgrades ease daily commuter struggles?

Mumbai's suburban rail overhaul aims to fix overcrowding and safety issues. But do the upgrades make travel easier? Commuters weigh in.

Imagine the entire population of a small country getting packed beyond capacity in trains so that they can reach their workplace. This is what happens on Mumbai’s suburban railway trains daily. Every day 62 lakh people travel by the Central Railway in Mumbai—that’s almost the entire population of Singapore. Not to be sidetracked, the Western Railway (WR) ferries 31 lakh commuters daily—that's the number of people who live in the whole of Mongolia.It is no surprise that Mumbai’s suburban railway network draws unimaginable crowds. After all, it is one of the most affordable, fastest and well-connected means of transport available…