Rs 2 Cr may be held back from underpass contractor

BBMP issued notice to the contractor of the JP Nagar 15th cross underpass to complete work and fix quality issues.

The contractor who built the recently inaugurated JP Nagar underpass is now in the dock for poor quality of work. BBMP is planning to withhold Rs.2 crores of payments to pressurise the contractor to finish the work.

JP Nagar’s 15th Cross underpass. Incomplete and riddled with issues. Pic: Yogaraj S Mudalgi

Poor quality of asphalting and water stagnation along drains of service roads have been among the many issues, along with a whole host of unfinished work.

BBMP’s technical vigilance committee (TVC) gave a report to Commissioner Siddiah in January. On Feb 2, BBMP’s Executive Engineer inspected the site and gave notice to the Engineering Projects (India) Ltd (EPIL) asking them to finish the remaining works.

A whole host of unfinished work and problems having up come in the inspection and have been mentioned in the notice to EPIL.

– Concrete slabs on service roads

– Footpath drain cover slabs

– Kerb stones and weepholes clearing

– Expansion joints treatment, footpath railings, drainage, re-strengthening, delineators and lane markings

– Raising of parapet wall the on deck of the underpass

BBMP Special Commissioner K R Niranjan says that after the company responds to the notice, a deadline will be set for them to finish works (about 15 days). BBMP has to pay Rs 2 crores for the earlier works. If EPIL does not finish all works within BBMP’s deadline, the amount corresponding to these works will be deducted from 2 crores, says Niranjan.

When asked about whether BBMP would take any harsher penal action beyond holding back payment, Niranjan indicated that it was not a major showstopper case yet. "Usually in case of huge flaws, the company will be blacklisted. But it is a long procedure – they can to go to court  and can challenge the decision and get stay", says Niranjan. ⊕

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Out of reach: Chennai’s informal settlements lack safe and accessible bus shelters

MTC is expanding its fleet but an analysis found that 41% of Chennai slum settlements lack nearby bus shelters. Here’s what needs to change.

The Metropolitan Transport Corporation (MTC) serves as the backbone of Chennai's urban mobility, carrying millions of residents every day and accounting for over 70% of the city's public transport share. As the transport utility expands its fleet with new buses and renovates shelters across Greater Chennai Corporation (GCC) limits, evaluating the accessibility of this mode of public transit becomes important, especially around access points near the city’s informal settlements.  To what extent does the MTC bus shelter network provide accessible and adequate service to slum settlements? And, where should improvements be prioritised? That forms the basis of this study, which…

Similar Story

Draft GBA Parking Rules: Fixing the problem or making it worse?

In a panel on Bengaluru's parking rules, experts explain how the clauses prioritise revenue generation and supply over mobility. Watch the video here.

The Urban Development Department published the draft Greater Bengaluru Authority (Parking) Rules, 2026 on August 11 and opened it up to the public to give suggestions and file objections. This draft is the legal framework meant to strengthen Bengaluru's Parking Policy 2.0, introduced by the Directorate of Urban Land Transport in Feb 2021. When the parking policy was first brought in, the idea was to discourage the use personal vehicles and free up road space to ensure better mobility. However, the draft rules mostly focus on creating paid on-street parking zones, off-street parking on corporation land, leasing vacant private plots to run…