BBMP’s deadline to fill potholes passes, quietly

Corporators and engineers say there are too many potholes, too little money and too little time. Did the Commissioner speak too soon?

On September 1st 2010, local daily newspapers reported that BBMP Commissioner H Siddaiah had issued a circular to zonal joint commissioners to fill all potholes in the city within a fortnight. Each ward was given Rs 1 lakh for this purpose.

potholes

On September 15th, the deadline came. And went. But potholes continue to remain.

In south Bangalore’s Kengeri (Ward 159), Corporator R Anjanappa (BJP) says they have completed work only to an extent. "Rs 1 lakh is too little money for us to fill all potholes…there are still many potholes to be filled", he says.

Suresh Devathraj, an engineer in the same ward, says they would try to finish filling potholes by next week.

Panning east, the situation is entirely different in Garudacharpalya (Ward 82) in Mahadevapura Assembly Constituency. "No work has been started here. The funds allotted by BBMP have been withdrawn and they are in the process of issuing tenders now for filling potholes, so there is no question of deadline of 15 days", claims corporator N Pillappa (Congress).

However, BBMP Mayor S K Nataraj denies withdrawing funds and says the ward Assistant Executive Engineers (AEE) are responsible to monitor complete the work.

The BBMP Commissioner may have given his directive to fill all potholes in the city in 15 days, but local engineers and corporators explain the practical problems they face while implementing the work, clearly indicating that a 15-day ultimatum may not necessarily work to make the city pothole-free.

K R Puram AEE, Narayan K says they are still in the process of "identifying" potholes. "We are currently working in Devasandra area and the funds allotted are far too small. We will try to finish the work in another ten days and request more funds later. We could not deliver on time due to rain which is worsening the roads further with more potholes", he says.

BBMP Joint Commissioner (Mahadevapura zone) Shivabasavaiah says filling of potholes is a continuous process. "There are a large number of potholes. Our engineers keep looking for them and filling them", he says, adding, "A drive like this will not fill all potholes. Tomorrow rains will come and more potholes will be created."

Comments:

  1. S Srinivasan says:

    The filling of potholes should have been done carefully and professionally. What we see is just dump some demolished structural remains, not tamped properly and Tar mix spread over. This cannot stand even one rain. When vehicles pass over this area, the potholes open up again. In addition to the unscientific speed breaker humps, we have this bonus depressions in the roads to slow down the traffic. This type of shoddy work left to the contractor without any inspection is a waste of public funds. What else we can expect from BBMP. CM does not have his house in all the roads .Afterall, the burden and sufferings are reserved for the general public.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Sion overbridge: Work in progress or a project stalled?

The delay in reconstructing one of Mumbai's iconic bridges is inconveniencing commuters. Residents hope the project will be completed soon.

On August 1, 2024, the Sion overbridge was closed for a two-year reconstruction project, disrupting traffic and daily commutes. The plan is to rebuild the century-old bridge — originally constructed across the railway tracks in 1912 — through a collaboration between the Central Railway and the BMC. However, to the dismay of citizens, the bridge has yet to be demolished. What are the reasons for this delay? Inconvenience to commuters The bridge connecting Sion East to Sion West serves as a vital link between Lal Bahadur Shastri (LBS) Marg, Dharavi, the Bandra Kurla Complex (BKC), and the Eastern Express Highway.…

Similar Story

BEST no longer: How contract buses are hampering services in Mumbai

Wet-leased buses, far outnumbering BEST’s own fleet now, are bogged down by multiple problems as contractors try to cut costs.

In Part 1 of this series, we discussed how BEST’s wet-leased buses — owned and operated by private contractors — are rapidly replacing its own fleet. In Part 2, we explore how this model is impacting the quality of bus services.Last December, nine people were killed and another 37 injured in an accident involving a wet-leased electric bus in Kurla. According to the police, the driver had not been adequately trained before being moved to an automatic electric bus from manual, geared buses. Under the wet-leasing model, introduced to cut BEST’s costs, a contractor owns and operates the bus, and…