Pre-monsoon maintenance: Gear up for power cuts

Have you faced power cut in Bangalore recently? Here's why.

Some areas in Bengaluru faced power cut in the last few days, even when the Energy Department of Karnataka submitted to the High Court that the state has surplus power.

However the reason is the pre-monsoon maintenance work being carried out by the Karnataka Power Transmission Corporation Limited (KPTCL) and Bangalore Electricity Supply Company (BESCOM). KPTCL is carrying out its annual major works around the city. The capital city will continue to have a few power cuts in some areas.

Pic for representational purpose only. Courtesy: Reuters

In the past eight days, AECS Layout in Whitefield was badly hit by power cut. On Tuesday night (on April 29, 2014) the blackout lasted for 10 hours. Residents complained that their electrical appliances and Sewage Treatment Plants (STP) in apartments went for a toss due to intermittent power cuts, while some complained their children got an excuse not to study. “Most of us own inverters, but even inverters were not charged enough to sustain for the whole day,” says Sanjay Vijayraghavan, a resident of AECS Layout.

Non-communication of power cut

Sanjay Vijayraghavan lodged multiple complaints with the BESCOM customer care service. When no response was forthcoming, he took to Facebook to share his trauma. After this, BESCOM engineers acted on it. Assistant Executive Engineer, BESCOM of Mahadevpura zone posted on facebook a notification informing people about the 12 hour power cut scheduled on two days, ie. April 25th and 26th.

Sanjay Vijayraghavan says that the notification issued had not-easily-comprehensible technical terms. The notification warned of a power cut from 9 am on April 25th to 9 pm on April 26th 2014. The reason cited in the notification for the intermittent power supply was to shift transformer load on newly commissioned 220/66kV EPIP GIS station.

The areas to be affected were F4-Green Garden Layout, Light Spro Road, Keerthi Flora Apt, AECS Layout D& E Block, F5- Kundalahalli(V) & Kundalahalli Colony, AECS Layout A, B & C Block, F14-Knight Bridge Apts, F15-Siddapura, Thubarahalli, BEML Layout, F17-Puravankara, Purva Fountain Square  Apts, F18-Rohan Vasantha Apts, F19-Sriram Properties Apts, F21-Sterling Apts, F22-Kalyani Tech Park, MTB Apts, Rajani Apt, Part of Thubarahalli, F25-Divyasree Tech Park.

KPTCL-BESCOM communication problem?

When Citizen Matters probed, KPTCL official Superintendent Engineer said that under the annual major works to be done in the year 2013-14, commissioning of new stations was initiated. Such many new stations will come up in the city. KPTCL Chief Engineer was unavailable for clarifications. However, when we asked why did they fail to inform citizens, he said that BESCOM is supposed to inform power cuts to people.

Sanjay points to systems that are better-managed without troubling the customers: “I have stayed in foreign countries, even they have maintenance and upgradation work but they have a back up system, which we don’t seem to have.”

Work without planning
Sanjay points to the lack of planning among government bodies. Referring to the switch board boxes placed on footpath and streets he adds:
“BESCOM has been replacing the old boxes with new big ones. Near my area they have dug the footpath to set up these new boxes. It has been a month, the place remains dug. Commuters can’t use the footpath but the open pit increases the risk of accidents. When I enquired with the AEE he said that the cables are yet to be sanctioned. Why do they start the work without having the all the materials required?” he questions..

General Manager of Customer Relation, BESCOM, Jayanthi N said, “Summer brings a lot of load on transformers. At Mahadevpura, KPTCL has decided to shift the load to 220/66KV EPIP GIS station. There will be interruption in particular areas because of maintenance and repair work. Along with that, we have BESCOM quarterly maintenance work to carry out. Therefore it is necessary to cut power. All these are pre-monsoon activities, which are carried out on feeder service lines.”

She added that the scheduled power cuts can be informed to people, but it is very difficult to inform the unscheduled cuts. KPTCL informs BESCOM on the day or just two days before they carry out the work, which is why BESCOM cannot inform everyone. However leading newspapers are informed about the cut, said Jayanthi.

“As and when we are informed about power cuts, we upload a list of expected power cuts on our website. Under Operation header, Daily Statistics Operation Wing section provides a list of power cuts along with the reasons,” she informed.

The major work at Mahadevpura has been completed. Residents of Whitefield are enjoying regular power now.

Comments:

  1. Debashis Ghosh says:

    Great write up highlighting problems faced by not just the consumers but also by KPTCL, BESCOM etc ……
    One thing for sure – we public are Irresponsible in general and have become too used to EXPECTING EVERYTHING HUNKY DORY ……….
    Which is Wrong –
    We want 24×7 power & water (when 90% urbanites don’t implement even a basic RWH in their homes), Roads clean (when we chuck our garbage out, when we think no one is noticing) , wonderful policing (when we break many rules) …. and many more ….

    Before we talk about Corruption, let’s also analyse how Corrupt we are from within us, even in basic day to day activities ……… Corruption is not just the Monetary part … It’s also something from within ….. 🙂

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Street Vendors Act overlooked even as Chennai eyes new vending zones

Greater Chennai Corporation is set to finalise 776 vending and 493 non-vending zones in Chennai for 35,588 registered street vendors

In a recent incident, a 56-year-old woman died when the Greater Chennai Corporation (GCC) conducted a drive to evict street vendors from a ‘no-hawking zone’ at the NSC Bose Road junction. According to news reports, the woman, M Krishnaveni, was trying to protect her wares during the eviction drive. This incident has sparked widespread concern and reignited discussions on designating vending and non-vending zones fairly. A series of such developments in Chennai have impacted both residents and street vendors. While residents raise issues like reduced walkability and increased garbage, vendors argue they need a proper space to sell their wares.…

Similar Story

Are building regulations followed in Bengaluru? A case study in Vijayanagar

One of the teams in a recent Bengaluru design jam explored the conformity of buildings to existing rules in Vijayanagar's residential areas.

The extension of 3rd Cross road in Vijayanagar is like any emerging neighbourhood in Bengaluru, with houses packed like boxes on either side. This led us to explore the role of regulations in shaping our buildings, streets and city at large. We presented our findings at the ‘Bengaluru Design Jam’, organised by organised by OpenCity, and held on July 6th. The participants collaborated to analyse and interpret different aspects of BBMP’s construction bye-laws.  The changes and growth of cities are often guided by economic activities. But the development of cities needs to be managed and regulated to ensure liveability. This…

39960