Pollution watchdog reviews implementation of e-waste rules

KSPCB Chairman reviews the implementation of E-waste (Management) Rules, 2016 in Karnataka.

The Ministry of Environment, Forest and Climate Change, Government of India has notified the E-waste [Management] Rules, 2016 which is effect from 01.10.2016. For implementation of these Rules, the Central Pollution Control Board has notified “implementation of guidelines for E-waste Management Rules, 2016”. The Board had issued authorization to 27 collection centers, 42 dismantlers, 24 recyclers and
14 recyclers/dismantlers.

To review the implementation of E-waste (Management) Rules, 2016 in the state, meeting was conveyed by the Chairman of the Board on 12.6.2017. The representatives of the Central Pollution Control Board and the Ministry of Environment, Forest & Climate Change were also attended the meeting. Detail presentations on E-waste rules and guidelines were made and interactions were held. 47 numbers of processing units attended the meeting. After detailed deliberations, following directions were given:

  1. As per the  E-waste [Management] Rules, 2016,  meeting is treated as an opportunity of hearing to the processers and  for those who have not attending the meeting and not complied, further action will be initiated and also their names will be  published  in the website of the Board for information of all .
  2. Since the provision of individual collection center is no more existing in 2016 rules, the collection center for which the authorization has given by the Board is deemed to have been withdrawn and they are require to surrender the passbook/authorization.
  3. All the units are required to give quantity of material received by them from 1.4.2016 along with its source and discontinuity from the generator side.
  4. The producers are required to obtain EPR approved plan from CPCB.
  5. The manufactures including the parts of electric and electronic equipment are required to get it registered.
  6. All the bulk consumers are required to give their waste to the authorized dismantlers/recyclers after making entry in the passbook issued by the Board.
  7. The plastic waste (10 to 12% of the total waste) generated during processing of e-waste shall be handed over to registered recyclers under the Plastic Waste Management Rules, 2016.
  8. The other waste has classified under the hazardous and other waste shall be required to hand over the waste to the actual user.
  9. All the non-recyclers waste shall be disposed to TSDF facility.
  10. The Board has proposed to design vehicle for transportation of e-waste as done  in case of transportation  of  hazardous waste.
  11. The dismantlers and recyclers shall provide infrastructure as specified in the  guidelines.
  12. The recyclers  involved in generation of effluents are required to operate with preliminary treatment plant as per the directions of Hon’ble Supreme Court. Any violation noticed closure directions will be issued.
  13. The area specification of 300 sq.mt/ton of dismantling activity and 500 sq.mt/ton for recyclers will be followed. Non-availability of space, existing units are required to be shifted within 6 months.
  14. The Board will not allow dismantler/recyclers activities in residential area.
  15. Annual report shall be submitted within 7 days time.

The Board hereby directs all the bulk consumers, manufacturers, recyclers, dismantlers to follow/comply e-waste (Management) Rules, 2016 and treat this as final opportunity given to them.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Uthandi’s ₹91-crore ‘flood drain’: Is Chennai solving one problem by creating another?

The WRD's flood fix puts Uthandi at risk. Residents flag pollution, CRZ violations, aquifer damage, and threats to nearby fishing livelihoods.

The Straight-cut Flood Escape Channel project at Uthandi in the southern part of Chennai along East Coast Road was conceived by the Water Resources Department (WRD) as a flood mitigation measure, with a budget of ₹91 crores. The plan proposes a cut-and-cover drain through the VGP Layout in Uthandi, to connect the Buckingham Canal to the Bay of Bengal. The drain is supposedly meant to divert excess floodwater in Buckingham Canal during heavy rains, when areas around the Pallikaranai marsh and Okkiyam Madavu face flooding.  Work on the project started immediately after its inauguration in August 2025. However, residents of…

Similar Story

CIDCO’s new flamingo study raises questions on Navi Mumbai airport safety, wetland future

The Bombay Natural History Society had earlier pointed out that protecting wetlands and ensuring aviation safety should go hand in hand.

The City and Industrial Development Corporation of Maharashtra (CIDCO)'s decision to appoint Australian aviation consultancy Avisure to study bird movement around the Navi Mumbai International Airport has raised fresh questions about the future of Navi Mumbai's wetlands. The agency has cited the ongoing study as grounds to defer legal protection for DPS Flamingo Lake, arguing that no irreversible decision should be taken until the assessment of bird-related aviation risks is complete. But bird movement around the airport is not being studied for the first time. Findings of BNHS More than a decade ago, the Bombay Natural History Society (BNHS) was…