Mumbai’s housing crisis: Is self-redevelopment the answer?

Mumbai has over 16,000 old buildings that must be redeveloped. Experts say residents can come together for redeveloping on their own.

Mumbai has over 16,000 cessed and dilapidated buildings — some close to a hundred years old — that must be redeveloped. On May 14, 2023, the state government announced that it would constitute a separate authority to push for self-redevelopment of such buildings — a solution to the city’s housing crisis that involves societies of residents living in these buildings undertaking the redevelopment. 

Deputy chief minister and housing minister Devendra Fadnavis said the government has set up a particular cell for self-redevelopment to ensure that proposals are approved within three months and deemed conveyance — a significant requirement for such projects — would henceforth be issued within a month from the date of application by cooperative housing societies. 

The government considered constituting a self-redevelopment financial corporation, even as the Maharashtra Central Cooperative Bank and the Mumbai District Cooperative Bank have been appointed as nodal agencies to facilitate finance for such projects. The administration will also extend benefits and subsidies to help housing societies and their tenants get bigger houses at lower costs.

These announcements would no doubt be a relief to thousands living in buildings in dire need of redevelopment in the city. Self-redevelopment has had a bit of a rocky past: In September 2020, the Reserve Bank of India (RBI) refused permission to Maharashtra’s state and district central co-operative banks (DCCBs) to finance self-redevelopment of co-operative housing societies, stating that such projects would fall under the category of commercial real estate and hence, outside the banks’ primary purview of lending for activities related to agriculture and rural development.

The abrupt cessation of funding caused several ongoing projects in Mumbai to reach a standstill. However, in September 2022, the Maharashtra government removed the limitations on state co-operatives and DCCBs, allowing them to finance self-development housing projects.

Benefits of self-redevelopment

The redevelopment of housing societies isn’t a novel concept and has been promoted by successive governments over the past few decades. The traditional housing development model involved agreements between housing societies and developers to construct and hand over flats to buyers with very few added benefits. Developers utilised the balance plot potential to construct and sell additional flats and shops as per statutory body approvals.

This model is lucrative for developers, but it often leads to poorly designed and constructed buildings, inordinate delays, and sometimes even project abandonment. These issues put housing societies and residents at risk of losing their investments with little recourse.

Consequently, a framework for regulating such power was put in place under the RERA (Real Estate Regulatory Authority) so developers couldn’t divert funds from one project to another and, thus, increase risk. However, that isn’t enough – a new, better redevelopment model is needed. 

With the re-introduction of the self-redevelopment scheme, the aim is to empower residents to take control of the redevelopment process through its entire timeline – from commissioning a suitable architectural or contracting firm and managing construction to selling the additional real estate constructed and sharing the final profits. The autonomy of the process guarantees merit in all respects; society members would reap the benefits of good quality construction, modern amenities and infrastructure, and time-bound and cost-controlled construction.

Additionally, with the developer removed from the process, there is no risk of fraud, delayed construction, or loss of area; in fact, residents can expect up to 40-50% increase in carpet area compared to 15-20% through the traditional process.

Most importantly, self-redevelopment can bring down the cost of the surplus apartments built (as opposed to the price inflation that occurs when a developer driven by profit margins is involved), creating a ripple effect in the market and ensuring housing remains affordable to the masses.


Read More: BDD chawl redevelopment: Bumpy road to a better life


Government incentives

The government extended the amnesty scheme to push deemed conveyance to city buildings. A conveyance deed must be executed to transfer the title of the land and the building to the society. It is an important document that confers the legal ownership of the common areas of a housing society and is crucial for a housing society in proving its legal ownership over the property and for undertaking redevelopment projects.

A conveyance deed is an important document in proving its legal ownership over the property and for undertaking redevelopment projects. Pic: Gopal MS
A conveyance deed is an important document in proving its legal ownership over the property and for undertaking redevelopment projects. Pic: Gopal MS

In many instances, builders or landowners fail to convey the title of land and building to the housing societies, owing to their personal interests. Thus, to keep a check on such practices, amendments were made in the MOFA in 2008 to appoint a ‘competent authority’, the registrar of cooperative housing societies, to address the societies’ grievances and protect their interest by executing deemed conveyance under section 11(3) of the MOFA.

Deemed conveyance enables a society to get permission from the planning authorities to redevelop its structures.

Including banks as nodal agencies to implement self-redevelopment and extending additional FSI benefits to buildings abutting roads of less than nine metres will benefit several housing societies.

By supporting self-redevelopment initiatives, the government can encourage a more participatory approach to housing development and help address the issues of poorly designed and constructed buildings and project delays. Such measures could lead to a more sustainable and equitable housing market, benefiting residents and the broader community.

Understanding the challenges

The first and the most challenging step in a self-redevelopment project is arranging for funds. The process of funding for self-redevelopment can be carried out through two methods: obtaining a loan from the Mumbai District Central Co-operative (MDCC) Bank or pooling contributions from members and availing personal loans to create a fund.

Several housing societies that have taken the self-redevelopment route have reaped the benefits of this democratic approach.  For example, the Charkop Jin Prem Cooperative Housing Society in Kandivali was completed in two years and was self-funded by the residents. Another example is the Jayakunj CHS in Borivali, where each flat has 44% additional area.

Mumbai MHADA office
Representative Image. Doing adequate research and finding the right developer is the key to a successful self-redevelopment project.

It is essential to ensure that the project cost does not exceed the projected realisation from sales and leads to a net profit of atleast 10%. Extra FSI is permissible – as per DCPR 2034 – partly by paying a premium for additional FSI and partly through the purchase of TDR. Existing members are eligible for 35% extra built-up area by default due to the fungible area provision in the DCR. The balance area can be sold in the open market. 

A feasibility study is conducted to compare costs v/s profit from sales, and depending on the results, either the members can opt for an extra area beyond 35% or increase the sale area to increase net profit. The sale area can be commercial or residential. More often than not, the commercial property rate is higher than residential. Hence, the society can decide on the same, within the permissible limits of generating commercial sale area, per the DC rules.


Read more: Why Mumbai housing societies can’t self-redevelop anymore


Another challenge is that housing societies often don’t have the required documentation for redevelopment in place, which necessitates follow-ups with various authorities and the investment of funds – and becomes a time-consuming process. Additionally, non-cooperation among members or mistrust towards the managing or redevelopment committee members often hinders progress. In some cases, certain members have vested interests in promoting developer-driven redevelopment.

The unavailability of funds or high interest rates for loans, particularly for initial expenses and statutory requirements before receiving the IOD (Intimation of Disapproval) from the MCGM (Municipal Corporation of Greater Mumbai) or MHADA (Maharashtra Housing and Area Development Authority), poses another challenge.

Blending professional and personal expertise

Appointing a competent team of experts to assess project feasibility realistically and oversee the entire process is crucial for ensuring success. 

The Development Management (DM) Model has been gaining popularity amongst societies that initially opted for self-redevelopment. In this model, the society still plans on its own through the professional team appointed by them. The society also has the liberty to allot their flats as per their wish and finalise all internal and external amenities as per their budget with the help of their appointed professional team.

In this model, the role of the Development Manager is to arrange for funds for the project, undertake construction management, site management, and sales management, and, in turn, charge fees for it.

Despite several challenges, self-redevelopment projects can thrive and deliver positive outcomes with careful management and collective efforts.

Also read:

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai: Out of SRA purview, Jai Bhim Nagar residents stare at a rocky road ahead

Residents and activists continue to fight for rights of Jai Bhim Nagar residents despite several legal and administrative hurdles.

In the previous part of this series, we reported on the demolition of the Jai Bhim Nagar settlements in Powai and delved into the legally dubious history of Hiranandani Gardens where they stood. On October 5th, the Powai police filed an FIR against officials of BMC's S ward, Hiranandani Group (HGP Community Pvt Ltd), and four associates on the recommendation of the Bombay High Court for conducting unauthorised demolitions in Jai Bhim Nagar. The charges against the accused include criminal conspiracy, public servant framing an incorrect document with intent to cause injury, and furnishing false information among others.  About 100-150 families…

Similar Story

The fight over Jai Bhim Nagar: Whose land is it, anyway?

Settlers in Jai Bhim Nagar in Powai’s Hiranandani Gardens were forcefully evicted in June. And it’s a contentious move in more ways than one.

A tarp-covered shed on a busy sidewalk in Powai lights up every evening with the cacophony of children. The ‘sabki library’ is a makeshift after-school space for the children of Jai Bhim Nagar living on the sidewalk, where they show up diligently to study with volunteers from nearby IIT Bombay.  The library was set up there over three months ago, soon after the Jai Bhim Nagar settlement was demolished, and its residents forcibly evicted. While many residents from the 600-odd homes have shifted elsewhere since then, about 150-200 families still live on the streets surrounding the demolished slum. “We have…