Study: Bengaluru’s new road-widening project will irreparably damage the environment

The felling of thousands of trees for the 'Bangalore Surrounding Roads Project' will permanently damage the city's environment, finds an EIA by Azim Premji University. The actual number of trees to be cut are far higher than that reported as well, finds the EIA.
Thousands of trees around Bengaluru will be cut for the road-widening project. Pic credit: APU report

The Karnataka Road Development Corporation Limited (KRDCL) proposes to start widening and construction of roads surrounding Bengaluru. Newspaper reports estimate that 8,561 trees will be cut over 152.03 km of road length, but official numbers have not been released. The project’s public-available feasibility reports fail to provide information on its environmental or ecological impacts.

In this context, we at Azim Premji University, conducted an independent rapid EIA (environmental impact assessment) of this road-widening project based on rapid field visits between February 29 and March 6.

The impacts of the road-widening project will include:

  • Health issues from increased air pollution
  • Increased urban heat island effects
  • Threat to lakes
  • Loss of trees, especially many heritage trees
  • Loss of urban biodiversity
  • Threat to forest ecosystems
  • Loss of spiritually-important ashwathkattes
  • Reduction in carbon sequestration
Roads proposed for widening, with trees marked for cutting

Key highlights of the rapid EIA

  • Several old and large trees have already been cut or lopped even before the project has begun. For example, we noted 51 trees cut in the stretch between Kanchugaranahalli and Jigani.
  • The actual numbers of trees that will be cut seem much higher than reported. In the stretch from the Kanchugaranahalli to Jigani, newspaper reports state that 184 trees will be cut. But in our field survey, we counted around 1,000 trees marked for cutting.
  • Many heritage trees will be lost, and this loss can’t be replaced by planting saplings. In just one 15-km stretch between Madure and Nelamangala, we counted 206 banyan trees, including massive specimens with girths of 17.7 m and 14.9 m, that will be cut.
  • 15 sacred ashwathkattes (platforms with massive peepal and neem trees, many with nagarkallus) have been marked for removal. These are essential sacred, cultural and community spaces for local residents.
  • The project will have adverse impacts on endangered wildlife in important biodiversity habitats, especially Anekal Reserve Forest which connects Bannerghatta National Park, and Junnasundra Mini Forest.
  • The road will disturb fauna including the endangered slender loris (Loris tardigradus), which is a Schedule 1 protected species under the Indian Wildlife Protection Act 1972, palm civet (Paradoxurus hemaphroditus), and Indian jackal (Canis aureus aureus).
  • It will have environmental impacts on as many as 14 lakes, including large lakes like Varthur and Madure kere.

Trees provide a number of tangible and intangible services to a city and its residents. Street trees are the lungs of Bengaluru, cleaning air of harmful pollutants such as NOx, sul­phur dioxide, and Suspended Particulate Matter that causes breathing disorders and reduces life expectancy. Street trees help to reduce the temperature of road surfaces by 20°C and air temperature by 3-5 °C, and sequester carbon.

When heritage trees are lost, the historical and social links between the city and its residents is erased. Habitats that support endangered biodiversity are destroyed forever, and linear roads that cut through protected areas disturb and endanger wildlife, also increasing human-animal conflict.

Bengaluru is expanding into peripheral areas. Such expansion must be planned with care. Rather than planning urban expansion to ensure that there is enough greenery for people’s health and well-being, projects like the proposed road expansion will destroy important, essential patches of greenery, which cannot be compensated for by planting saplings or transplanting trees.

The full EIA can be read here.

[This article is based on a press release from Azim Premji University, and has been published with minimal edits.]

Comments:

  1. Nihar says:

    It is ofcourse sad to hear that trees will be chopped and this needs to be considered and avoided as much as possible. However, narrow roads and extreme traffic is a reality. It would have been better if the author had provided both perspectives instead of simply bashing the project.

  2. Sanjay Joseph says:

    It’s sad…but Then first govt should be asked to plant new trees, almost double the amount they cut…also check if they have technology to relocate these trees…

  3. Maitri says:

    As a concerned citizen, is there a representative of the government we can contact about this report?

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Commuters, vendors bear the brunt of rising air pollution in Chennai’s Ambattur

IIT-M’s Project Kaatru finds high PM2.5 levels at Ambattur Estate, Padi flyover and Dairy Road, exposing residents to dust and pollution daily.

Commuters passing through Ambattur Industrial Estate inevitably find a layer of dust coating their vehicles, faces, and hands. For Lalitha*, a domestic worker employed at a high-rise apartment near Padi flyover’s Saravana Stores, the last two weeks of December have been especially unbearable. "Dust, dust, dust everywhere," she says, coughing through a persistent cold. At 6 pm, when the rush hour begins, it takes her nearly 30 minutes by bus to cover the 5 km journey home. The ride to the Dunlop area is punctuated by pollution, blaring horns, and endless traffic snarls. “It should take 15 minutes usually, but…

Similar Story

முதல்வர் சீக்கிரம் அடிக்கல் நாட்ட வேண்டும் என்பதற்காக அறிவியல்  ஆய்வுகளைப் புறந்தள்ளுவதா?

CRZ clearance has been granted for a new drinking water reservoir in the naturally formed coastal salt marshes in Chengalpattu near Chennai.

செங்கல்பட்டு மாவட்டம், திருப்போரூர் மற்றும் திருக்கழுக்குன்றம் வட்டங்களுக்குட்பட்ட வருவாய் கிராமங்களில், இயற்கையாக அமைந்துள்ள கழுவேலி, உப்பங்கழி நீர்நிலையில், புதிய குடிநீர் நீர்த்தேக்கம் அமைக்க CRZ அனுமதி வழங்கியுள்ளது மாநில கடற்கரை ஒழுங்குமுறை மண்டல ஆணையம். இத்திட்டத்தின் முதல் கட்டத்தில் நெம்மேலி, கிருஷ்ணகாரனை, தண்டலம், பட்டிபுலம், திருப்போரூர், மாமல்லபுரம், சலுவான்குப்பம், பையனூர் ஆகிய வருவாய் கிராமங்களுக்குட்பட்ட 4375 ஏக்கர் பரப்பளவில் வருவாய்த்துறை, நீர்வளத்துறைக்குச் சொந்தமான இடங்களில் நீர்த்தேக்கம் அமைக்கத் திட்டமிடப்பட்டுள்ளது. 1.655TMC கொள்ளளவு கொண்ட இந்நீர்த்தேக்கம் மேற்கூறிய கிராமங்களைச் சேர்ந்த 50 ஆயிரத்துக்கும் மேற்பட்ட மக்களின் குடிநீர்த் தேவையைப் பூர்த்தி செய்யும் எனவும் அருகாமை கிராமங்களின் வெள்ள பாதிப்பைக் குறைக்கும் எனவும் அரசுத் தரப்பில் கூறப்படுகிறது. Map showing components of the Kovalam reservoir. Pic courtesy: Tamil Nadu Water Resources Department. இத்திட்டத்திற்கான விண்ணப்பத்தை 17.11.2025 அன்று  தொழில் நுட்ப  வல்லுநர் குழு பரிசீலித்தது. 20.11.2025 அன்று  மாநில கடற்கரை  மண்டல ஆணையம் விண்ணப்பத்தைை பரிசீலித்து CRZ அனுமதிக்கு பரிந்துரைக்கிறது.…