Stop sewage inflow into Bellandur lake soon, says Green court

Bellandur lake always hits headlines for some reason - this time it's in news because the National Green Tribunal has taken it on itself to save the lake from sewage abuse.

The National Green Tribunal (NGT), in a hearing held on April 12 2017, has warned of passing restraining directions against the State of Karnataka, if discharge of untreated sewage into the Bellandur Lake in Bengaluru is not stopped immediately. The NGT also directed the Chief Secretary of the state to be present before the Tribunal during the next hearing.

The Tribunal also pulled up Karnataka Lake Catchment Development Authority (KLCDA) for allowing the situation to reach a stage where lake catches fire. The State government, KLCDA and other authorities have been directed to apprise the court of the measures taken after the lake fire incident on February 16, 2017. Meanwhile Karnataka State Industrial Infrastructure Development Corporation (KSIIDC) has been allowed to implead in the case.

Namma Bengaluru Foundation reacts

Namma Bengaluru Foundation (NBF), initiated by Rajyasabha MP Rajeev Chandrasekhar has been working with citizens to save Bengaluru lakes, and has helped them to take many of these fights to court. NBF has been actively involved in Bellandur lake, trying to come up with rejuvenation plans for the lake.

A press note from Namma Bengaluru Foundation (NBF) says: “The Tribunal was unhappy with the way Karnataka Lake Conservation and Development Authority (KLCDA) handled the lake fire issue. KLCDA along with other authorities have been directed to apprise the court about the measures taken post lake fire incident (16 Feb 2017) to prevent such accidents in future. The tribunal also pulled up KLCDA and observed that it is the only lake development authority in the world which is causing fire in the lakes.”

Sridhar Pabbisetty, the CEO of NBF says in the press note, “It is imperative that Government ensures critical infrastructure is put in place before uncontrolled approvals are given for large development projects. We want KLCDA to no longer allow rampant abuse of our lakes that are in custody of various government agencies.” Pabbisetty says NGT’s observations further strengthens their resolve to fight for the protection and rejuvenation of the city’s lakes and water bodies.

The struggle of Bellandur lake

Bellandur lake, Bengaluru’s infamous lake known for sewage, garbage, froth, fire and encroachments, hits headlines often for one of these reasons. The NGT, for sometime now, has been trying to put systems in place to ensure Bellandur lake ecosystem is not swallowed by human greed.

Earlier in another case related to the special economic zone (SEZ) coming up on the lake bed, the NGT quashed the environmental sanctions given to Mantri Developers and Coremind Software and Services Private Limited. In a landmark judgment, the NGT came up with new buffer zone definitions for all water bodies and drains, a directive to the state government to notify the wetlands in and around Bengaluru and a directive to survey and demolish all illegal structures around Bellandur lake. A fine amounting to almost 129 Crore was levied on the two erring builders.

The builders filed a Civil Appeal in the Supreme Court. The Supreme Court, while staying the payment of fines pending hearing of the appeal, declined to stay any other portion of the judgment. Meanwhile, the two builders were joined at the Supreme Court by many other builders who claim that they will be put to financial losses if they observe the new buffer norms.

Following the fire on Bellandur lake, the NGT initiated a suo-motu case, asking the government of Karnataka to respond with the actions taken to prevent sewage from entering the lake, and future plans. Along with the case, On February 22nd 2017, the NGT brought up its earlier order on Bellandur lake (the Forward Foundation v/s Government of Karnataka case related to Mantri Developers/ Coremind Software & Services Pvt Ltd) and asked the government why it should not be held in contempt.

Enviro clearances for nearby structures

On February 23rd, the State Environment Impact Assessment Authority (SEIAA) cancelled the environmental clearances accorded to as many as 28 builders, including both Mantri Techzone Pvt Ltd and Coremind Software and Services Pvt Ltd. The formal cancellation of environment clearance also leads to the automatic cancellation of the Karnataka State Pollution Control Board (KSPCB) clearance accorded to both entities, as the KSPCB clearance accorded to the Bellandur SEZ project is valid only until the date of the Environment Clearance obtained and becomes invalid if the Environment Clearance is annulled or withdrawn.

Meanwhile, Sterling Infinia, an apartment development next to the SEZ project put out a notice informing that its project was accorded environmental clearance on March 20, 2017. The same structure had been denied environment clearance in August 2016, as the SEIAA found through village maps that a canal from Agara lake leading to Bellandur lake ran through the project site. About 3 guntas of canal land was granted to the Sterling Developers through a government order dated November 23, 2013 by the Siddaramaiah regime itself, states a Times of India report.

 

Related Articles

False promise to save Bellandur lake exposed
In pictures: Bellandur lake’s fire and snow
The black sea of Namma Bengaluru: Bellandur lake in pictures
All you need to know about Bellandur Lake and its problems

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Opinion: Why climate action must recognise and include India’s informal workers

As COP29 discusses ways to mitigate the climate crisis, India must address the adversities faced by informal workers and chalk out plans.

The ongoing COP29 conference in Baku, is a pivotal moment in climate action, focusing on global cooperation to limit warming to 1.5°C. Key priorities include mobilising financial resources for developing countries to submit ambitious climate plans (NDCs) by 2025 and continuing support through the Fund for Loss and Damage (FRLD) established at COP28. COP29 also aims to strengthen adaptation efforts by setting finance-backed targets for the Global Goal on Adaptation.  While COP29 primarily focuses on international climate initiatives, India must address pressing domestic issues. One key group often overlooked is informal workers in Indian cities. Over 80% of India’s urban…

Similar Story

Status check: Key concerns remain as Chennai moves ahead with WTE plans

Greater Chennai Corporation's tender for the Waste-To-Energy plant is at the final stage; Here is what we know about the bidders

17,422 metric tonnes per day — that's the staggering amount of trash the Greater Chennai Corporation (GCC) will generate in 30 years. Currently, Chennai produces 6,143 metric tonnes of waste daily, which adds to the growing piles in Kodungaiyur and Perungudi dump yards. Like many other major cities, GCC is struggling to find a sustainable solution for waste management and has proposed a Waste-To-Energy (WTE) plant. However, the experiences of cities like Delhi are testimony to the significant environmental and health impacts of WTE plants. A recent The New York Times investigative report on the Delhi WTE reveals: "The government…