How to get occupancy certificate within BBMP limits

What is an Occupancy Certificate?

certificate of occupancy is a document issued by a local government agency or building department certifying a building’s compliance with applicable building codes and other laws, and indicating it to be in a condition suitable for occupancy.

Obtaining an OC is a requirement under the Karnataka Apartment Ownership Act, 1972. The law says one cannot legally move into a building unless the developer gets an occupancy certificate from the BBMP or BDA. The corporation can ask apartment owners to leave such illegally occupied flats or impose heavy penalties. Occupancy certificate is also required when the buyer applies for Khata.

However, note that the occupancy certificate is not needed for registration of the property during purchase currently in Bangalore (though is mandatory in some parts of India). This often leads buyers to believe that the occupancy certificate is not important.

Who is responsible for getting/applying for it?

The builder/person who is constructing the flat/villa/apartment is responsible for getting this to the buyer of the flat/villa/apartment. The builder needs to fill an occupancy certificate application form, submit documents and pay required fees for the issue of the certificate. However, in case the deviations are upto five percent from the plan, then a fine will be charged based on the extent of deviation made. Once the fee is paid, the occupancy certificate will be issued.

PROCESS OF GETTING an Occupancy Certificate (OC)

  1. Requisition for issue of Occupancy Certificate.
  2. Completion Certificate as in Bye law – 2003, Schedule VIII (Extract Attached – Pg 2 of this document).
  3. Recent Katha Extract, Katha Certificate and Current Year Tax paid Receipt.
  4. Fire Clearance Certificate –  issued by Fire Force and Emergency Services Department(For High Rise Buildings)
  5. Consent For Operation – Issued from KSPCB (for Buildings with Built up area more than 20000 sq.m).
  6. Photos –  of Buildings
    1. Rain Water Harvesting System.
    2. Waste Collection System.
    3. Solar Water Heating System.
    4. Transformer yard
    5. Vehicle parking system.

As mentioned by Additional Director, Town Planning, Bruhat Bangalore Mahanagara Palike .

How BBMP treats the OC proposal

BBMP may treat the proposal as follows (ref: Cl 303+304 of KMCA)

  • Grant without changes
  • Grant subject to specific modifications
  • Grant with conditions
  • Reject

BBMP may ask the developer to take the following measures, for the sake of existing/proposed power/water/sewerage lines, new roads or widening of roads:

  • change the location of the proposed building,
  • provide open space or ventilation,
  • use specified materials for construction,

The developer must re-submit revised plans to comply with BBMP’s objections and conditions. The Plans must be revised thoroughly: They must not contain superimposed corrections. After the grant, the developer may apply for increase in permissible floor area the Developer must pay fees and penalty if modifications are proposed after the work starts, additional penalty applies The developer must deposit a refundable security deposit of Rs. 25/m2 and If the construction is not as per plan, BBMP forfeits this deposit.

Comments:

  1. Ashok kalburgi says:

    If one wants buy a flat, as October not available and builder says he has applied for oc and yet to receive Octel from Bbmp, what should buyer do, buy or cancel purchase of flat ?

  2. Ashok kalburgi says:

    Occupation certificate

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Bidadi GBIT project: Land acquisition process and compensation raises critical questions

As the goverment focuses on land acquisition for the 7,481-acre project, are farmers' rights and crucial social impact checks being compromised?

The Greater Bengaluru Integrated Township (GBIT) in Bidadi, first notified in March 2025, received its final notification in June 2026 under the Karnataka Urban Development Authorities Act (KUDA Act), 1987. The project is branded as India's first and largest AI City, featuring an AI-integrated township. The project will be implemented by the Greater Bengaluru Development Authority (GBDA) under the same act. Three villages, Kempainapalya, Vaderahalli, and Mandalahalli are notified in the Gazette under Section 19(1) of the KUDA Act for the implementation of a development scheme, deemed as public purpose. The development scheme is spread over a total of 7,481…

Similar Story

Karnataka SIR: How to check your ASDDO list status and next steps

The draft electoral rolls will be published on August 24. Karnataka voters, here's what you can do to complete verification by August 17.

In Karnataka's Special Summary Revision (SIR), all enumeration forms have now been digitised. Out of the state's 5.54 crore electors, Booth Level Officers (BLOs) have signed and collected forms for over 4.45 crore voters. However, 1,09,13,776 voters, representing 19.69% of the electorate, have been categorised under the Absent, Shifted, Dead, Duplicate, and Others (ASDDO) list. Following the publication of the ASDDO list on August 4, election officials verified and removed three lakh voters from the list within the first six days. To check your registration details, search the electoral roll, or access voter verification services, visit the Chief Electoral Officer,…