To B or not to B: Weighing the BRTS option for OMR

Residents of OMR attended a public consultation for the proposed Bus Rapid Transit System in Chennai but remain apprehensive about the project and its utility for them. Here's why.

Last week the consultants tasked with preparing the Detailed Project Report (DPR) for the BRTS invited us to a meeting. A few of us from FOMRRA (Federation of OMR Resident Associations), representing citizens living and using OMR (Old Mahabalipuram Road), went to the meeting.

The show started with some short films on the “successfully implemented projects” in Pune, Amdavad, Hubli-Dharwad and others. As the consultation started more than an hour late, they breezed through a PowerPoint presentation. However, we, who follow the mass transit planning and development studies associated with OMR, found that most of the data presented was based on an outdated 2011 report by ITDP. We also found that very little data, especially in terms of vehicle numbers, had been updated and the figures quoted rarely matched with the data that FOMRRA had collected.

Given the fact that OMR is owned/managed by the Tamil Nadu Road Development Company (TNRDC), there was no clarity about the partnership between the two – the toll collecting wing of the government which promises 6 lanes plus service lanes for the toll collected, and the BRTS, which is going to reduce the available number of lanes to 4. Will this reduce the toll rates?

As OMR residents, we believe that any “cut and paste” or “one size fits all” solution that could apply to any other part of Chennai cannot work in OMR because of its unique ecosystem. What we require here is a supplementary feeder service that will enable citizens living in the interior areas to reach the central median of OMR – alignment of the new metro rail system.

Most of the “high quality features” that the consultants were pitching — such as tracking, air conditioned buses and stops, accessibility, etc — can easily be implemented in the current bus system itself. Just because the existing bus and metro system are not disabled-friendly, we don’t go about building an entirely new system. We can solve these issues by strategically building ramps, escalators and elevators. The MTC has already announced that they will be making some buses on all routes disabled-friendly.

As representatives of welfare associations of OMR, we want the consultants to go back to the drawing board and propose a customised solution that would work for our area.

Comments:

  1. Sriram says:

    The entire BRTS idea seems to be ITDP’s brainchild as that seems to be their only agenda. With the city firmly embracing the Metro, most of the proposed corridors overlap the two phases of metro rail and need to be redone. However, the consultants can’t be blamed as the corridors have been selected by ITDP and Govt of Tamil Nadu

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

City Buzz: Rains batter Gujarat, Delhi | Steps for Telangana’s infrastructure…and more

Other News: Plans for 12 new industrial cities, air pollution raises death risk and urban heat islands raise night-time warmings by 60%.

Rains batter Gujarat and Delhi The India Meteorological Department (IMD) issued a red alert for Gujarat on August 26th because of heavy rains in the state. The rains are expected to continue till August 29th, with the IMD marking the state as a ‘flash flood risk’ zone. Baroda recorded 26 cm of rainfall, the highest in the state, from 8.30 am to 8.30 pm on the August 24. Ahmedabad recorded a rainfall of 10 cm, while the state average was 63.36 mm. Since August 24th, low-lying areas have experienced waterlogging, prompting the National Disaster Response Force (NDRF) to conduct rescue…

Similar Story

Draft hoarding policy: Mumbaikars, check it out and send feedback to BMC

Here's the draft and some key points from BMC's new outdoor advertising policy. People can send suggestions/objections till September 9th.

On May 13,  a 140 X 120 feet billboard erected in 2022 collapsed in Ghatkopar, killing 17 people and injuring 74. It clearly violated the permissible limit of 40 X 40 feet specified by the Brihanmumbai Municipal Corporation (BMC). It was reported that the advertising agency, Ego Media, which had put up the hoarding had been leased a total of nine billboards by the Government Railway Police (GRP)—four at Ghatkopar and five more at Dadar Tilak Bridge. Moreover, the due tendering process was followed only for three of them. Terms and conditions in the tender document related to the Ghatkopar…