Commercial Street mishap: Why crores were lost for a Smart City project

Under the Smart Cities Mission, Commercial Street was redeveloped by following TenderSURE guidelines. Why then did the road get damaged so quickly?

When former Chief Minister B S Yediyurappa inaugurated Bengaluru’s Commercial Street in July, one didn’t expect the makeover to run as quickly as it did. Within hours, the so-called ‘Smart’ street was unable to contain the rainwater, which then found its way into shops. Within a week, the street wore its usual haggard look. It certainly didn’t look like a year had been spent giving the road an expensive makeover!

Commercial Street is among the 36 roads being developed under the Smart Cities Mission in the Central Business District (CBD). While the roads under the project have had their issues, none quite like Commercial Street (and these roads have to live up to higher standards than regular roads, don’t they?). So, what went wrong? 

“TenderSURE guidelines diluted”

The roads under the Smart Cities project were designed by Jana Urban Space, part of the Jana Group, as per TenderSURE principles. But while the initial TenderSURE projects like Church Street and St Marks Road are holding strong, Commercial Street was a washout. “TenderSURE has been diluted over and over again. Whatever they now call TenderSURE is not the TenderSURE from the original times,” says Srinivas Alavilli, Head, Civic Participation, Janaagraha, which is part of Jana Group.


Read more: What’s this TenderSURE all about?


While planners and designers follow a set of guidelines and design principles to reimagine roads, these get diluted by the time of execution. Nithya Ramesh, Director, Urban Design at Jana Urban Space, says, “Though the Smart Cities road designs are as per TenderSURE guidelines, we’ve only done the working drawings. We were not involved in the implementation. Unfortunately, I haven’t done a site visit (to Commercial Street) and don’t know why this happened. My informed guess is that it’s because it was done in a hurry or they didn’t maintain the slopes that went toward the storm water drains.”

Nithya adds that some amount of dilution in guidelines is not necessarily a bad thing. “In some cities, dilution is essential. For example, in Bengaluru there are many TenderSURE footpaths, without doing the roads and utilities. I think this is still great because these are places that either didn’t have footpaths or they were in bad condition.” 

But problems arise when a road that’s supposed to be entirely based on a certain set of guidelines (TenderSURE in this case) is diluted. “Then there’s something wrong and why that’s happening needs to be questioned. But if due to time, budgetary or capacity constraints, certain local bodies decide to renovate only footpaths or intersections, I think that’s a great idea. At least they are being honest. Commercial Street doesn’t fit into this,” says Nithya.

Where’s the accountability?

Srinivas Alavilli says that poor execution of works, as in the case of Commercial Street, happens all the time but people don’t pay attention to it. “When it happens in Commercial Street, under the Smart Cities Mission, people notice. Otherwise we are used to bad civic work. So, I’m glad it happened because it creates a sense of accountability in officers, and frustration in people.”   

Commercial Street pavement dug open after inauguration while pedestrians use the road
Though pavements are being dug up again, there are no barricades to prevent citizens from getting hurt. They are forced to walk on the main street. Pic: Ananya Revanna

Trained planners and designers give a lot of thought on how to construct roads, says Akhila Suri, Manager, Sustainable Cities and Transport programme, World Resources Institute (WRI). “But there are many factors that ultimately influence their implementation on the ground,” she says.

This systemic issue can only be solved through political accountability, says Srinivas. “If something fails, who holds the engineer responsible for not doing a good job? Usually the municipal councillor is supposed to monitor the work. If they don’t like how it’s going, they have to escalate it to higher officials. But we didn’t have [BBMP Council] elections for a year.” 

In the absence of an elected BBMP Council, ward committees — which are supposed to monitor all works in a ward — don’t exist either. “In addition, these roads come under Bengaluru Smart Cities Ltd (BSCL) and I don’t know if they can be monitored by ward committees. These are all the checks and balances in our system and at the end of the day, if someone doesn’t do a good job, there isn’t a mechanism to punish or penalise them,” says Srinivas.

A common complaint against ‘Smart’ roads has been that they seem to take just as long to construct as regular roads, cost much more, and fall apart as quickly. So, what makes them different?

Akhila says, in general, there is a lack of awareness about the long-term gains of reimagining roads. “The ultimate goal is to create more inclusive and equitable streets. We tend to look at this as ‘pedestrian priority’. But when you design for pedestrians, you are designing for all the other users on the street. There is data that shows why it’s important to design for pedestrians, but the conversation hasn’t really expanded to demonstrate the clear benefits for vehicles as well,” she says.


Read more: How Bengaluru can build safe, pedestrian-friendly roads


Back to Commercial Street. As a result of the initial shoddy work, the street and its inhabitants must endure more construction as the contractor redoes the footpaths and carriageway. Rajendra Cholan, MD of Bengaluru Smart Cities Ltd, who was unavailable for comments, has mentioned in interviews that the new works will solve the issue of flooding and more. But it seems more of a band-aid fix. It’s essential that we address the systemic issues at hand. 

What is the most pragmatic solution going forward? “Decentralisation. When you want accountability, you have to decentralise. Things should be run and monitored by ward committees,” says Srinivas.

Also read:

Comments:

  1. Swamy says:

    My view is all brown field projects will have few realignments after completing the civil and constructions since live servicing lines has to flow to cater requirements such as water, electric poles, sewage drains OFCs. The quantum of civil work redoing can be reduced when pre feasibility survey and test were conducted and accounted workable solutions. Several contractors in the race to get to L1 of Tendering do not account for the workable solutions. Hence this situation.
    Take the example of Green field projects like NHAI, T2 terminal expansion in KIAL. Infra projects are seamless for execution since it will not disrupt citizens life directly day in and out.
    Now the introspection is the nature of criticism to a failure and will decentralization, elected council and ward committees will erode repeating of these situations. I doubt. Strengthening ULBs with powers and functions and executing officials for a successful completion of a civic project is possible when there is a sense of belonging and pride in taking head on the challenges faced at the time of on ground execution. Keeping the consultation and information of the project transparency will encourage citizen critique and participation.
    My reflection is i do not recollect a case of citizen appreciation to officials/administration for the work seamlessly executed and opened for citizens usage.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai: Out of SRA purview, Jai Bhim Nagar residents stare at a rocky road ahead

Residents and activists continue to fight for rights of Jai Bhim Nagar residents despite several legal and administrative hurdles.

In the previous part of this series, we reported on the demolition of the Jai Bhim Nagar settlements in Powai and delved into the legally dubious history of Hiranandani Gardens where they stood. On October 5th, the Powai police filed an FIR against officials of BMC's S ward, Hiranandani Group (HGP Community Pvt Ltd), and four associates on the recommendation of the Bombay High Court for conducting unauthorised demolitions in Jai Bhim Nagar. The charges against the accused include criminal conspiracy, public servant framing an incorrect document with intent to cause injury, and furnishing false information among others.  About 100-150 families…

Similar Story

The fight over Jai Bhim Nagar: Whose land is it, anyway?

Settlers in Jai Bhim Nagar in Powai’s Hiranandani Gardens were forcefully evicted in June. And it’s a contentious move in more ways than one.

A tarp-covered shed on a busy sidewalk in Powai lights up every evening with the cacophony of children. The ‘sabki library’ is a makeshift after-school space for the children of Jai Bhim Nagar living on the sidewalk, where they show up diligently to study with volunteers from nearby IIT Bombay.  The library was set up there over three months ago, soon after the Jai Bhim Nagar settlement was demolished, and its residents forcibly evicted. While many residents from the 600-odd homes have shifted elsewhere since then, about 150-200 families still live on the streets surrounding the demolished slum. “We have…