Metro work chugging along

But rather wearily, and with many hiccups. Recent update is that 11 cases against land acquisition on CMH Road were dismissed in just three days.

Between 9th and 11th February 2009, the Karnataka High Court dismissed 11 cases against land acquisition, filed by individuals regarding their residential and commercial properties, on Chinmaya Mission Hospital (CMH) Road. The court’s position was the acquisition were made for “public position” and hence cannot be challenged. This means that some of the tenant traders on CMH Road, who were part of the CMH Road Traders Association and had filed a PIL challenging the validity of the project, have also been asked to surrender their tenancy claims. The traders have time until 31st March this year to vacate their premises.

Metro work on 100 feet road, Indiranagar

Metro work on 100 feet road, Indiranagar (pic: Vaishnavi Vittal)

B L Y Chavan, Chief Public Relations Officer at the Bangalore Metro Rail Corporation Limited (BMRCL), claims that this is the first time in the country where tenants affected by an infrastructure project are being offered compensation packages. However, the tenants are not satisfied with the compensation amount, which was decided on the basis of the annual Value Added Tax and Sales Tax that they pay to the government. The tenants’ original demand was that they be allocated shops inside the CHM Road railway station. Chavan says that no such promises were made to the traders in the first place. In any case, as per the station design plans, there is no space for shops.

Until September 2008 BMRCL had been embroiled in long-standing disputes against the acquisition of individual properties in different parts of the city. However, the court has been quick in dismissing land acquisition cases this time around, in a span of just three days. The current judgments have been issued by Justice K L Manjunath.

Around this time last year, Justice Manjunath had also dismissed the CMH Road traders’ petition requesting a change in the alignment of the Metro from CMH Road to Old Madras Road. The judge had questioned the locus standi of the traders, arguing that since most of the traders were tenants and not property owners, they had no legal standing to petition for a change in the Metro alignment. Following this, the traders filed a PIL in the Karnataka high court, stating that the metro rail project was not valid; on the grounds that it was being implemented under the Mysore Tramways Act whereas in reality, the Metro is a train and not a tram. The PIL is being pursued, says Imtiyaz Ahmed, President of the CMH Road Shops and Establishments Association. He adds that the bench now consists of two judges – Gopalgowda and Manjunath.

Progress of work

The work on the Byappanahalli – MG Road corridor has speeded up. This is because the Byappanahalli station will be used as space for parking the trains. Work has also commenced on West of Chord Road and around Rajajinagar area, states Chavan. He points out that the work is proceeding as per schedule and that the litigations on CMH Road have not delayed the works on the road.

Metro work on Old Madras Road

Metro work on Old Madras Road (pic: Vaishnavi Vittal)

Lessons from Hyderabad Metro?

Meanwhile, the Hyderabad Metro Rail Project (HMRP), which has yet to take off, is already in troubled waters. This is because the group implementing the project – Maytas, has now been asked to prove their financial capability by 18th March. Maytas is owned by Satyam Computers which is itself on rocky terrain owing to fudged accounts and finances.

Dr Ramachandraiah Chigurupati, professor at the Centre for Social and Economic Studies (CESS), says Maytas does not have the financial resources to execute the Metro rail project. He is also a member of the Citizens for a Better Public Transport in Hyderabad, a coalition of individuals and civil society organisations who have been campaigning against HMRP.

Protests against HMRP stemmed from suspicions about whether Maytas had been favoured as a bidder even before the final tender was over. This allegation was also raised by E Sreedharan, Managing Director of the Delhi Metro Rail Corporation and chief consultant to HMRP. Other grounds for protests against HMRP include ‘large-scale demolition of buildings, including of the State archives and defacement of the historic heritage precincts’, lack of information sharing with the public about the project such as Detailed Project Reports (DPRs), high levels of noise likely to be caused by the running of the trains, and poor environment assessment of the project.

 

Issues plaguing Bangalore Metro

Some of the issues raised about the Hyderabad Metro also plague the Bangalore Metro Rail Project – DPRs and alignment studies have not been shared with the public and the way environmental clearance was given by the Ministry of Environment and Forests (MoEF). MoEF cleared the Metro rail project on the grounds that that the trains do not cause air pollution. However, no inquiry was made at that time into the noise pollution that would be caused by the running of the trains as well as the air pollution caused in the process of the construction.

Will heritage structures be affected with the Metro construction? Chavan states that the Metro will run underground in crowded areas such as Chickpet, KR Market and Majestic. This is because the surface space is too narrow for construction. The structures likely to be impacted are Tipu’s Palace and the fort. “But this impact will be in terms of the noise and the running of the trains underground. We have taken precaution to lay the lines some distance away from these structures. We have also conducted studies to understand the impact of the construction work and will take measures accordingly,” he said.

Will the current downturn affect the Metro project?

The financing for Bangalore’s Metro rail comes partly from the state government and partly from the central government. The Japan Bank for International Cooperation (JBIC) is also funding the Bangalore Metro rail project.

So, will the current economic slowdown affect the Bangalore project? Chavan suggests that this is not likely, though the state government has committed only Rs. 600 crores for the project in this year’s budget. He was in fact optimistic, stating that the low prices of cement and steel in the current scenario will lower the costs of construction and ultimately benefit the project.

Metro also expects a small amount of additional revenue. Chavan said about five per cent of the revenues for the Metro will come from advertising and another five per cent from property development. Asked whether cafes, eateries and shops will be constructed inside the stations, Chavan emphatically says, “We are not here to do property development. Our task is to facilitate the flow of the crowd in the station, not to add to the crowds. We will have minimum conveniences inside the station premises such as an ATM facility, a small coffee vending machine, et cetra.”

What remains to be seen now, as Dr Ramachandraiah has also pointed out in the case of the Hyderabad, is whether the public will actually take to using the Metro. Citizen Matters requested BMRCL to share the Metro alignment study to understand how the route had been determined and was told that the route was decided on the basis of peak-hour-peak-density traffic.

And so, Namma Metro proceeds……

Comments:

  1. Deepa Mohan says:

    Good report Zainab….I am not sure whether the Metro is a good thing or a bad one….so I am torn between wanting it to get along at a quick pace, and wanting to stop it …but that will still not get the trees back…

  2. Vinay Sreenivasa says:

    The Metro is not really a cost-effective solution at all. After spending 8000 crores and tearing the city apart, the Metro can carry a maximum of 10 lakh people in 2011(as per BMRCL figures). However BMTC carries 30 lakh people per day already. Getting a better bus-system in place (eg. B.R.T) is what most cities in the world do nowadays.It’ll serve more people, is cheaper and does not involve breaking homes, shops, forts and trees.

    Anyways check http://tinyurl.com/cy72bh for more information (its a link to the Hasiru Usiru site)

  3. Palahalli Vishwanath says:

    One should visit Delhi to see the enormous advantage a big city can get by having a metro. Also the rate of progress there in the last five years is phenomenal.It should not be too difficult to compare notes with what is happening there and proceed properly. Mumbai has wonderful bus transport but has Bangalore learnt anything worthwhile from it? Two cities in the same state do not learn from each other. Two states in the same country do not learn from each other.And it goes on. As for METRO, there were talks 5 decades ago to have a train between Yashwantpur and the South End ! Hope METRO becomes a reality very soon

  4. Malolan R Cadambi says:

    Traders evade VAT and other taxes and cannot expect a compensation when they are not honest in the first place. In our country, it takes years to enforce a rental contract and evict a tenant. I do not feel sorry for the tenants. Good riddance!

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Alternative to Bengaluru’s tunnel roads: Improve public transport, enhance mobility, complete projects

Instead of expensive tunnel roads, Bengaluru needs better mobility, metro, suburban rail and buses. Sustainable mobility is the way forward.

Part 1 of this series looked at the cost, risks and challenges of tunnel roads. Part 2 will focus on the alternatives to tunnel roads, and how they can be implemented.  Improve traffic flow: BMTC, Namma Metro and Suburban Rail Metro to Airport:  Namma Metro is extending its Blue Line to Kempegowda International Airport (KIAL) as part of Phase-2B. This metro line, connecting Kasturinagar to KIAL, is expected to be operational by June 2026. Once completed, it will significantly reduce traffic on the road to the airport. Namma Metro Blue Line to Kempegowda International Airport (KIAL). Graphic: Rajkumar Dugar Suburban…

Similar Story

Tunnel roads will not fix Bengaluru’s traffic problem: Here’s why

The tunnel road planned between Hebbal Flyover and Mekhri Circle will cause disruptions and encourage the use of private vehicles.

In October 2023, Deputy Chief Minister/Bengaluru Development Minister, DK Shivakumar, had announced a 190 kilometre-tunnel road as a solution to ease Bengaluru traffic. In May 2024, the Bruhat Bengaluru Mahanagara Palike (BBMP) announced its initial phase plan to construct an 18 kilometre-tunnel road connecting Hebbal and Central Silk Board. This road will include five entry and exit points for vehicles. A tunnel road is an underground passageway for vehicles to travel through. It provides a direct route through an obstacle, such as a mountain or body of water, which would be otherwise impractical or impossible to traverse through by vehicle.…