Roads vs trees turns political

A High Court directive empowered a committee to oversee the city's road widening and metro works and decide on tree felling. NGOs are accusing the committee of disregard for the law.

In response to a public interest litigation, the High Court of Karnataka had directed the Bruhat Bengaluru Mahanagara Palike (BBMP) three months ago to constitute a special committee to monitor its road widening projects and the Metro works. But, the court’s intervention has not impacted the ‘free’ uprooting of trees. 

Trees impacted
Kanakapura Road
Bellary Road
Race Course Road
Palace Road
Sarjapur Road
BBMP note constituting the committee

The BBMP constituted the nine-member ‘Sustainable Development Empowered Technical Advisory Committee’ in July 2008, under the chairmanship of Yellapa Reddy, a retired officer of the Indian Forest Service (IFS. According to the court’s order, the committee has to take public opinion into account and pass orders on the advice of the experts. The court had directed the BBMP and other agencies working on infrastructural development to consult the committee.

The mandate of the committee was to ensure that suggestions, if any, by the public necessarily be considered, provided they were in true public interest, within the realm of law and in furtherance of sustainable developmental works to be carried on by the statutory authorities.

The court also ordered that the committee would pass such orders by taking into consideration all the suggestions that may be offered by the members, keeping in mind the various legal grounds urged in the petition.

Trees cut on Kanakpura Road

Trees cut on Kanakpura Road (Pic: Environment support group)

Soon after the constitution of the committee it was observed that the BBMP and other respondents in the litigation (authorities) were carrying on with road widening and related developmental works in violation of the directions of the High Court. In particular it was also observed that massive tree felling was undertaken on Kanakapura Road, Bellary Road, Race Course Road, Palace Road, Sarjapur Road, amongst others.

Respondents
State of Karnataka represented by the Chief Secretary, Department of Urban Development, Department of Forests Ecology& Environment, Department of Home and Transport, Bangalore Metropolitan Land Transport Authority, Bruhat Bangaluru Mahanagar Palike, Deputy Conservator of Forests and Tree Officer BBMP, Deputy Conservator of Forests Bengalore Urban Division

Petitioners
Environment Suport Group represented by Dr Robert John Chandran, Leo Saldanha
Civic Bangalore represented by Kathyayini Chamaraj

As per the court’s directive, the petitioners — Environment Suport Group and Civic Bangalore represented by Kathyayini Chamaraj — were supposed to be allowed to observe the proceedings of the committee and get a copy of the minutes of proceedings. But they were not allowed to attend even one meeting.

On 25th July 2008 the petitioners went to attend the Committee meeting at BBMP. They hoped that Yellapa Reddy, Chairman of the Committee, would consider their submissions favourably if were presented to him directly. The petitioners had submitted representations and interim applications requesting to look into issues relating to the road widening projects.

“But such hopes were quickly dashed when he expelled the petitioners, disregarding fervent and respectful appeals that the forum ought to be open to petitioners, in the very least, as much it was to the respondents," said Leo Saldanha, Coordinator of Environment Support Group in a press conference on 19th September.

Road widening and tree cutting continues on Palace road

Road widening and tree cutting continues on Palace road (Pic: Environment support group)

He further added that the proceedings of this committee meeting, signed by the convener R Suresh (who is the BBMP’s Assistant Conservator of Forests) inaccurately and unfairly recorded that the petitioners and their advocate entered the committee meeting by aggression.

"Dr Subbarayan Prasanna, a member of the Committee contested this dishonest recording and a decision was taken to strike down that recording by the Chair. However, the Chair reversed this decision in a recent letter to Prasanna and retained the earlier false recording," added Saldanha.

ESG has reported violation of some other orders and that convener Suresh was rejecting submissions made by the petitioners on behalf of the project affected communities. In a letter addressed to the petitioners dated 10th September, the convener mentioned that the petitioners did not have the right of participation in the committee meetings. The letter said that all the concerns of the petitioners had been considered in the five meetings held by the committee.

Tree cuttings on race course road

Tree cuttings on race course road (Pic: Environment support group)

A careful review of the committee’s proceedings unofficially obtained by the petitioners, however, revealed that not a single written submission made by the petitioners was considered by Reddy nor have these been brought to the attention of the members in a formal way.

Members of the committee expressed their dismay and disappointment over such arbitrary conduct of the committee’s proceedings, according to Saldanha. Some had written detailed letters to Reddy requesting for a proper procedure to be instituted to conduct meetings in a transparent and publicly accountable manner, he added.

Carol Upadhyay, a professor at the National Institute of Advanced Studies and one of the committee members expressed her concern that there could be the possibility of bias when the committee listened to issues only from the perspective of the respondents. She also added that transparency was the key point for which such a committee was formed at the first place, but that seemed to be getting blurred in due course.

However, Yellappa Reddy refused to respond to any questions when contacted. Convener Suresh promptly said that the committee was following all the rules put by the court and was functioning accordingly. In fact sources say that he sent a letter recently to all the petitioners refuting allegations that the committee’s workings were wrong.

Several members have repeatedly insisted that no project should be considered for approval unless they were in full compliance with law and involved the public in decision making. (This was the premise of the original litigation filed in the High Court.) In some instances it has also been highlighted that the minutes were not an accurate reflection of the proceedings of the meetings. But no action seems to have been taken on these allegations. Instead the tree officer and the convener has given further permission to cut more trees without consensus from the committee members.

Such is the status of a committee whose constitution was initiated by no less a body than the High Court. What then is next recourse of the common public?

RELATED
RELATED

Related Articles

Green today, gone tomorrow
Committee to review road widening: High Court

Comments:

  1. Omar Farook says:

    I am happy that Environment Suport Group and Civic Bangalore is working to control the ‘free’ uprooting of trees. We all need to support them otherwise our lungs will get choked with carbon-dioxide. Maybe something similar to ‘No Smoking’ ban should be imposed.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Anger behind the wheel: How to rein in the growing menace of road rage

Traffic congestion coupled with anxiety, peer pressure and a lack of self-awareness has led to an increased number of road rage incidents.

Priyanshu Jain, an MBA student at Mudra Institute of Communications (MICA) in Ahmedabad, tragically lost his life in a road rage incident on November 11th. The 23-year-old was stabbed by Virendrasinh Padheriya, a head constable in the city, following an altercation. Padheriya, who has a criminal past, was later apprehended from Punjab. Priyanshu's family and friends are devastated by his death, and both his hometown of Meerut and citizens in Ahmedabad are demanding justice. A series of protests have been organised, including a silent march, a candlelight vigil, and a peaceful hunger strike. Pranav Jain, his cousin, describes Priyanshu as…

Similar Story

How a student app to connect with share autos can help commuters in Chennai

A team from St. Joseph's Institute of Technology and IIT Madras makes commuting easy for Chennai residents through their innovative app.

Crowded buses, with passengers jostling for space, are common on Chennai's roads. The city has many public transport users, including college students and people commuting daily for work. Share autos play a crucial role in providing last-mile connectivity, helping passengers travel from bus stops and MRTS stations to their final destinations. These share autos fill the gap by making multiple stops between bus stations, schools, colleges, and other key locations. However, the share auto system has its shortcomings, the most notable being that it is unreliable. Share auto drivers often decide daily whether to stop at a specific location. If…