Water harvesting pits or just pits?

BBMP has allocated Rs 30 cr for setting up RWH pits in the city. But faulty design may render much of this useless.

Last year, BBMP initiated a plan to install Rainwater Harvesting (RWH) pits in roadside drains, parks etc,. to improve ground water levels. Rs 30 crore was approved for installing pits across the city, from emergency funds. Emergency funds are allocated as per BBMP Commissioner’s discretion, and is separate from funds specifically given for RWH in the budget. But going by BBMP’s plans, much of this amount might simply be wasted.

An RWH pit built along a drain in 27th Main, Jayanagar 9th Block. File Pic

The project is supposed to be implemented as per the design made by RWH expert A R Shivakumar. Shivakumar is principal investigator-RWH at KSCST (Karnataka State Council for Science and Technology), of IISc (Indian Institute of Science).

Not the expert’s design

Shivakumar had given a presentation to BBMP Commissioner and other top officials on the design and estimates to be adopted. But in many wards, BBMP engineers have adopted their own designs, which RWH experts say would not stand a chance in the rains.

Wards like Rajajinagar and Basaveshwarnagar have adopted Shivakumars design of an open (empty) pit. Some others like Arekere and Puttenehalli have adopted a different design, in which the pits are not open, but are filled with granite gravel and sand throughout. In both wards, 50 such pits will be dug on road side drains; each pit costs Rs 50,000. Combined, they cost Rs 50 lakh.

Shivakumar opines that the design in Arekere and Puttenahalli wards are not fit for roadside drains, but are meant for big compounds. “It would work in large spaces like Vidhan Soudha. If used in roadside drains, water will not seep through and the pit will be clogged in a few months.”

Rain water expert S Vishwanath says, “The sand and granite jelly (gravel) can be easily eliminated from the design, or else replaced by large boulders. If there is sand in the recharge pit, it will have to be cleaned after every rain; else there will simply be no percolation into the ground.”

Will it be effective?

He says that BBMP should have made one or two recharge pits initially and tested its effectiveness, rather than digging all pits at a time. “Is there an understanding of the location of pits and the nature of the soil? For example, if the soil is clay-like, the structure will not work,” he says.

The effectiveness of the pits can be measured only after one or two rainy seasons, by checking if water levels have risen in the nearby borewells.

RWH pit model approved for Arekere and Puttenahalli. Pic Courtesy: BBMP

Narasimha Babu, Assistant Executive Engineer (AEE) at Puttenahalli and Arekere wards, says  that the design was adopted from another zone, but was not sure which zone it was. “Works have already been done in Jayanagar with this design.”

His justification for the new design seemed specious. “With open pits there is a chance of someone removing the mesh and people falling in. They are difficult to maintain.”  When pointed out that there would also be a reinforced concrete slab along with safety mesh covering the pit, Babu said that there was still a chance of accidents.

Engineers clueless

The design for each ward is made by the concerned AEEs and AEs (Assistant Engineers). These are then approved by the Executive Engineer, Chief Engineer and Joint Commissioner of the zones. BBMP head office is not involved with the design approvals. Srinivas Murthy, Executive Engineer at Bommanahalli zone who had approved the Puttenahalli and Arekere projects, were unaware of the design change. He had initially said that Shivakumar’s design was adopted.

B S Prasad, Chief Engineer (RWH & OFC) at BBMP head office, says that he is not aware of specific designs as they are made at the ward level. “Our job is to only monitor the projects and get data from wards. Design approval is not routed through us.” He says that all 198 wards have started the work, which will be done in phases, but that the department has not received the entire Rs 30 crore yet.

Additionally, the estimates for works also seem suspect. Companies that handle RWH projects quote much lesser amounts. On being shown the design, one company Refurb-India quoted only Rs 20,600 for the Arekere-Puttenahalli project, and Rs 22,900 for the Rajajinagar-Basaveshwaranagar project. The latter, as per BBMP estimates, would cost Rs 39,000. BBMP says that the estimates were prepared as per current specifications, and hence there is no inflation.

In Puttenahalli and Arekere, the works on drains are yet to take off. Though tenders were called last year, BBMP has not got any responses for those; the tenders are again open for bidders now. Works in open spaces have started off.

Puttenahalli ward has Rs 55.5 cr for RWH works, of which works worth Rs 5.5 lakh has been completed. Arekere ward has Rs 66 lakh allocation, of which works worth Rs 18.5 lakh is going on. Overall, in Bommanahalli zone, Rs 2.12 cr is allocated for RWH work, of which works of Rs 50 lakh is completed, and those worth Rs 34 lakh is going on.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai floods once again. Will BMC’s climate budget help?

Experts say that BMC's recently launched climate budget needs to be more focused on urban flooding to be able to protect vulnerable citizens.

On July 8th, rains lashed Mumbai, disrupting regular life and causing waterlogging and floods in low-lying areas and on important routes. Central Railway officials mention that almost 900 train services were cancelled leaving several commuters stranded, while many BEST buses were diverted. Since then several incidents of heavy rains and flooding have been reported in the city. Commuters, civic activists and residents have questioned the claims made by the Brihanmumbai Municipal Corporation (BMC) about being prepared for the monsoons.  “The half-constructed, newly-built DP road number 9 in Chandivali was waterlogged, which caused inconvenience to commuters,” said Mandeep Singh Makkar, founder…

Similar Story

Mumbaikars get a taste of Murbad’s forest food and tribal culture

It was a treat for city dwellers to learn about wild vegetables and other forest foods harvested by tribal communities of Murbad, near Mumbai.

Throughout the year, vegetable shops and markets are stocked with select vegetables and produce that form our diets. This produce is grown in large scale farms and sold across the country despite geographic and seasonal variations. But 23rd June was an aberration for some of us, who spent time at the Hirvya Devachi Yatra. We got in touch with forest foods that grow in the wild, people who harvest them and make delicacies out of these.  The Hirvya Devachi Yatra was organised this year by the Shramik Mukti Sanghatana, Van Niketan, Ashwamedh Pratisthan and INTACH Thane Chapter. It has been…