Key garbage plant unapproved, dumping spreading diseases

Much of Bangalore's wastes are being dumped in a one-acre plot at Subbarayanpalya near Rajarajeshwari Nagar. A garbage processing plant is yet to see light of day, and residents are suffering.

Bruhat Bengaluru Mahanagara Palike‘s Rs 600 million garbage segregation plant at Subbarayanpalya, an interior village in Kumbalgudu, which should have been completed by the end of 2011, is still at the tender stage. The area is near Rajarajeshwari Nagar in SW Bengaluru.

Sixty-five trucks reportedly visit this site daily to dump waste from Bangalore. Pic: Sankar C G

As per information from the BBMP website, the tender process for the 750 metric-tons-per-day plant should have been wound up before April 10, 2011.

"It was in 2009 that BBMP thought of implementing a new automated garbage plant, similar to the one in Mumbai, by considering the garbage elimination problem in Subbarayanpalya," said Puttamurthy, Assistant Engineer at the BBMP’s Solid Waste Management Department.

After processing the tender, an additional nine months are needed to build the plant.

"We had canceled the first tender process because of the lack of bidders and competition," Puttamurthy said.

Residents falling sick

Most of Bangalore’s wastes have been dumped in a one-acre plot here for the past eight years.

"3,500 tonsof waste is produced in Bangalore in every day, out of which more than half is dumping in Subbarayanpalya," Puttamurthy said.

Due to this, people living there suffer from itching, allergy, malaria and other diseases.

"We protested against it three or four times but it was of no use," said Manjunath, a local resident. "Sixty-five trucks reach here daily to dump wastes from Bangalore."

Most of Bangalore’s waste has been dumped on the one-acre plot for the past eight years. Pic: Sankar C G

"Our children miss classes because of fever and other diseases. We can’t even have food because of the bad smell of garbage," Manjunath added.

Pollution control board  has ‘no idea

"In 2010, the mayor and deputy mayor of BBMP visited the plant and formed a technical committee, headed by officers from pollution control board, the Solid Waste Management Department, the Indian Institute of Science and others, to study about it," Puttamurthy said. "The committee later recommended this project."

"Automated garbage plant is a new technology for segregating wastes," Puttamurthy said. "After segregating wastes, plastics will be sent for recycling, domestic waste for biogas production, and the remaining 20 percent will be sent for landfill."

But the pollution control board officer, who is supposed to provide environmental clearance for the project, said: "We don’t have any idea about the plant that BBMP going to implant in Subbarayanapallya. We have not provided any approval for the plant as the BBMP has not approached us for approval of the plant so far."

After the project was approved, BBMP built two similar plants at Mandoor and Mavelipura. The BBMP is now exploring ways to generate electricity from the waste at the plant in Mavelipura.

Meanwhile, the villagers in Subbarayana Pallya are living with huge piles of garbage in their backyard.

Comments:

  1. kavitha venugopal says:

    I appreciate your work and your effort to dig out this issue which is spoiling a new generation in Subbarayanpalya,a gift given by concern authority… who should work for their welfare.

    TILL NOW THEY ARE THINKING….
    Let them think and plan mean while if once they would have thaught about the residents who are suffering they would have act.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai floods once again. Will BMC’s climate budget help?

Experts say that BMC's recently launched climate budget needs to be more focused on urban flooding to be able to protect vulnerable citizens.

On July 8th, rains lashed Mumbai, disrupting regular life and causing waterlogging and floods in low-lying areas and on important routes. Central Railway officials mention that almost 900 train services were cancelled leaving several commuters stranded, while many BEST buses were diverted. Since then several incidents of heavy rains and flooding have been reported in the city. Commuters, civic activists and residents have questioned the claims made by the Brihanmumbai Municipal Corporation (BMC) about being prepared for the monsoons.  “The half-constructed, newly-built DP road number 9 in Chandivali was waterlogged, which caused inconvenience to commuters,” said Mandeep Singh Makkar, founder…

Similar Story

Mumbaikars get a taste of Murbad’s forest food and tribal culture

It was a treat for city dwellers to learn about wild vegetables and other forest foods harvested by tribal communities of Murbad, near Mumbai.

Throughout the year, vegetable shops and markets are stocked with select vegetables and produce that form our diets. This produce is grown in large scale farms and sold across the country despite geographic and seasonal variations. But 23rd June was an aberration for some of us, who spent time at the Hirvya Devachi Yatra. We got in touch with forest foods that grow in the wild, people who harvest them and make delicacies out of these.  The Hirvya Devachi Yatra was organised this year by the Shramik Mukti Sanghatana, Van Niketan, Ashwamedh Pratisthan and INTACH Thane Chapter. It has been…