High Court to question BDA on Sankey Road widening

The citizens' side explains to High Court that city authorities did not tell the whole story in 2005 when the master plan for Bangalore, including Sankey Road widening, was thrown open for objections.

The High Court case on Sankey Road’s widening, which citizens had filed against BBMP and state government, will include BDA as a party. Five citizens and the residents’ association Malleswaram Swabhimana Initiative had jointly filed the PIL last month when BBMP cut 17 trees across Sankey road stretch.

HC ordered a stay on BBMP’s tree cutting at the time, when two of the 17 trees were still standing. Hundreds of trees are expected to be cut for road widening from Cauvery Circle to CNR Rao Circle, and subsequently till Yeshwanthpur flyover.

The High Court bench headed by Justice N Kumar passed the order to rope in BDA into the case, during a hearing on August 10. This was because the petitioners’ counsel questioned BDA’s RMP (Revised Master Plan) map, which is the basis for road widening projects.

Petitioners’ counsel K G Raghavan specified that citizens were not questioning the RMP itself, but only its execution. He highlighted sections of the Karnataka Town and Country Planning (KTCP) Act, which defines RMP. According to these, RMP should include a series of maps showing complete street pattern, showing all roads and their traffic circulation patterns. Improvement proposals should be specifically mentioned. After this, the draft plan has to go to government and then put in public domain, calling objections from citizens. The final plan will be published after this.

Clip of the Sankey Road section of a map from Revised Master Plan 2015. See 30m marked as an encircled (30).

The counsel presented copies of the RMP map for Malleswaram to the judges and asked if they could recognise Sankey road widening plan in the map. The road is to be widened from 12 m to 30 m. The RMP map shows a small circle with ‘30′ inscribed in it, along the road marking. The legend section on the map says that the circle symbol indicates ‘proposed width of road in meters’.

"The existing road width is not mentioned. Even proposed widening cannot be identified by laypeople using this map, if they have to put forth objections," Adv Raghavan said. The previous (1995-2005) CDP had clear markings to indicate widening – proposed width of roads were mentioned in text across the length of road, on maps.

Vijayan Menon, member of the citizen’s group Koramangala Initiative and the city-based Citizen’s Action Forum (CAF), agrees. CAF as one of the petitioners in the 2008 PIL that challenged the legal validity of RMP itself (link to https://citizenmatters.in/articles/view/270-cdp-charged). "A marking on the final plan without any further details to explain it, does not help. There was no clarity on the exact extent of widening and reasons for it. There were no consultations after the final RMP was published, which is contrary to practice all over the world." Menon also accuses BBMP of not being consistent in its own practices. "In some cases like in Hosur road, BBMP is not doing the full extent of widening as in the RMP. So projects are taken up as per BBMP’s convenience."

For it’s part, the court accepted counsel Raghavan’s argument and said that this issue should be clarified by BDA. The petitioners have already sent a notice to BDA. On August 19, BDA will appear before the court. Date of next hearing will be fixed on 19th.

The case has been getting delayed as it was moved to different benches. It was first heard by the bench headed by Justice Manjula Chellur, who inspected the spot while BBMP cut the trees and ordered a stay on it. It was then heard by the bench headed by Chief Justice J S Khehar, who moved it back to Justice Manjula.

When the case came to Justice Manjula, BBMP Counsel objected citing conflict of interest – Justice Manjula’s son was working with Adv Raghavan. The case was then transferred to Justice N Kumar.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Making Mumbai school buses safe and accessible: What stakeholders want

A Maharashtra government committee is drafting school bus guidelines. Parents and operators highlight key issues they want it to address.

“It is something you will remember throughout your life,” says Archana Patney about the experience of making friends while riding the bus to school. She opted for the school bus for her older child, but not for her younger one. She is among the many parents in Mumbai who have to make this important decision come June every year. The Maharashtra Transport Department is set to introduce new regulations for school buses in the upcoming academic year, with a committee led by retired transport officer Jitendra Patil tasked with drafting these measures. This decision follows a series of crimes against…

Similar Story

Sion overbridge: Work in progress or a project stalled?

The delay in reconstructing one of Mumbai's iconic bridges is inconveniencing commuters. Residents hope the project will be completed soon.

On August 1, 2024, the Sion overbridge was closed for a two-year reconstruction project, disrupting traffic and daily commutes. The plan is to rebuild the century-old bridge — originally constructed across the railway tracks in 1912 — through a collaboration between the Central Railway and the BMC. However, to the dismay of citizens, the bridge has yet to be demolished. What are the reasons for this delay? Inconvenience to commuters The bridge connecting Sion East to Sion West serves as a vital link between Lal Bahadur Shastri (LBS) Marg, Dharavi, the Bandra Kurla Complex (BKC), and the Eastern Express Highway.…