Now, 3-hour scheduled power cuts daily

After ten days of erratic power cuts in Bengaluru, BESCOM’s return to ‘normalcy’ means this: three-hours of scheduled load-shedding, at one hour per cut, in residential areas everyday.

After more than a week of erratic power cuts, BESCOM now says things will slowly get back to normal. "Everything is stabilised", says H Nagesh, Director (Technical), BESCOM. Nagesh says that load-shedding will now be scheduled.

BESCOM officials say domestic feeders will face three-hour power cuts daily. Pic: Vaishnavi Vittal

To know when you are likely to loose power during the day and how many times, read the tables in this article..  For domestic feeders, there will three hours of power cuts daily,  one hour per cut, in three time windows: 6 AM to 10 AM, 10 AM to 2 PM, and 2 PM to 6 PM.

For commercial feeders, power cuts will be two-hours a day in two cycles: 2 to 4 PM and 4 to 6 PM. In the case of industrial feeders, powers cuts are for a maximum of 6 hours. This is between 6 and 8 AM in the morning, and between 6 and 10 PM in the evening. The rest of the day, industrial feeders receive uninterrupted power supply, says Nagesh.

The batches will change every week on a rotation basis, starting Mondays.

Feeder type

Hours of load-shedding

Timings of power cuts

Domestic

3

6 AM to 10 AM

10 AM to 2 PM

2 PM to 6 PM

(one hour in each batch)

Commercial

2

2 PM to 4 PM

4 PM to 6 PM

(one hour in each batch)

Industrial

6

6 AM to 8 AM

6 PM to 10 PM

Mixed (Residential and Commercial)

4

8 AM to 10 PM

6 PM to 10 PM (cyclical)

Data courtesy: BESCOM

How to read the box above: For example, when power is cut off from 6 AM to 7 AM in an area, then there will be power cuts from 10 AM to 11 AM, and finally from 2 PM to 3 PM. Similarly, if power is cut from 7 AM to 8 AM, then it will again be cut from 11 AM to 12 noon, and 3 PM to 4 PM. The cycle continues this way for different areas.

In some areas, where there are mixed feeders (both commercial and residential), power supply is cut for four hours a day. This is between 8 AM and 10 PM in the mornings and is cyclical in the evenings, between 6 and 10 PM.

There will be no power cuts during night times.

Bengaluru’s shortage to continue

Nagesh also says that the state is now buying power from both private and central government sources. This includes 200 MW from the Jindal Power Plant  in Bellary, 200 MW from the Power Trading Corporation and another 200 MW from the National Thermal Power Corporation.

H Nagesh, Director (Technical), BESCOM.
Pic: Vaishnavi Vittal

This apart, power supply from state-owned plants include: 800 MW from five units of the Raichur Thermal Power Station (earlier it was about 500 to 600 MW), 200 MW from the Bellary Thermal Power Station (which may go up to 400 MW), 50-150 MW from the Almatti dam and 589 MW from the Sharavathi. The state also produces power through wind energy. This accounts for about 100 MW on an average daily.

BESCOM’s sources of power
Raichur Thermal Power Station – 800 MW
Bellary Thermal Power Station – 200 MW
Almatti dam – 150 MW
Sharavathi plant – 580 MW
Wind power – 100 MW

New sources
Jindal Power Plant – 200 MW
Power Trading Corporation – 200 MW
National Thermal Power Corporation – 200 MW

The figures shown indicate power generated at the station. Of this, BESCOM receives only 50%, of which 25% is for Bangalore city.

BESCOM receives about 50% of the total power supply in the state. Of this, Bangalore City is allocated approximately 25% of power.

In total, Bangalore is supplied about 1500 MW of power, whereas the demand is around 1800 MW, making the shortage close to 300 MW approximately.

The crisis of the past few days has shown a steep rise in the number of complaints. While on a regular day, BESCOM receives around 1000 complaints (not just related to power cuts), the last ten days has seen a one and half time increase in the number of complaints.

If you make any observations about BESCOM’s load-shedding schedule in your area, do write in to Citizen Matters here

Nagesh says the power crisis was due to technical snags at the Raichur Thermal Power Station and Udupi Power Station. But now as the state is purchasing power and with scheduled load-shedding, Nagesh says the scene is likely to get better.

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

Bidadi GBIT project: Land acquisition process and compensation raises critical questions

As the goverment focuses on land acquisition for the 7,481-acre project, are farmers' rights and crucial social impact checks being compromised?

The Greater Bengaluru Integrated Township (GBIT) in Bidadi, first notified in March 2025, received its final notification in June 2026 under the Karnataka Urban Development Authorities Act (KUDA Act), 1987. The project is branded as India's first and largest AI City, featuring an AI-integrated township. The project will be implemented by the Greater Bengaluru Development Authority (GBDA) under the same act. Three villages, Kempainapalya, Vaderahalli, and Mandalahalli are notified in the Gazette under Section 19(1) of the KUDA Act for the implementation of a development scheme, deemed as public purpose. The development scheme is spread over a total of 7,481…

Similar Story

Karnataka SIR: How to check your ASDDO list status and next steps

The draft electoral rolls will be published on August 24. Karnataka voters, here's what you can do to complete verification by August 17.

In Karnataka's Special Summary Revision (SIR), all enumeration forms have now been digitised. Out of the state's 5.54 crore electors, Booth Level Officers (BLOs) have signed and collected forms for over 4.45 crore voters. However, 1,09,13,776 voters, representing 19.69% of the electorate, have been categorised under the Absent, Shifted, Dead, Duplicate, and Others (ASDDO) list. Following the publication of the ASDDO list on August 4, election officials verified and removed three lakh voters from the list within the first six days. To check your registration details, search the electoral roll, or access voter verification services, visit the Chief Electoral Officer,…