BDA continues to disrupt peace of HSR layout

BDA's flyover construction work at the meeting point of 14th Main and Ring Road junction is causing severe traffic congestion.

During the past three to four years, the residents of HSR layout have been subjected to tremendous hardships and inconveniences due to BDA’s flyover and bridge constructions.

During 2007-08, a bridge construction work at the junction of 14th Main and Ring Road junction (HSR junction) went on for more than 15 months. During that time all entry points to HSR layout except for one or two were closed from Ring Road side. Residents had to take diversions from all sectors.

Now, BDA’s yet another flyover construction work at the meeting point of 14th Main and Ring Road junction is causing severe traffic congestion. Couldn’t the planners forecast construction of this flyover two years ago, when the bridge construction was going on? We fear that all incoming traffic from Madiwala side will be diverted inside HSR layout till the completion of the flyover construction.

Digging and relaying works in some roads by BWSSB, BSNL, BDA and BBMP are also going on in this layout. There is lack of coordination among the agencies in all these works. Why is the planning so slipshod? When will this end? The layout now suffers from air and noise pollution. We certainly deserve better treatment.

Traffic diversions from the Sarajapur and Ring Road into HSR layout, due to construction of flyover at Agara circle have seriously inconvenienced the residents and shopkeepers. All mains and some cross roads have been used mercilessly by all types of vehicles plying on them. The flyover construction work is still going on, however, we were earlier informed that the work will be completed in four months. We do not know when this will be completed. The authorities should have put in place a co-ordinated solution before resorting to this unilateral and sudden decision.  ⊕

RELATED
RELATED

Related Articles

Peace of HSR Layout disturbed

Comments:

  1. Kirshnan says:

    I completely agree with this article. Constuction will go on and on.. If one gets over after years another one will start. May be metro, cable lying some thing or other.
    Bangaloreans are now used to it!
    Imagine: We can always dicuss this hours together with others else where and they can always ask. People return from many places and can still enjoy these. And if at all constuction get complete it will hit big headlines and lots of reasons to celebrate..

  2. B Dutta says:

    Most probably when the Agara flyover is completed, Kormangala traffic would be routed through the sarjapur road, while the Silk Board traffic would be diverted through HSR.

    The sad thing is that, in this arrangement, the trucks and other heavy vehicles would still ply through HSR. This happens to be my biggest complaint.

    Another issue is making the 27th main one way. I miss my favorite petrol pump near BFC.

    Also, for people going towards Marathalli, exiting through the narrow stretch of the crowded 24th main is a big big pain.

    The BDA complex flyover is probably going to take another 2 years to complete. Speaking of which, we would really appreciate if the Citizen Matters people somehow manage to share the designs for BDA complex flyover(the same way they did for the Iblur and Agara flyovers).

    I’ve seen more flyovers under construction at Bellandur, Intel and so forth. Coming 2 years is going to be a harrowing experience for people travelling to the airport. Hopefully for better posterity.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Ways to make the cycling track in Mumbai’s BKC more commuter-friendly

As traffic gets worse by the day in the business district of Bandra Kurla Complex, utility and need for the cycle track comes under scrutiny.

In the past few months, heavy traffic jams in the Bandra Kurla Complex (BKC) have led to suggestions of drastic measures. Mumbai’s guardian minister Mangal Prabhat Lodha has proposed that the dedicated cycle tracks at BKC be scrapped and merged with the main vehicular road to accommodate more vehicles.  This has led to much debate about the fate of the BKC cycling track, Mumbai’s first and longest stretch of planned cycling track. However, the Mumbai Metropolitan Regional Development Authority (MMRDA) is yet to officially declare its intent and whether it will act upon Lodha’s suggestion.  However, the cycling track which…

Similar Story

Rating Mumbai’s walkability: Which neighbourhood came out on top?

With its wide, tree-lined footpaths, the Dadar East route had the best walkability scores while Mahakali Caves Road was rated the lowest.

Over nine months, we at Walking Project in Mumbai hosted 25 community walks across various neighbourhoods in the city. In groups of 10–15 people, walking across different neighbourhoods, we discussed walkability, educated citizens about the guidelines which dictate the design of walking spaces nationwide, and advocated for urban planning that prioritises walking, among other topics. One of the key highlights of this initiative was the ranking system we developed for the routes we walked. During each walk, we asked participants to rate their route based on specific walkability criteria. This allowed us to create a ranking of the best and…