BWSSB projects March 2021 deadline for sewage network in 110 villages

Better groundwater quality in cities requires an underground sewage network and its timely treatment and usage. Outskirts of BBMP limits in Bengaluru are yet to be covered by a sewage network, though plans are underway.

Solving their civic-woes has been a challenge for the 12 lakh residents living in the 110 villages on the outer circle in the Bruhat Bengaluru Mahanagara Palike (BBMP) limits, in Bengaluru. Not only has the struggle to get drinking-water been unfruitful, the lack of drainage network lets the sewage accumulate in open drains and lakes, causing irreversible long-term ecological and health problems.

There is, however, about to be a slight change in their plight. The infrastructural work to lay underground drainage facilities in the five zones — Mahadevapura, Byatarayanapura, Bommanahalli, Dasarahalli and RR Nagar — officially commenced on March 15, 2018 and March 19, 2018 respectively. A progress-review report presented during a meeting at the Bangalore Water Supply and Sewerage Board (BWSSB) head office on May 26, 2018 says that 36 months is the timeline set to complete building the sewerage system for the 225 sq km added to BBMP in 2007. That means by March 2021, the sewage network will be connected to the erstwhile villages. 

Most importantly, a presentation by BWSSB in possession with Citizen Matters reveals that 14 STPs and 7 Intermediate Sewerage Pumping Stations (ISPS) have been proposed by the board (table below).

The table below shows the locations and capacities:

Proposed STPs and ISPS under the Cauvery Water Supply Stage V scheme Source: BWSSB

Zone STPS MLD ISPS MLD
Bytrayanapura Jakkur 7.0/11.0 Bellahalli 0.9/1.5
Yelahankakere 6.0/15.0
Doddabettahalli 7.0/11.0
Bilishivalli 17.0/27.0
Mahadevapura Varthur 15.0/24.0 Hagadur 15.0/24.0
Bommanahalli Pilaganahalli 4.06/6.0 Naganathapura 9.0/13.0
Thalaghattapura 5.0/8.0
RR Nagar Somapura 8.0/12.0 Arehalli 1.1/1.7
Hemmigepura 13.0/20.0 Hemmigepura 1.7/2.5
Dasarahalli Kariobavanahalli 10.0/16 Herohalli 0.5/0.7
Herohalli 3.0/5.0 Doddabidarakullu 8.1/ 2.8
Hosahalli 6.0/10.0
Chikkabanavara-2 4.0/10.0
Nagasandra 9.0/13.0

 

The map of proposed STPs. Source: BWSSB/JICA

There are two Detailed Project Reports that were prepared to avail the loan from JICA. The approved DPR does not contain the plans for sewers and house constructions. Instead, it sticks to the projected increase in sewage generation up to 2049 and the proposed Sewage Treatment Plants. The reason is that the first DPR prepared in September 2016 already had a networking plan of lateral sewers and was hence excluded, which the department plans to use for reference.

Projected sewerage generation

The villages became a part of Bengaluru when Bengaluru Mahanagara Palike (BMP) became Bruhat Bengaluru Mahanagara Palike (BBMP) by expanding to accommodate 7 city municipal councils, 1 town municipal council and the 110 villages. This was largely unplanned, and increased the burden of sewerage. Sewage from Bengaluru area is projected to reach 1345 MLD by 2019 – almost equivalent to the city’s daily water-distribution (1400 MLD).

JICA claims that the existing 14 Sewerage Treatment Plants (STPs) within BBMP area had the capacity to treat 57.4% of sewerage in 2016. The JICA Preparatory Survey makes an ambitious estimation of capacity to process a good 97% of the waste water by 2034. The below table shows the projected growth of sewage generated in the city’s core areas, ULBs and 110 villages up to 2049.

Area 2016 2019 2024 2034 2049
Core 745 762 792 856 961
ULBs 323 366 447 634 1,005
110 Villages 190 217 263 372 587
Total 1,258 1,345 1,502 1,862 2,553

Source: JICA Preparatory Survey. (MLD)

Budget for sewage lines

The work to provide sewerage facilities is being taken up in three packages.

  • The first package (Byatarayanapura and Mahadevapura) is estimated at Rs. 327.11 crore.
  • Bommanahalli will be taken up in the second package costing Rs. 301.55 crore.
  • Dasarahalli and RR Nagar in the third package will cost Rs 296.38 crore.

The BWSSB in its progress report has mentioned the period of completion as 36 months. It implies that by March 2021, all the 110 villages would have a fully functional drainage system.

The Bangalore Development Authority (BDA) is managing the upkeep of the villages, which also have layouts for bank employees and revenue officials. It still took a decade to get administrative approval to start drainage work, which came as late as 2017 under the order number UDD-174 MNI 2017, issued on November 7, 2017. The order gave the BWSSB the permission to start establishing the entire sewerage network at a cost of Rs 1,000 crore combined with STPs and ISPS projects.

Unlike the water distribution-network which is being funded by the Japanese agency JICA, the Karnataka government is pooling in half the amount by bearing Rs 500 crore for the sewerage network. The first half ( Rs 250 crore) is being given through a grant and the other Rs 250 crore is being loaned to BWSSB.

The below table offers a breakdown of the finances and timelines.

Zone Contractor Awarded cost Commencement Date Period of completion Date of completion
Byatarayanapura

& Mahadevpura

M/S Khilari Infrastructure Pvt Ltd Rs 327.11 crore 15.03.2018 36 months 14.03.2021
Bommanahalli M/S Larsen & Toubro Ltd Rs 301.55 crore 19.03.2018 36 months 18.03.2021
R R Nagar & Dasarahalli M/S Larsen & Toubro Ltd Rs 296.38 crore 19.03.2018 36 months 18.03.2021
Total: 925.04

Source: BWSSB

The GoK and BWSSB are sharing the cost by dividing Rs 500 crore each. Bangalore Water Supply and Sewerage System (BWSSB) is also using their own funds of Rs 500 crore through the finance collected from Beneficiary Capital Contribution (BCC), Greater Bangalore Water And Sanitation Project (GBWASP) and AMRUT (Atal Mission for Rejuvenation and Urban Transformation) scheme.

This concept was followed in constructing sewage networks in the eight Urban Local Bodies added in 2007, for which funding was generated through the same channels.

Also read: Part I of this series covering the status of water network for 110 villages.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Civic amenities and urban growth: Lessons from a design jam on Bengaluru BBMP Bye-laws

Access to civic amenities like parks is skewed even when they exist as per BBMP bye-laws, finds a representative study of three Bengaluru wards.

In the OpenCity Bengaluru Design Jam on BBMP, our team analysed and debated the bylaws and zoning rules governing civic amenities, parks and open spaces in the city. As a diverse group of spatial thinkers and design creatives, we sought to understand what liveability meant for citizens navigating the urban landscape, and how building and zoning laws address our needs and the city’s densifying future. Urbanisation is transforming cities worldwide, significantly impacting the quality of life both socio-economically and environmentally. In democratic societies, livability crises affect and are affected by the different levels of urban growth and how cities are…

Similar Story

Why all Bengaluru lakes need a biodiversity survey: Lessons from Dorekere

The Dorekere survey highlighted the importance of documenting the biodiversity of lakes and the need to involve the community in such an activity.

A lake is not just a body of water, it is an ecosystem. Action Aid Association India organised a survey to document the biodiversity of Dorekere, a lake in South Bengaluru. The biodiversity survey was funded by the Australian Consulate in Chennai. It not only documented several species but highlighted the importance of such an activity in understanding whether Bengaluru lakes are being developed in an ecologically sound manner. Dorekere is a 28-acre lake in the Uttarahalli suburb of South Bengaluru. The Bruhat Bengaluru Mahanagara Palike (BBMP) currently manages the lake. Earlier, it came under the purview of the Karnataka…