BBMP’s rainwater harvesting works stillborn

The city council allocated crores of rupees last year for rainwater harvesting at parks, playgrounds and BBMP buildings. What happened?

The monsoon rains are delayed this year. But by sheer coincidence, BBMP’s rainwater harvesting plans of last year remain unimplemented, almost as if the monsoons were granting their own extension to BBMP, ominously. What’s worse, a Citizen Matters inquiry revealed that the city’s accounts department declined to release funds due to the engineers’ lack of interest.

Bengaluru faces a shortage of 410 MLD (megalitre water per day) of water. The average rainfall here is 923 mms within a geographical area of 800 sq kms.  It is in this context by seeing the potential of RWH, BBMP made implementation of rainwater harvesting compulsory in all its offices, parks and playgrounds and allocated Rs 20 crores in 2011-12 budget. It also proposed to reserve 10 per cent of ward grant allocation to RWH. In addition to that, to encourage citizens, a two percent rebate in property tax also proposed in all the houses, which are having RWH units. This 2011-12 decision now seems utopia.

A BBMP official explaining how the newly installed RWH unit works.

Last month, when Citizen Matters spoke to Krishnaswamy K S, Executive Engineer of the RWH project, ahead of the nearly approaching monsoon season, he said, “We have not done any kind of works associated with RWH so far. But we have some plans and have started doing some work.” 

There is more. The 20 crore rupees allocated in the previous budget for RWH has been withheld by the BBMP Account Section due to the lackadaisical approach from the incharge engineers. The officers in-charge for RWH were supposed to submit the proposal details prior to the release of the money.

“The in-charge officers were supposed to do the site verification, tender allocation, project layout and so many other works prior to the release of the money. Nothing has been done so far. So the money has not been released,” said N V Subbanna, Chief Accounting officer BBMP.

B S Prasad, Chief Engineer for RWH at BBMP, declined to comment on the delay.

In the meantime, a new financial year has begun and the budgetary allocation of the previous year appears to have been forgotten.  Most of the flats, parks, playgrounds, offices, buildings in the city are still devoid of a RWH system.

RWH unit at BBMP head office is the biggest one.

Ironically, one RWH unit was installed at BBMP head office and at IPP (Indian Population Programme) Malleswaram office this year. Surprisingly, this project was not part of the BBMP RWH initiative. Executive Engineer L Chandrasekhar says, “The total cost of the project was Rs 35 lakhs. We have done all the works with our department money only. It does not have any connection with the 20 crore allocated for RWH in the budget.”

As our officials take a long stretch to plan and blame each other for the delay in starting the work, even the delayed monsoon rains may come and go. The city’s water problem will only be more severe in the coming days.

Comments:

  1. Shashidhar K. G. says:

    BBMP projects (east) have implemented two recharge wells in Richards Park (ward60) in 2011.This was an initiative of RTRA with the support of the local MLA Hon Prasanna Kumar.

    Shashidhar /RTRA-Richards Town Residents Association

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Story

முதல்வர் சீக்கிரம் அடிக்கல் நாட்ட வேண்டும் என்பதற்காக அறிவியல்  ஆய்வுகளைப் புறந்தள்ளுவதா?

CRZ clearance has been granted for a new drinking water reservoir in the naturally formed coastal salt marshes in Chengalpattu near Chennai.

செங்கல்பட்டு மாவட்டம், திருப்போரூர் மற்றும் திருக்கழுக்குன்றம் வட்டங்களுக்குட்பட்ட வருவாய் கிராமங்களில், இயற்கையாக அமைந்துள்ள கழுவேலி, உப்பங்கழி நீர்நிலையில், புதிய குடிநீர் நீர்த்தேக்கம் அமைக்க CRZ அனுமதி வழங்கியுள்ளது மாநில கடற்கரை ஒழுங்குமுறை மண்டல ஆணையம். இத்திட்டத்தின் முதல் கட்டத்தில் நெம்மேலி, கிருஷ்ணகாரனை, தண்டலம், பட்டிபுலம், திருப்போரூர், மாமல்லபுரம், சலுவான்குப்பம், பையனூர் ஆகிய வருவாய் கிராமங்களுக்குட்பட்ட 4375 ஏக்கர் பரப்பளவில் வருவாய்த்துறை, நீர்வளத்துறைக்குச் சொந்தமான இடங்களில் நீர்த்தேக்கம் அமைக்கத் திட்டமிடப்பட்டுள்ளது. 1.655TMC கொள்ளளவு கொண்ட இந்நீர்த்தேக்கம் மேற்கூறிய கிராமங்களைச் சேர்ந்த 50 ஆயிரத்துக்கும் மேற்பட்ட மக்களின் குடிநீர்த் தேவையைப் பூர்த்தி செய்யும் எனவும் அருகாமை கிராமங்களின் வெள்ள பாதிப்பைக் குறைக்கும் எனவும் அரசுத் தரப்பில் கூறப்படுகிறது. Map showing components of the Kovalam reservoir. Pic courtesy: Tamil Nadu Water Resources Department. இத்திட்டத்திற்கான விண்ணப்பத்தை 17.11.2025 அன்று  தொழில் நுட்ப  வல்லுநர் குழு பரிசீலித்தது. 20.11.2025 அன்று  மாநில கடற்கரை  மண்டல ஆணையம் விண்ணப்பத்தைை பரிசீலித்து CRZ அனுமதிக்கு பரிந்துரைக்கிறது.…

Similar Story

Buyers and sellers in Koyambedu Market face health risks from winter air pollution

IIT-M study records winter PM2.5 spike in Koyambedu market; stakeholders flag vehicular emissions and the need for hyperlocal data.

As sweater weather arrives, winter brings purple December flowers, fresh Ooty carrots with slivers of roots, and crisp Kashmiri apples to Chennai’s Koyambedu Wholesale Market Complex (KWMC). Much before dawn, workers unload crates of seasonal produce, and retailers vie for the best prices at Asia’s biggest market place for perishable goods. For the last 15 years, Murugan*, a parking personnel at the flower market's gate, has witnessed the coming and going of seasons, flowers, customers, and trucks. Most of all, he has seen the cityscape change with the addition of flyovers, bridges, cars, and metro construction. This December, a combination…